ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / 99 SILVER OAKS

Registered Litigation declared Others project

99 SILVER OAKS

By BOMBAY CONSTRUCTION & INFRAPROJECTS PVT LTD

RG-MH-07341 · RERA P51700076739 · Last updated on MahaRERA portal: 31 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 6 cases
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2033Possession promisedmoved 24 months from the original
1 of 9Construction stages donefurthest along: Plinth, 0%
105 of 108Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

99 SILVER OAKS is a Others project by BOMBAY CONSTRUCTION & INFRAPROJECTS PVT LTD in Raigarh, Maharashtra, registered with MahaRERA as P51700076739 on 25 Jun 2024. Possession is promised by 31 Dec 2033. The completion date has moved by 24 months from the original filing. 3 of the 108 units on this registration are recorded sold or booked, and 1 of 9 construction stages are filed complete.

At a glance

Project

  • Name99 SILVER OAKS
  • TypeOthers
  • Location
    • PLOT NO 30
    • SECTOR 9
    • ULWE
    • NAVI MUMBAI
    • ULWE
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700076739
  • ReraGenie IDRG-MH-07341

Builder

  • NameBOMBAY CONSTRUCTION & INFRAPROJECTS PVT LTD
  • Entity typeCompany
  • DirectorsLalitkumar Somdutt Nagpal, Kapil Lalitkumar Nagpal
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2024First promiseDec 2031Revised toDec 2033

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Jun 2024
  • Promised completion31 Dec 2033
  • Revised completionRevised to 31 Dec 2033 (originally 31 Dec 2031)
  • Buildings1 building record
  • Documents filed79 files

Current status

3%3 of 108 units booked
3.9%Work done, per cost certificate

Figures as on 31 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
99 SILVER OAKSNA16151026108

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 9 construction stages are filed complete. The stage furthest along is Plinth, at 0%.

99 SILVER OAKS: 11% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNo0%
Community BuildingsNo0%
Treatment And Disposal Of Sewage And Sullage WaterNo0%
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNo0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed126

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots126
Closed/Covered126

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,249 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Jul 2025
LandownerVillageDistrict
LALIT KUMAR SOMDUTT NAGPALChemburMumbai Suburban

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI10808.1
Proposed, not sanctioned10,808 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO C/20, OPP M WEST WARD, BMC OFFICE, CHEMBUR, MUMBAI
Estimated costRs 52.00 cr
Cost incurredRs 2.04 cr
Work done3.92%
BuildingWingEstimatedIncurred
99 SILVER OAKSNARs 47.36 crRs 2.04 cr
-NARs 4.64 cr-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHiten Sethi & Associates
EngineerStructural Concept Designs Pvt Ltd
EngineerS G AMBOLE
Chartered AccountantDeepak H. Padachh & Co.
Chartered AccountantP J JAIN & ASSOCIATES
Chartered AccountantLILANI & CO
Chartered AccountantDEEPAK H PADACHH & CO
PartnerRole in project
BOMBAY CONSTRUCTION & INFRAPROJECTS PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA25052621080Dec 2031 → Dec 2033

Reason as filed by the promoterThe Promoter has registered project as per originally sanctioned Plans. Further due to changes in DP Rules and the Promoter decided to change the sanctioned plans as per the revised DP Rules. The Promoter in the case has delayed the project due to delay in receipt of the revised approvals.

Litigation declared6

CaseCourtStatus
65/2012Panvel Court Senior DivisionEvidence Compliance Issues
357/2012Panvel Court Senior DivisionEvidence Compliance Issues
345/2021Panvel Court Senior DivisionArgument on Exhibit
65/2012Panvel Court Senior DivisionEvidence Compliance Issues
264/2009Panvel Court Senior DivisionEvidence Compliance Issues
345/2021Panvel Court Senior DivisionArgument on Exhibit

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Mar 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2033

