Home / Browse projects / Nagpur, Maharashtra / AADHAR NAGARI

Registered No litigation declared Residential / Group Housing project

AADHAR NAGARI

By MADHAV INFRA

RG-MH-70796 · RERA P50500023088 · Last updated on MahaRERA portal: 3 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 50 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 50 months from the original
31 of 99Construction stages doneacross 9 buildings; furthest along: Slabs of Super Structure, 35%
1Complaints at MahaRERAon this registration
Jump to the 178 documents Report an error

AADHAR NAGARI is a Residential / Group Housing project by MADHAV INFRA in Nagpur, Maharashtra, registered with MahaRERA as P50500023088 on 29 Nov 2019. Possession is promised by 31 Dec 2027. The completion date has moved by 50 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAADHAR NAGARI
  • TypeResidential / Group Housing
  • Location
    • WARDHA ROAD
    • KANHOLI
    • Hingna
    • Nagpur
    • 441108
  • Pincode441108
  • RERA no.P50500023088
  • ReraGenie IDRG-MH-70796

Builder

  • NameMADHAV INFRA
  • Entity typeOthers
  • ProprietorDEEPAK NILAWAR Nilawar

Key dates

this monthRegisteredNov 2019First promiseOct 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Nov 2019
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 28 Oct 2023)
  • Buildings9 building records
  • Documents filed178 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Row HouseNA31000
GokulNA66000
VrundavanNA77000
VedNA76000
AkshraNA76000
VasuNA76000
RADHEYNA66000
MAYURNA66000
KESHAV AND RIDDHISIDDHINA76000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building9

As on 3 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

31 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Slabs of Super Structure, at 35%.

Row House64%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Gokul29%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure15%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Vrundavan29%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Ved30%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Akshra29%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Vasu28%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RADHEY29%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
MAYUR29%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
KESHAV AND RIDDHISIDDHI29%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 3 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes90%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes30%
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
TEMPLEYes0%

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered9
Open Space9
BuildingClosed/CoveredOpen SpaceTotal
Row House112
Gokul112
Vrundavan112
Ved112
Akshra112
Vasu112
RADHEY112
MAYUR112
KESHAV AND RIDDHISIDDHI112

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area44,609 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMaharashtra Housing and Area Development Authority
Permissible FSI44609.0
Proposed, not sanctioned44,609 sq m
Buildings approved9
Buildings sanctioned9

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAMDASPETH NAGPUR

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPB Associates
EngineerSK Consultants & Engineers
Chartered AccountantVikas Abhang & Associates
Chartered AccountantPRANAV BHASKARAN & ASSOCIATES
PartnerRole in project
MADHAV INFRA-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500017903Oct 2023 → Oct 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

EXT50500024453Oct 2023 → Dec 2027

Reason as filed by the promoterI, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P50500023088.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12604348Rupesh Kanthuji HatitelMADHAV INFRA12/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Sep 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Sep 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Oct 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Sep 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed178

