New projects and RERA data in Osmanabad district, Maharashtra
48 projects are registered in Osmanabad district: 2,047 units across them, 1 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 48 covered registrations, 5 have revised their promised completion date and 0 declare litigation. The median project here is 16% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.
Also free on ReraGenie: a monthly RERA report for the seven biggest markets in Maharashtra (Pune, Mumbai, Thane, Navi Mumbai, Nagpur, Nashik and Vasai-Virar): what registered that month, the possession pipeline and the busiest pincodes, from the filings. See the latest editions.
When Osmanabad projects promise possession
Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 48 projects with a promised date, 29 are recorded delivered, 8 are still on the register and 11 have a registration that has lapsed or been cancelled.
DeliveredOn the registerRegistration lapsed or cancelled
9 projects promise possession in 2026 or later. Facts as per filings on RERA website.
971 flats are promised in 2026 or later, across the 33% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Facts as per filings on RERA website.
How far Osmanabad possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 5 of 48 projects (10%) have moved at least once; the median move is 12 months and the longest is 31 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Permissions and land in Osmanabad
Whose name the land is in
Every one of the 48 registrations on this page answers this: on 35 the promoter is the only owner named; on 12 the promoter is an owner with other names on the file, which is what a joint development looks like on paper; on 1 the promoter is not an owner. Where other names are on the file, ask which of them signs your agreement for sale. A landowner who is not a party to it is a question for your lawyer before you pay, not a defect in the project.
Where in Osmanabad: projects by taluka
48 of the 48 registrations on this page name their taluka.
| Taluka | Projects | Share |
|---|---|---|
| Osmanabad | 19 | 40% |
| Umarga | 13 | 27% |
| Tuljapur | 10 | 21% |
| Kalamb | 2 | 4% |
| Paranda | 2 | 4% |
| 2 other talukas | 2 | 4% |
Projects in Osmanabad
Showing all 48 projects.
Largest first, by the unit count in the filing.
| Project | Developer | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| RSM DHARASHIV SHELTERS- OSMANABAD PROJECTOsmanabad, 413501 | RSM DHARASHIV SHELTERS | 899 | 56% | 26 Jun 2021 | Registered |
| Chhoriya Township Plotting Layout ParandaParanda, 413502 | Pragati Infra Services Pvt. Ltd. | 253 | 81% | 22 Aug 2017 | Completed |
| R M Dhariwal Township Bhoom PlottingBhoom, 413504 | Dhariwal And Chhoriya Buildcon Pvt Ltd | 211 | 56% | 27 Aug 2017 | Completed |
| Vidhyanagar Bunglow PlottingOmerga, 413604 | Vidhyanagar Bunglow Plotting Prop Mrs Vidhya P Chavan | 104 | 1% | 16 May 2024 | Completed |
| R M Dhariwal Township Tuljapur PlottingTuljapur, 413601 | Dhariwal And Chhoriya Buildcon Pvt Ltd | 96 | 49% | 22 Aug 2017 | Completed |
| SHANTADEVI HOMESEkundi (j), 413606 | SANJAY BHASKARRAO CHALUKYA | 90 | 17% | 17 Aug 2017 | Completed |
| Shivaji Nagarumarga, 413606 | Vikram Venkatrao Gaikwad | 85 | 16% | 1 Sep 2017 | Completed |
| PRAGATI TOWERNA, 413606 | SHALIMAR CONSTRUCTIONS | 56 | 20% | 22 Sep 2023 | Completed |
| TULJAI TOWERDHARASHIV, 413501 | S P CONSTRUCTION | 48 | 0% | 15 Apr 2026 | Registered |
| VrundavanKalamb, 413507 | Gautam Limbraj Wayse | 43 | 0% | 15 Jun 2022 | Registration lapsed |
| SHREE SAMARTH KRUPA NAGARUmarga(rural), 413606 | SAINATH VENKATRAO PISKE | 38 | 26% | 23 Aug 2017 | Completed |
| SHIVRAI SOCIETYTAMBARI VIBHAG, 413501 | BALASAHEB BUDRUK SATISH PATIL | 36 | 0% | 14 Jan 2020 | Completed |
| Vijay NagarTamalwadi, 413623 | vijay anant kulkarni | 28 | 0% | 26 Jun 2018 | Completed |
| SHRI SAMARTH SOCIETYSURVEY NO 717/2 BEHIND OM SAIRAM NAGAR OSMANABAD, 413501 | SHRI DEVELOPERS | 26 | 0% | 14 Jan 2020 | Completed |
| DHANESHWAR TOWERDHARASHIV, NEAR EYE ROTARY HOSPITAL, 413501 | S . P. CONSTRUCTION | 24 | 83% | 29 Apr 2024 | Registered |
| MANJIRI PRATHAMSHRI SAMARTH SOCIETY,, 413501 | SHRI DEVELOPERS | 10 | 10% | 11 Oct 2022 | Completed |
| AKASH CONSTRUCTIONOsmanabad, 413501 | ABASAHEB RAOSAHEB KOKATE | - | - | 11 Apr 2022 | Registration lapsed |