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form1_30062026.pdf31 Jul 2026
Withdrawal Update Form 2File: Form 2_ Engineers Certificate300626.pdf31 Jul 2026
Withdrawal Update Form 3File: Form 3_C A Certificate 30062026.pdf31 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold-Unsold List.pdf7 May 2026
Form 1File: Architect Certificate (1).pdf7 May 2026
Form 2File: Engineers Certificate.pdf7 May 2026
Form 3File: Form 3.pdf7 May 2026
Withdrawal Update Form 1File: Form - 1 Architects Certificate.pdf7 May 2026
Withdrawal Update Form 2File: Form - 2 Engineers Certificate.pdf7 May 2026
Withdrawal Update Form 3File: Form - 3 CA Certificate.pdf7 May 2026
Form 5 (FY 2024-2025)File: Form 5.pdf7 May 2026
Building plan approvalFile: 1-4.pdf25 Mar 2026
Building plan approvalFile: 5-9.pdf25 Mar 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate 31-12-2025.pdf24 Mar 2026
Withdrawal Update Form 2File: Form 2 - Engineers Certificate 31-12-2025.pdf24 Mar 2026
Withdrawal Update Form 3File: Form 3 - C A Certificate 31-12-2025.pdf24 Mar 2026
Form 1File: Form 1 - Architects Certificate 31-12-2024.pdf6 Nov 2025
Form 2File: Form 2 - Engineers Certificate 31-12-2024.pdf6 Nov 2025
Form 3File: Form 3 - CA Certificate 31-12-2024.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold Inventory 31-12-2024.pdf6 Nov 2025
Form 1File: Form 1 - ARCHITECTS CERTIFICATE 30-09-24.pdf6 Nov 2025
Form 2File: Form 2 - ENGINEERS CERTIFICATE 30-09-24.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold Inventory 30-09-2024.pdf6 Nov 2025
Form 3File: Form 3 - C A CERTIFICATE 30-09-24-.pdf6 Nov 2025
Form 2A (FY 2024-2025)File: Form - 2A i.e. Annexure - C_Site Supervisors Certificate.pdf6 Nov 2025
Form 1File: Form 1 - Architect Certificate 31-03-2025.pdf5 Nov 2025
Form 2File: Form 2 - Engineers Certificte 31-03-2025.pdf5 Nov 2025
Form 3File: Form 3 - C A Certificae 31-03-2025.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold_Unsold Inventory 31-3-2025.pdf5 Nov 2025
Withdrawal Update Form 1File: Form 1 - Architect Certificate 30-09-25.pdf5 Nov 2025
Withdrawal Update Form 2File: Form 2 - Engineers Certificate - 30-09-25.pdf5 Nov 2025
Withdrawal Update Form 3File: Form 3 - C A Certificate - 30-09-25.pdf5 Nov 2025
Withdrawal Update Form 1File: Form 1 - Architectu0027s Certificate 30-06-2025.pdf22 Jul 2025
Withdrawal Update Form 2File: Form 2 - Engineeru0027s Certificate 30-06-2025.pdf22 Jul 2025
Withdrawal Update Form 3File: Form 3 - C A Certificate 30-06-2025.pdf22 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architects Certificate 31-12-2024.pdf15 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate 31-12-2024.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate 31-12-2024.pdf15 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - ARCHITECTS CERTIFICATE 30-09-24.pdf21 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - C A CERTIFICATE 30-09-24_compressed.pdf21 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ENGINEERS CERTIFICATE 30-09-24_compressed.pdf21 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 18062024.pdf20 Jun 2024
CERSAI detailsFile: No CERSAI declaration 15062024.pdf15 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Bank account disclosure15062024.pdf15 Jun 2024
Proforma of Agreement for saleFile: RERA AFS -08-04-2024.pdf19 Apr 2024
Other - LegalFile: Agreement to Lease-CIDCO-1.pdf19 Apr 2024
Other - LegalFile: Agreement to Lease-CIDCO-2.pdf19 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Email to Maharera from CIDCO.pdf8 Apr 2024
Proforma of Allotment letterFile: 1 Proforma of Allotment letter.pdf8 Apr 2024
Details of encumbrances concerned to FinanceFile: Legal Encumbrances Declaration210324.pdf22 Mar 2024
Details of encumbrances concerned to LegalFile: Legal Encumbrances Declaration210324.pdf22 Mar 2024
