Home / Developers / SWAPNALOK DEVELOPERS

SWAPNALOK DEVELOPERS: RERA track record

Others ยท attribution by exact filing name, entity resolution in progress

SWAPNALOK DEVELOPERS has 7 registrations in this build, including Swapnalok Nagari Building no. 34,35,36,37 and Swapnalok Township Amenity Building. Its filings disclose 8 earlier MahaRERA projects: 6 of 7 past projects completed on time. Litigation is declared on 2 of its registrations.

7Registrations in this build
8Past projects disclosed
on timeMedian delivery slip
2Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Swapnalok Nagari Building no. 34,35,36,37Pune, Maharashtra--Completed
Swapnalok Township Amenity BuildingPune, Maharashtra4657%Registered
SWAPNALOK NAGARI PLOTSPune, Maharashtra1963%Completed
Swapnalok Nagari Commercial BuildingPune, Maharashtra--Completed
Swapnalok Nagari, Building No -3Pune, Maharashtra--Completed
SWAPNALOK NAGARI, BHOR, BUILDING NO. 4Pune, Maharashtra--De-registered
SWAPNALOK DEVELOPERS, SWAPNALOK NAGARI BHOR,- PLOTS -PHASE 2Pune, Maharashtra4667%Completed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Swapnalok Nagri Building no 38 to 56
30 Apr 201729 Apr 2017On time
Swapnalok Nagari Building no. 34,35,36,37
P52100001827
31 Dec 20188 Oct 2018On time
SWAPNALOK NAGARI PLOTS
P52100018545
31 Mar 201912 May 2021+25 months
Swapnalok Nagari Commercial Building
P52100017103
30 Jun 20241 Nov 2021On time
Swapnalok Nagari, Building No -3
P52100017102
30 Jun 20241 Nov 2021On time
SWAPNALOK DEVELOPERS, SWAPNALOK NAGARI BHOR,- PLOTS -PHASE 2
P52100052233
31 Dec 202416 Jan 2024On time
Swapnalok Township Amenity Building
P52100004288
30 Jun 2026Not completed yetOngoing
SWAPNALOK NAGARI, BHOR, BUILDING NO. 4
P52100033872
31 Dec 20272 Jun 2023On time

Frequently asked questions

How do I verify SWAPNALOK DEVELOPERS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with SWAPNALOK DEVELOPERS?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make SWAPNALOK DEVELOPERS unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.