SAMARPAN HOMES & DEVELOPERS: RERA track record
GSTIN 27ADIFS1401J1Z6 · Partnership · attribution by exact filing name, entity resolution in progress
SAMARPAN HOMES & DEVELOPERS has 13 registrations on MahaRERA, including BORIVALI OM APARTMENT CO-OP HSG SOCIETY LTD and RAM DUTT CO-OPERATIVE HOUSING SOCIETY LTD. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Litigation is declared on 2 of its registrations.
Projects by this developer
Showing all 13 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| ANAND CO-OPERATIVE HOUSING SOCIETY LTD BUILDING NO 2P51800055685 | BORIVALI (EAST), Mumbai Suburban, 400066 | 140 | 15% | 8 Apr 2024 | Registered |
| SAMARPAN SANKALPP51800054977 | AT JAYA NAGAR, BORIVALI (EAST), Mumbai Suburban, 400066 | 125 | 40% | 21 Feb 2024 | Registered |
| ASHTALAKSHMI PARRADISE CHSLPM1180002503081 | Malad, Mumbai Suburban, 400064 | 124 | 0% | 31 Mar 2026 | Registered |
| GOLDMIST CO-OPERATIVE HOUSING SOCIETY LIMITEDP51800054965 | KANDIVALI (EAST), Mumbai Suburban, 400101 | 93 | 17% | 21 Feb 2024 | Registered |
| OM SHRI JAGANNATH CHSLP51800054351 | BORIVALI (W), Mumbai Suburban, 400092 | 74 | 14% | 15 Jan 2024 | Registered |
| Sambhav Darshan Purshottam Park CO-OPERATIVE HOUSING SOCIETY LTDPM1180002500277 | BORIVALI EAST, Mumbai Suburban, 400066 | 69 | 0% | 16 Jul 2025 | Registered |
| SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITEDP51800079662 | BORIVALI EAST, Mumbai Suburban, 400066 | 60 | 15% | 20 Mar 2025 | Registered |
| MEGH MAHAL CHSLPM1180002500265 | BORIVALI EAST, Mumbai Suburban, 400066 | 25 | 0% | 14 Jul 2025 | Registered |
| ANURAJ CO-OPERATIVE HOUSING SOCIETY LIMITEDP51800046877 | BORIVALI EAST, Mumbai Suburban, 400066 | - | - | 16 Sep 2022 | Completed |
| BORIVALI OM APARTMENT CO-OP HSG SOCIETY LTDP51800025172 | BORIVALI EAST, Mumbai Suburban, 400066 | - | - | 20 Mar 2020 | Registration lapsed |
| HIRANMAY NIWAS CO-OPERATIVE HOUSING SOCIETY LIMITEDP51800050518 | BORIVALI EAST, Mumbai Suburban, 400066 | - | - | 17 Apr 2023 | Completed |
| NIKUNJ VIHAR CO-OPERATIVE HOUSING SOCIETY LIMITEDP51800047603 | BORIVALI EAST, Mumbai Suburban, 400066 | - | - | 14 Nov 2022 | Completed |
| RAM DUTT CO-OPERATIVE HOUSING SOCIETY LTDP51800027648 | BORIVALI EAST, Mumbai Suburban, 400066 | - | - | 25 Dec 2020 | Completed |
What this promoter declares as its own experience
SAMARPAN HOMES & DEVELOPERS declares experience on 3 earlier projects. 3 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
3 of these declarations can be compared with the dates those projects' own registrations hold. On 1, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. It changes nothing about whether that project was delivered on time.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| OM SHRI JAGANNATH CHSL P51800054351 | 31 Dec 2026 | Not completed yet | Ongoing |
| GOLDMIST CO-OPERATIVE HOUSING SOCIETY LIMITED P51800054965 | 31 Dec 2026 | Not completed yet | Ongoing |
| ANAND CO-OPERATIVE HOUSING SOCIETY LTD BUILDING NO 2 P51800055685 | 31 Dec 2026 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify SAMARPAN HOMES & DEVELOPERS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27ADIFS1401J1Z6 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SAMARPAN HOMES & DEVELOPERS?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make SAMARPAN HOMES & DEVELOPERS unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.