ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / 55 HAPPYNEST

Registered No litigation declared Residential / Group Housing project

55 HAPPYNEST

By Rupesh Prakashchand Mutha

RG-MH-29990 · RERA P51500052128 · Last updated on MahaRERA portal: 29 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Jun 2028Possession promisedmoved 24 months from the original
45 of 77Construction stages doneacross 7 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
50 of 55Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 127 documents Report an error

55 HAPPYNEST is a Residential / Group Housing project by Rupesh Prakashchand Mutha in Aurangabad, Maharashtra, registered with MahaRERA as P51500052128 on 24 Jul 2023. Possession is promised by 30 Jun 2028. The completion date has moved by 24 months from the original filing. 5 of the 55 units on this registration are recorded sold or booked, and 45 of 77 construction stages are filed complete.

At a glance

Project

  • Name55 HAPPYNEST
  • TypeResidential / Group Housing
  • Location
    • Sawangi Road
    • Sundarwadi
    • Aurangabad
    • 431007
  • Pincode431007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500052128
  • ReraGenie IDRG-MH-29990

Builder

  • NameRupesh Prakashchand Mutha
  • Entity typeIndividual

Key dates

this monthRegisteredJul 2023First promiseJun 2026Revised toJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Jul 2023
  • Promised completion30 Jun 2028
  • Revised completionRevised to 30 Jun 2028 (originally 30 Jun 2026)
  • Buildings7 building records
  • Documents filed127 files

Current status

9%5 of 55 units booked
76.0%Work done, per cost certificate

Figures as on 29 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA3311011
Building BNA3310010
Building CNA33909
Building DNA33808
Building ENA33808
Building FNA33808
Building GNA22101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 29 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

45 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

Building A27%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building B11%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth20%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building D90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building E90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building F35%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building G91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes55%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes70%
Street LightingYes70%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes70%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes55%
Open ParkingNoNot applicable

Parking filed55

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots55
Closed/Covered55
BuildingClosed/CoveredTotal
Building A1111
Building B1010
Building C99
Building D88
Building E88
Building F88
Building G11

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,644 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jun 2025

Approvals and building plan

Sanctioning authorityCIDCO Aurangabad
Permissible FSI8411.95
Proposed, not sanctioned7,412 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNear Prozone Mall, MIDC Chikalthana Auranagabad
Estimated costRs 18.80 cr
Cost incurredRs 14.28 cr
Work done75.96%
BuildingWingEstimatedIncurred
Building ANARs 2.57 crRs 1.95 cr
Building BNARs 2.57 crRs 1.95 cr
Building CNARs 2.57 crRs 1.95 cr
Building DNARs 2.57 crRs 1.95 cr
Building ENARs 2.57 crRs 1.95 cr
Building FNARs 2.57 crRs 1.95 cr
Building GNARs 2.57 crRs 1.95 cr
-NARs 80.00 lakhRs 60.00 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRahul Thole
EngineerNiranjan Muley
EngineerPramod Mungikar
Chartered AccountantCA Narendra Navandar
Chartered AccountantLathi and Tapdiya
Chartered AccountantD GABSS & Associates
PartnerRole in project
Rupesh Prakashchand Mutha-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA01072501904Jun 2026 → Jun 2028

Reason as filed by the promoterFinancial Slowdown and Market Conditions: The real estate sector faced an economic slowdown and poor market response, which impacted sales and affected cash flows required for seamless project execution.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed127

