YUVRAJ RESIDENCY

By YESHWANT VITHALRAO TIDKE

RG-MH-98128 · RERA P51500026163 · Last updated on MahaRERA portal: 17 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 33 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Jan 2024Possession promised33 months past this date
59 of 88Construction stages doneacross 8 buildings; furthest along: Slabs of Super Structure, 70%
0Complaints at MahaRERAon this registration
Jump to the 40 documents Report an error

YUVRAJ RESIDENCY is a Residential / Group Housing project by YESHWANT VITHALRAO TIDKE in Aurangabad, Maharashtra, registered with MahaRERA as P51500026163 on 25 Aug 2020. Possession was promised by 31 Jan 2024 and is now 33 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameYUVRAJ RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Gopalpur road
    • pisadevi
    • Gopalpur road Pisadevi
    • Pisadevi
    • Aurangabad
    • 431008
  • Pincode431008
  • RERA no.P51500026163
  • ReraGenie IDRG-MH-98128

Builder

  • NameYESHWANT VITHALRAO TIDKE
  • Entity typeIndividual

Key dates

33 months past promisethis monthRegisteredAug 2020First promiseJan 2023Revised toJan 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Aug 2020
  • Promised completion31 Jan 2024
  • Revised completionRevised to 31 Jan 2024 (originally 31 Jan 2023)
  • Buildings8 building records
  • Documents filed40 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA20000
BUILDING BNA20000
BUILDING CNA20000
BUILDING DNA60000
BUILDING ENA20000
BUIDING FNA60000
BUILDING GNA30000
BUILDING HNA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 17 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

59 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Slabs of Super Structure, at 70%.

BUILDING A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING D43%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUIDING F52%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING G43%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING H61%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered4
BuildingClosed/CoveredTotal
BUILDING D11
BUIDING F11
BUILDING G11
BUILDING H11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,755 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5697.0
Proposed, not sanctioned4,939 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThane West

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Dhanajay Dohifode
EngineerSuvarna Consultancy
EngineerKiran Tidke
Chartered AccountantJAIN BHUTA & ASSOCIATES
PartnerRole in project
YESHWANT VITHALRAO TIDKE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500012961Jan 2023 → Jan 2024

Reason as filed by the promoterDue To Covid Issues and Lockdown the Project started late & due to COVID impact material & labour were not available in required volume therefore project work begins very slow & is Not Completed within time 31/01/2023.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Aug 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Jan 2025

Documents filed40

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: archite certificate .pdf17 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Epson229_compressed.pdf17 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Epson230_compressed.pdf17 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: occupancy certificate .pdf8 Aug 2024
Disclosure of sold/ booked inventoryFile: sold booking .pdf20 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: cidco completion certificate .pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arcitect Certificate_compressed.pdf6 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer's Certificate Form 2.pdf6 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf6 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annexure_F_Form_5.pdf6 Dec 2023
CERSAI detailsFile: CERSAI_Search_Report_200257560856_For_Asset_Based_Search_13_01_2023_19_11_38_575.pdf13 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Discloser in other real estate project.pdf13 Jan 2023
Proforma of Agreement for saleFile: RERA AGREEMENT 2023.pdf13 Jan 2023
Proforma of Allotment letterFile: Allotment Letter.pdf13 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account.pdf13 Jan 2023
Deviation Report with respect to Allotment letterFile: Deviation Letter.pdf13 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Letter.pdf13 Jan 2023
Details of encumbrances concerned to FinanceFile: Search Report.pdf9 Jan 2023
Details of encumbrances concerned to LegalFile: Search Report.pdf9 Jan 2023
Declaration about Commencement CertificateFile: Declaration09012023.pdf9 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate06012023.pdf9 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Annexure C06012023.pdf9 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Bookded Inventory09012023_compressed.pdf9 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rera form -3 Balaji infra_compressed.pdf9 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Rera form 5 Balaji infra_compressed.pdf9 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_compressed.pdf10 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5.pdf10 May 2022
Building plan approvalFile: scan-compressed.pdf14 Aug 2020
Layout approvalFile: scan-compressed.pdf14 Aug 2020
PAN CardFile: Pan card.pdf14 Aug 2020
Copy of the legal title reportFile: Search Report.pdf14 Aug 2020
Details of encumbrancesFile: Encumbrance Certificate.pdf14 Aug 2020
Copy of Layout Approval (in case of layout)File: scan-compressed.pdf14 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: scan-compressed.pdf14 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf14 Aug 2020
Declaration in FORM BFile: form B.pdf14 Aug 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arcitech Cericate.pdf14 Aug 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf14 Aug 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf14 Aug 2020
Proforma of Allotment letterFile: Agreement to sale flat 1.pdf14 Aug 2020

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 12 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep YUVRAJ RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gopalpur road Pisadevi1,400+ in Aurangabad

Builder: YESHWANT VITHALRAO TIDKE

YESHWANT VITHALRAO TIDKE has 1 registration on MahaRERA, including YUVRAJ RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that YUVRAJ RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if YUVRAJ RESIDENCY is delayed beyond 31 Jan 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of YUVRAJ RESIDENCY?

The registered promoter entity is YESHWANT VITHALRAO TIDKE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in YUVRAJ RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for YUVRAJ RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at YUVRAJ RESIDENCY?

The professionals named in the filing: Architect: Mr Dhanajay Dohifode; Engineer: Suvarna Consultancy; Engineer: Kiran Tidke; Chartered Accountant: JAIN BHUTA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in YUVRAJ RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About YUVRAJ RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save YUVRAJ RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.