Declaration in FORM BFile: Form B - Bombay Construction (Color).pdf22 Mar 2024
Other - LegalFile: Tripartite Agreement Sector 9, Ulwe.pdf22 Mar 2024
Other - TechnicalFile: Declaration - Order No 50.pdf22 Mar 2024
Building plan approvalFile: PROFORMA - 1.pdf1 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: PROFORMA - 1.pdf1 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Corrigendum Letter.pdf29 Feb 2024
CERSAI detailsFile: Cersai Page 1.pdf29 Feb 2024
CERSAI detailsFile: Cersai Page 2.pdf29 Feb 2024
Deviation Report with respect to Allotment letterFile: Deviation Sheet - Allotment letter.pdf29 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Sheet - Agreement - Final.pdf29 Feb 2024
Layout approvalFile: No Layout Declaration.pdf13 Feb 2024
Building plan approvalFile: 1) FINAL CIDCO Approved Plan - Part1.pdf13 Feb 2024
Building plan approvalFile: 1) FINAL CIDCO Approved Plan - Part2.pdf13 Feb 2024
Copy of the legal title reportFile: Legal Title Report - Format A.pdf13 Feb 2024
Copy of Layout Approval (in case of layout)File: No Layout Declaration.pdf13 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 1) FINAL CIDCO Approved Plan - Part1.pdf13 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 1) FINAL CIDCO Approved Plan - Part2.pdf13 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - KRN.pdf12 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - RN.pdf12 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - LN.pdf12 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - KN.pdf12 Feb 2024
PAN CardFile: PAN CARD.pdf7 Feb 2024
Details of encumbrances concerned to FinanceFile: 1) Declaration for Encumbrances.pdf7 Feb 2024
Details of encumbrances concerned to FinanceFile: Financial Encumbrances Declaration210324.pdf7 Feb 2024
Details of encumbrances concerned to LegalFile: 1) Declaration for Encumbrances.pdf7 Feb 2024
Details of encumbrances concerned to LegalFile: Financial Encumbrances Declaration210324.pdf7 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: 2) FINAL Commencement Certificate dt 12-09-2023.pdf7 Feb 2024
Declaration about Commencement CertificateFile: 4) Declaration for CC.pdf7 Feb 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Kritika JewelsPlot No 48 Sector No 18 P Ulwe Node Ulwe Navi Mumbai 410206134CompletedJun 2013Late, May 2017

How this compares with Raigarh

3%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 24 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 99 SILVER OAKS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ULWE5,900+ in Raigarh

2 km99 SILVER OAKSCompleted 129Lapsed / revoked 38Other 116Dot size: filed unitsN

Filed coordinates, straight-line distance. 283 registered projects within 2 km.

Builder: BOMBAY CONSTRUCTION & INFRAPROJECTS PVT LTD

BOMBAY CONSTRUCTION & INFRAPROJECTS PVT LTD has 2 registrations on MahaRERA, including Sahil Exotica and 99 SILVER OAKS. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if 99 SILVER OAKS is delayed beyond 31 Dec 2033?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 99 SILVER OAKS?

The registered promoter entity is BOMBAY CONSTRUCTION & INFRAPROJECTS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 99 SILVER OAKS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for 99 SILVER OAKS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 99 SILVER OAKS?

The professionals named in the filing: Architect: Hiten Sethi & Associates; Engineer: Structural Concept Designs Pvt Ltd; Engineer: S G AMBOLE; Chartered Accountant: Deepak H. Padachh & Co.; Chartered Accountant: P J JAIN & ASSOCIATES; Chartered Accountant: LILANI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 99 SILVER OAKS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 99 SILVER OAKS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 99 SILVER OAKS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.