| Ambure ComplexNehru Chowk, 413501 | Bhavani Promters & Builders | - | - | 21 Oct 2020 | Registration lapsed |
| BHAVANI PROMOTERS AND BUILDERS CTS 3988 A/BOSMANABAD, 413501 | BHAVANI PROMOTERS & BUILDERS | - | - | 15 Oct 2018 | Completed |
| Bhavani Promoters and Builders Shivaji Nagar TuljapurShivaji Nagar, 413601 | BHAVANI PROMOTERS & BUILDERS | - | - | 3 Jun 2020 | Completed |
| Chhoriya Prestige, TuljapurTuljapur, 413601 | Dhariwal And Chhoriya Buildcon Pvt Ltd | - | - | 20 Apr 2018 | Completed |
| D.K. Garden SocietyNear Basweshwar School, 413606 | Sushil Mahadeoappa Dalgade | - | - | 23 Oct 2023 | Registered |
| D.S TowerJijamata School, 413606 | Sushil Mahadeoappa Dalgade | - | - | 4 May 2022 | Registration lapsed |
| DHANESHWAR HEIGHTSDHARSHIV MIDC, 413501 | RAMCHANDRA NANABHAU SANGLE | - | - | 28 Mar 2025 | Registered |
| EktaApartmentEkta Apartmnet, 413606 | Kiran Tukaram Sarpe | - | - | 11 Feb 2020 | Completed |
| EMPIRE ESTATEIN FRONT OF SAHYADRI HOSPITAL NARAYAN COLONY KAKADE PLOT, 413501 | CHHATRAPATI SAMRAJYA | - | - | 8 Feb 2018 | Completed |
| HILLS SIDE GALAXYYASHWANT NAGAR, 413501 | VIJAY SITARAM DANDNAIK | - | - | 10 Feb 2021 | Registration lapsed |
| KRISHNAKUNJNEAR DWARKA NAGRI, 413507 | AS BUILDERS AND DEVELOPERS | - | - | 5 Apr 2021 | Registration lapsed |
| NAKSHATRA HIGHTSANAND NAGAR, 413501 | DIGVIJAY RAMESH GHUTE PATIL | - | - | 24 Feb 2020 | Completed |
| NAKSHATRA RESIDENCYOSMANABAD, 413501 | CHETAN RANGNATHRAO WATHWADE | - | - | 31 Aug 2017 | Completed |
| NAWANDER LANDMARK 2Tuljabhawani Engineering Collage, 413601 | North West Infra | - | - | 20 Jan 2025 | Registered |
| PAI. ANUPSINGH SADDIWAL COMPLEXPARANDA, 413502 | PAI ANUPSINGH SADDH | - | - | 3 Jan 2020 | Completed |
| PANCHAVATI APPARTMENTOSMANABAD, 413606 | YASHODHAN BUILDERS & DEVELOPERS | - | - | 16 Feb 2022 | Completed |
| PARMESHWAR RESIDENCYTuljapur, 413601 | Tulja Developers | - | - | 23 Jun 2025 | Completed |
| PUJARI NAGARPlot No.61 to 69, 413601 | SHIVTEJ BUILDERS AND DEVELOPERS | - | - | 8 Feb 2018 | Completed |
| PUSHKRAJ TOWERSHIVAJI COLLEGE, 413606 | PUSHKRAJ SHRIKANT HEDDA | - | - | 11 Apr 2018 | Completed |
| RUDRA CITYTuljapur, 413601 | SHRI GANESH BUILDERS AND DEVELOPERS | - | - | 5 Dec 2017 | Registration lapsed |
| SAMARTH PLANETSAIDHAM COLONY, 413606 | SHRIKANT VITTHALDAS HEDDA | - | - | 10 Jan 2020 | Completed |
| SHINDE GREENSOsmanabad, 413501 | AMIT DILIPRAO SHINDE | - | - | 1 Sep 2017 | Completed |
| SHREE BHAGWATIOsmanabad, 413501 | SUNITA LAXMIKANT BAGAL | - | - | 24 Aug 2017 | Completed |
| SUDARSHAN TOWERDhaneshvar Nagar, 413501 | S . P. CONSTRUCTION | - | - | 14 Jan 2022 | Completed |
| Swastik PrimeOsmanabad Road, 413601 | DINESH KHUSHIRAM AGRAWAL HUF | - | - | 30 Mar 2021 | Registration lapsed |
| Swastik Saraswati ParkTuljapur, 413601 | S P Associates | - | - | 16 Jul 2024 | Registered |
| THE GRAND PADMAKSH PHASE 1Padmavati Nagar, 413501 | M/S PADMAJA DEVELOPERS | - | - | 30 Sep 2019 | Registered |
| THE GRAND PADMAKSH PHASE 2Padmavati Nagar, 413501 | M/S PADMAJA DEVELOPERS | - | - | 28 Jun 2020 | Registration lapsed |
| THE GRAND PADMAKSH PHASE 3PADMAVATI NAGAR, 413501 | M/S PADMAJA DEVELOPERS | - | - | 3 Dec 2021 | Registration lapsed |
| VIJAY GEETNear Potdar School, 413606 | North West Infra | - | - | 18 Feb 2020 | De-registered |
| YASH APARTMENTSHIVPURI COLONY, 413606 | MANISHA SRINIVAS JADHAV | - | - | 28 Dec 2018 | Completed |
Developers active in Osmanabad
Dhariwal And Chhoriya Buildcon Pvt Ltd (3), S P CONSTRUCTION (3), M/S PADMAJA DEVELOPERS (3), SHRI DEVELOPERS (2), BHAVANI PROMOTERS & BUILDERS (2), Sushil Mahadeoappa Dalgade (2). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Osmanabad projects listed above?
Compare each project against its neighbours, not against the brochure. The median project on this page is 16% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Osmanabad project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What stamp duty will I pay on a flat in Osmanabad district?
The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.
What does it mean that some Osmanabad registrations have lapsed?
A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.
What if a Osmanabad project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own MahaRERA filings, and we read every report.
Report an errorShare feedbackData from official MahaRERA filings.