New projects and RERA data in Osmanabad district, Maharashtra

47 of the projects in this build are in Osmanabad district: 1,999 units across them, 0 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.

47Projects in this build
0Registered, last 12 months
1,999Units declared
1,121Units not yet booked
4Completion dates revised
0With declared litigation

Of the 47 covered registrations, 4 have revised their promised completion date and 0 declare litigation. The median project here is 17% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.

When Osmanabad projects promise possession

Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 47 projects with a promised date, 29 are recorded delivered, 6 are still on the register and 12 have a registration that has lapsed or been cancelled.

DeliveredOn the registerRegistration lapsed or cancelled

025710today2017: 1 projects, delivered’172018: 4 projects, delivered’182019: 6 projects, delivered’192020: 5 projects, delivered’202021: 2 projects, delivered’212022: 3 projects, delivered2022: 2 projects, registration lapsed or cancelled’222023: 3 projects, delivered2023: 2 projects, registration lapsed or cancelled’232024: 1 projects, delivered2024: 3 projects, registration lapsed or cancelled’242025: 4 projects, delivered2025: 3 projects, registration lapsed or cancelled’252026: 2 projects, registration lapsed or cancelled’262027: 5 projects, on the register’272029: 1 projects, on the register’29

8 projects promise possession in 2026 or later. Facts as per filings on RERA website.

02505007501,000today2017: 38 flats, delivered’172018: 577 flats, delivered’182019: 186 flats, delivered (only 2 of 6 projects filed a flat count)’192020: 62 flats, delivered (only 2 of 5 projects filed a flat count)’20’21’22’23’242025: 170 flats, delivered2025: 43 flats, registration lapsed or cancelled’25’262027: 923 flats, on the register (only 2 of 5 projects filed a flat count)’27’29

923 flats are promised in 2026 or later, across the 25% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Facts as per filings on RERA website.

How far Osmanabad possession dates have moved

Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 4 of 47 projects (9%) have moved at least once; the median move is 13 months and the longest is 31 months.

Kept the original dateMoved by under 2 yearsMoved by 2 years or more

025710Originally due 2017: 1 projects kept the original date, 100% of the year’17Originally due 2018: 4 projects kept the original date, 100% of the year’18Originally due 2019: 6 projects kept the original date, 100% of the year’19Originally due 2020: 5 projects kept the original date, 100% of the year’20Originally due 2021: 2 projects kept the original date, 100% of the year’21Originally due 2022: 5 projects kept the original date, 100% of the year’22Originally due 2023: 5 projects kept the original date, 100% of the year’23Originally due 2024: 4 projects kept the original date, 67% of the yearOriginally due 2024: 2 projects moved by under 2 years, 33% of the year’24Originally due 2025: 4 projects kept the original date, 67% of the yearOriginally due 2025: 1 projects moved by under 2 years, 17% of the yearOriginally due 2025: 1 projects moved by 2 years or more, 17% of the year’25Originally due 2026: 2 projects kept the original date, 100% of the year’26Originally due 2027: 4 projects kept the original date, 100% of the year’27Originally due 2029: 1 projects kept the original date, 100% of the year’29

Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

05001,0001,5002,000Originally due 2017: 38 flats kept the original date, 100% of the year’17Originally due 2018: 577 flats kept the original date, 100% of the year’18Originally due 2019: 186 flats kept the original date, 100% of the year (only 2 of 6 projects filed a flat count)’19Originally due 2020: 62 flats kept the original date, 100% of the year (only 2 of 5 projects filed a flat count)’20’21’22’23Originally due 2024: 99 flats moved by under 2 years, 33% of the year (only 2 of 6 projects filed a flat count)’24Originally due 2025: 104 flats kept the original date, 67% of the yearOriginally due 2025: 10 flats moved by under 2 years, 17% of the yearOriginally due 2025: 899 flats moved by 2 years or more, 17% of the year’25’26Originally due 2027: 24 flats kept the original date, 100% of the year (only 1 of 4 projects filed a flat count)’27’29

Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

Projects in Osmanabad

ProjectDeveloperUnits BookedRegistered
RSM DHARASHIV SHELTERS- OSMANABAD PROJECTRSM DHARASHIV SHELTERS89949%26 Jun 2021
Chhoriya Township Plotting Layout ParandaPragati Infra Services Pvt. Ltd.25381%22 Aug 2017
R M Dhariwal Township Bhoom PlottingDhariwal And Chhoriya Buildcon Pvt Ltd21156%27 Aug 2017
Vidhyanagar Bunglow PlottingVidhyanagar Bunglow Plotting Prop Mrs Vidhya P Chavan1041%16 May 2024
R M Dhariwal Township Tuljapur PlottingDhariwal And Chhoriya Buildcon Pvt Ltd9649%22 Aug 2017
SHANTADEVI HOMESSANJAY BHASKARRAO CHALUKYA9017%17 Aug 2017
Shivaji NagarVikram Venkatrao Gaikwad8516%1 Sep 2017
PRAGATI TOWERSHALIMAR CONSTRUCTIONS5620%22 Sep 2023
VrundavanGautam Limbraj Wayse430%15 Jun 2022
SHREE SAMARTH KRUPA NAGARSAINATH VENKATRAO PISKE3826%23 Aug 2017
SHIVRAI SOCIETYBALASAHEB BUDRUK SATISH PATIL360%14 Jan 2020
Vijay Nagarvijay anant kulkarni280%26 Jun 2018
SHRI SAMARTH SOCIETYSHRI DEVELOPERS260%14 Jan 2020
DHANESHWAR TOWERS . P. CONSTRUCTION2483%29 Apr 2024
MANJIRI PRATHAMSHRI DEVELOPERS1010%11 Oct 2022
NAKSHATRA RESIDENCYCHETAN RANGNATHRAO WATHWADE--31 Aug 2017
SHREE BHAGWATISUNITA LAXMIKANT BAGAL--24 Aug 2017
SHINDE GREENSAMIT DILIPRAO SHINDE--1 Sep 2017
Chhoriya Prestige, TuljapurDhariwal And Chhoriya Buildcon Pvt Ltd--20 Apr 2018
PUJARI NAGARSHIVTEJ BUILDERS AND DEVELOPERS--8 Feb 2018
RUDRA CITYSHRI GANESH BUILDERS AND DEVELOPERS--5 Dec 2017
EMPIRE ESTATECHHATRAPATI SAMRAJYA--8 Feb 2018
BHAVANI PROMOTERS AND BUILDERS CTS 3988 A/BBHAVANI PROMOTERS & BUILDERS--15 Oct 2018
PUSHKRAJ TOWERPUSHKRAJ SHRIKANT HEDDA--11 Apr 2018
YASH APARTMENTMANISHA SRINIVAS JADHAV--28 Dec 2018
SAMARTH PLANETSHRIKANT VITTHALDAS HEDDA--10 Jan 2020
THE GRAND PADMAKSH PHASE 1M/S PADMAJA DEVELOPERS--30 Sep 2019
EktaApartmentKiran Tukaram Sarpe--11 Feb 2020
PAI. ANUPSINGH SADDIWAL COMPLEXPAI ANUPSINGH SADDH--3 Jan 2020
NAKSHATRA HIGHTSDIGVIJAY RAMESH GHUTE PATIL--24 Feb 2020
VIJAY GEETNorth West Infra--18 Feb 2020
Bhavani Promoters and Builders Shivaji Nagar TuljapurBHAVANI PROMOTERS & BUILDERS--3 Jun 2020
THE GRAND PADMAKSH PHASE 2M/S PADMAJA DEVELOPERS--28 Jun 2020
Ambure ComplexBhavani Promters & Builders--21 Oct 2020
Swastik PrimeDINESH KHUSHIRAM AGRAWAL HUF--30 Mar 2021
HILLS SIDE GALAXYVIJAY SITARAM DANDNAIK--10 Feb 2021
KRISHNAKUNJAS BUILDERS AND DEVELOPERS--5 Apr 2021
THE GRAND PADMAKSH PHASE 3M/S PADMAJA DEVELOPERS--3 Dec 2021
SUDARSHAN TOWERS . P. CONSTRUCTION--14 Jan 2022
PANCHAVATI APPARTMENTYASHODHAN BUILDERS & DEVELOPERS--16 Feb 2022
D.S TowerSushil Mahadeoappa Dalgade--4 May 2022
AKASH CONSTRUCTIONABASAHEB RAOSAHEB KOKATE--11 Apr 2022
D.K. Garden SocietySushil Mahadeoappa Dalgade--23 Oct 2023
Swastik Saraswati ParkS P Associates--16 Jul 2024
NAWANDER LANDMARK 2North West Infra--20 Jan 2025
DHANESHWAR HEIGHTSRAMCHANDRA NANABHAU SANGLE--28 Mar 2025
PARMESHWAR RESIDENCYTulja Developers--23 Jun 2025
Planning a launch in Osmanabad? The area consolidated report packs launches, inventory movement, unit sizes and absorption across the projects you pick into one document. Rs 2,999 for the first project and Rs 1,999 for each additional one. Area report · Rs 2,999 · coming soon  See what is coming

Developers active in Osmanabad

Dhariwal And Chhoriya Buildcon Pvt Ltd (3), M/S PADMAJA DEVELOPERS (3), SHRI DEVELOPERS (2), S . P. CONSTRUCTION (2), BHAVANI PROMOTERS & BUILDERS (2), North West Infra (2). Each link opens the promoter's track record built from their own filings.

Frequently asked questions

How do I shortlist among the Osmanabad projects listed above?

Compare each project against its neighbours, not against the brochure. The median project on this page is 17% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.

What does a revised completion date on a Osmanabad project actually mean?

The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.

What stamp duty will I pay on a flat in Osmanabad district?

The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.

What does it mean that some Osmanabad registrations have lapsed?

A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.

What if a Osmanabad project shows strong sales but slow construction?

That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.

Data from official MahaRERA filings.