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1 JUN 26.pdf29 Jul 2026
Withdrawal Update Form 2File: FORM-2 JUN 26.pdf29 Jul 2026
Withdrawal Update Form 3File: FORM-3 JUN 26.pdf29 Jul 2026
Withdrawal Update Form 1File: FORM-1 Mar 26.pdf29 Apr 2026
Withdrawal Update Form 2File: FORM-2 Mar 26.pdf29 Apr 2026
Withdrawal Update Form 3File: FORM-3 Mar 26 (O).pdf29 Apr 2026
Form 2A (FY 2023-2024)File: FORM 2A 23-24 signed.pdf14 Mar 2026
Form 2A (FY 2024-2025)File: FORM 2A 24-25.pdf14 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 24-25 signed.pdf2 Mar 2026
Withdrawal Update Form 1File: 55 HN FORM 1 DEC 25.pdf23 Jan 2026
Withdrawal Update Form 2File: 55 HN FORM 2 DEC 25.pdf23 Jan 2026
Withdrawal Update Form 3File: 55 HN FORM-3 DEC 25.pdf23 Jan 2026
Withdrawal Update Form 1File: 1 Form-1 Jun 25.pdf3 Dec 2025
Withdrawal Update Form 1File: 1 Form-1 Sep 25.pdf3 Dec 2025
Withdrawal Update Form 1File: 1 Form-1 Sep 25.pdf3 Dec 2025
Withdrawal Update Form 2File: 55 hAPPY Form 2 Mar 24.pdf3 Dec 2025
Withdrawal Update Form 2File: 2 Form-2 Sep 25.pdf3 Dec 2025
Withdrawal Update Form 2File: 2 Form-2 Sep 25.pdf3 Dec 2025
Withdrawal Update Form 3File: 3 Form-3 Jun 25.pdf3 Dec 2025
Withdrawal Update Form 3File: 3 Form-3 Sep 25.pdf3 Dec 2025
Withdrawal Update Form 3File: 3 Form-3 Sep 25.pdf3 Dec 2025
Form 1File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf28 Jun 2025
Form 2File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Jun 2025
Form 3File: 2 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf28 Jun 2025
OthersFile: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf28 Jun 2025
Form 1File: 2 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf28 Jun 2025
Form 2File: 2 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Jun 2025
Form 3File: 3 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: 2 Disclosure of sold_ booked inventory.pdf28 Jun 2025
OthersFile: From no-2A Rupesh Mutha Dt-06-01-2024.pdf28 Jun 2025
Form 1File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf28 Jun 2025
Form 2File: 3 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Jun 2025
Form 3File: 4 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory.pdf28 Jun 2025
OthersFile: 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf28 Jun 2025
Form 1File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf28 Jun 2025
Form 2File: Form -2 jun 24.pdf28 Jun 2025
Form 3File: 5 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure of sold_ booked inventory.pdf28 Jun 2025
OthersFile: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf28 Jun 2025
Form 1File: 5 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf28 Jun 2025
Form 2File: form 2 sep 24.pdf28 Jun 2025
Form 3File: 6 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Mahavir Infra Disclosuse of sold sep24.pdf28 Jun 2025
OthersFile: Form - 2A Rupesh Mutha Dt-10-10-2025_0001.pdf28 Jun 2025
Form 1File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf28 Jun 2025
Form 2File: 4 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Jun 2025
Form 3File: 7 CA Certificate on Project Cost & Fund withdrawal (Form 3) (1).pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Mhavir Infra Disclosure Of Sold dec 24.pdf28 Jun 2025
OthersFile: Form - 2A Rupesh Mutha Dt-10-01-2025_0001.pdf28 Jun 2025
Form 1File: 7 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf28 Jun 2025
Form 2File: Form 2Emginners Certificate_0001.pdf28 Jun 2025
Form 3File: CA Certificate Rupesh Mutha 55 Happynest Dt-18-04-2025_0001.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Mahavir Infra Disclosuse of sold mar 25.pdf28 Jun 2025
OthersFile: Form - 2A Rupesh Mutha Dt-10-04-2025_0001.pdf28 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architech Certificate_MARCH25.pdf3 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A Rupesh Mutha Dt-20-10-2024_0001.pdf3 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A Rupesh Mutha Dt-20-1-25_0001.pdf3 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A RUPESH MUTHA DT18-04-2025.pdf3 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 To Rupesh Mutha Dt-02-05-2025_0001.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form no 1 of Rupesh Mutha_D20-10-2024.pdf22 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form no 1 of Rupesh Mutha_20-01-2025.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form no 2 of Rupesh Mutha_0001.pdf22 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-31-12-2024_0001.pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From no-3 Dt-30-09-2024 of Rupesh Mutha_0001.pdf30 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate (1).pdf1 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineering Certificate Form 2 A.pdf1 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate of Rupesh Mutha 30-06-2024_0001.pdf1 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclosure (1).pdf25 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 55 hAPPY Form 2 Mar 24.pdf18 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate of Happynest MAR24.pdf4 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A Rupesh Mutha_0001.pdf27 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure Sold Book 55 Happynest.pdf27 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 55 happynest report 20 04.pdf25 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of 55 Happynest dt30-09-23_0001.pdf6 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of 55 Happynest dt31-12-23_0001.pdf6 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 of Rupesh Mutha Dt-30-09-2023__0001.pdf2 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 of Rupesh Mutha Dt-31-12-2023_0001.pdf2 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A of Rupesh Mutha Dt-05-10-2023.pdf22 Jan 2024

How this compares with Aurangabad

9%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 24 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep 55 HAPPYNEST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sundarwadi1,400+ in Aurangabad

2 km55 HAPPYNESTCompleted 1Lapsed / revoked 1Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: Rupesh Prakashchand Mutha

Rupesh Prakashchand Mutha has 1 registration on MahaRERA, including 55 HAPPYNEST. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if 55 HAPPYNEST is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 55 HAPPYNEST?

The registered promoter entity is Rupesh Prakashchand Mutha, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 55 HAPPYNEST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for 55 HAPPYNEST?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 55 HAPPYNEST?

The professionals named in the filing: Architect: Rahul Thole; Engineer: Niranjan Muley; Engineer: Pramod Mungikar; Chartered Accountant: CA Narendra Navandar; Chartered Accountant: Lathi and Tapdiya; Chartered Accountant: D GABSS & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 55 HAPPYNEST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 55 HAPPYNEST. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 55 HAPPYNEST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.