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 178 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 - Aadhar Nagari as on March 2026.pdf3 Jul 2026
Form 2File: Form 2 - Aadhar Nagari as on March 2026.pdf3 Jul 2026
Form 3File: Form 3 - Aadhar Nagari as on March 2026.pdf3 Jul 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Aadhar Nagari as on March 2026.pdf3 Jul 2026
Form 1File: Form 1- Aadhar Nagari as on 31st Dec 2025.pdf26 May 2026
Form 2File: Form 2 - Aadhar Nagari as on 31st Dec 2025.pdf26 May 2026
Form 3File: Form 3- Aadhar Nagari as on 31st Dec 2025.pdf26 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Aadhar Nagari as on 31st Dec 2025.pdf26 May 2026
Form 1File: Form 1 - Aadhar Nagari as on Sep 2025.pdf25 Nov 2025
Form 2File: Form 2 - Aadhar Nagari as on Sept 2025.pdf25 Nov 2025
Form 3File: Form 3 - Aadhar Nagari as on Sep 2025.pdf25 Nov 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Aadhar Nagari as on Sep 2025.pdf25 Nov 2025
Form 1File: Form 1 - Aadhar Nagari as on March 2025.pdf26 Sep 2025
Form 2File: Form 2 - Aadhar Nagari as on March 2025.pdf26 Sep 2025
Form 3File: Form 3 - Aadhar Nagari as on March 2025.pdf26 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Aadhar Nagari as on March 2025.pdf26 Sep 2025
Form 1File: Form 1 - Aadhar Nagari as on June 2025.pdf20 Sep 2025
Form 2File: Form 2 - Aadhar Nagari as on June 2025.pdf20 Sep 2025
Form 3File: Form 3 - Aadhar Nagari as on June 2025.pdf20 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Aadhar Nagari as on June 2025.pdf20 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aadhar Nagari - Form 1 March 2025.pdf30 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 March 2020.pdf30 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 March 2021.pdf30 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 March 2022.pdf30 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 March 2023.pdf30 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 March 2024.pdf30 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 June 2024.pdf30 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 September 2024.pdf30 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 December 2024.pdf30 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 March 2025.pdf30 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 March 2020.pdf30 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 March 2025.pdf30 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 December 2024.pdf30 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 September 2024.pdf30 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 June 2024.pdf30 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 March 2024.pdf30 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 March 2023.pdf30 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 March 2022.pdf30 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 March 2021.pdf30 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Aadhar Nagari - Form 5 FY 2023-24.pdf30 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Aadhar Nagari - Form 5 FY 2023-24.pdf30 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aadhar Nagari - Form 1 March 2020.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aadhar Nagari - Form 1 March 2021.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aadhar Nagari - Form 1 March 2022.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aadhar Nagari - Form 1 March 2023.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aadhar Nagari - Form 1 March 2024.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aadhar Nagari - Form 1 June 2024.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aadhar Nagari - Form 1 September 2024.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aadhar Nagari - Form 1 December 2024.pdf10 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 16 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf10 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 June 2024_11zon.pdf10 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 September 2024_11zon.pdf10 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aadhar Nagari - Form 3 December 2024_11zon.pdf10 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 16 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf10 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 June 2024.pdf10 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 September 2024.pdf10 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aadhar Nagari - Form 2 December 2024.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Aadhar Nagari as on June 2024.pdf11 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Aadhar Nagari as on Sep 2024.pdf11 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Aadhar Nagari as on Dec 2024.pdf11 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Aadhar Nagari as on June 2024.pdf11 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Aadhar Nagari as on Sep 2024.pdf11 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Aadhar Nagari as on Dec 2024.pdf11 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Aadhar Nagari as on June 2024.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Aadhar Nagari as on Sep 2024.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Aadhar Nagari as on Dec 2024.pdf3 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Adobe Scan 05 Aug 2024 (1) (1)_compressed.pdf5 Aug 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf1 Aug 2024
Declaration in FORM BFile: Form B (Affidavit cum Declaration).pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 23_11zon.pdf30 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 24.pdf30 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf30 Jul 2024
CERSAI detailsFile: CERSAI Declaration.pdf30 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar 24_11zon.pdf30 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (1).pdf30 Jul 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A - Seperate Bank Account Details.pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 as on 31-12-2023.pdf4 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: June 2022_compressed.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sept 2022_compressed.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 2022_compressed.pdf28 Feb 2024

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one moved by 50 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AADHAR NAGARI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANHOLI2,800+ in Nagpur

Builder: MADHAV INFRA

MADHAV INFRA has 1 registration on MahaRERA, including AADHAR NAGARI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if AADHAR NAGARI is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AADHAR NAGARI?

The registered promoter entity is MADHAV INFRA, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AADHAR NAGARI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AADHAR NAGARI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AADHAR NAGARI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AADHAR NAGARI?

The professionals named in the filing: Architect: PB Associates; Engineer: SK Consultants & Engineers; Chartered Accountant: Vikas Abhang & Associates; Chartered Accountant: PRANAV BHASKARAN & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AADHAR NAGARI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AADHAR NAGARI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AADHAR NAGARI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.