Yashwant Height
By M.P. GLOBAL HEIGHT PRIVATE LIMITED
RG-MH-63661 · RERA P51800010825 · Last updated on MahaRERA portal: 19 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 2 complaints at MahaRERA
- Completion date moved by 60 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Yashwant Height is a Others project by M.P. GLOBAL HEIGHT PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800010825 on 31 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 60 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameYashwant Height
- TypeOthers
- Location
- L.T Road
- Dahisar West
- Borivali
- Mumbai Suburban
- 400068
- Pincode400068
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800010825
- ReraGenie IDRG-MH-63661
Builder
- NameM.P. GLOBAL HEIGHT PRIVATE LIMITED
- Entity typeCompany
- CINU45201MH2021PTC370176
- GSTIN27AAPCM1127J1ZA
- PartnerJignesh Bharat Maniar
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2021)
- Buildings1 building record
- Documents filed79 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Yashwant Height | NA | 24 | 17 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 19 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 95%.
Yashwant Height: 70% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 95% |
| Plinth | 100% |
| Stilt Floor | 84% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 84% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 19 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 10% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 20% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed72
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| R.Y.Tawde and others | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Atul A Rana |
| Partner | Role in project |
|---|---|
| M.P. GLOBAL HEIGHT PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project was on hold due to covid-19 and financial issues, however, we are now going to complete the project on or before 30th June 2025.
Reason as filed by the promoterDue to delay in approval of loan from Swamih Investment Fund I and Covid there was delay in Project completion.
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000195672 | Chetan Parshuram Patil | Mrs Global Developers | 06/02/2021 |
| CC006000000210013 | Amit Gujar | Global Developers | 13/02/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 May 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed79
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: CA Certificate-Form 3.pdf | 19 Jun 2025 |
| Certificates of CA (Form 3)File: CA Certificate-Form 3.pdf | 19 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 19 Jun 2025 |
| Certificates of CA (Form 3)File: Form 3 - CA Certificate.pdf | 19 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 -2020-21.pdf | 16 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 -2021-22.pdf | 16 May 2025 |
| Layout approvalFile: plan.pdf | 2 May 2025 |
| Copy of Layout Approval (in case of layout)File: plan.pdf | 2 May 2025 |
| Disclosure of sold/ booked inventoryFile: sold unsold inventory.pdf | 28 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate DEC 24.pdf | 23 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate MAR 25.pdf | 23 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 - CA Certificate SEPT 24.pdf | 23 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 - CA Certificate DEC 24.pdf | 23 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 - CA Certificate MAR 25.pdf | 23 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer' Certificate DEC 24.pdf | 23 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer' Certificate MAR 25.pdf | 23 Apr 2025 |
| Layout approvalFile: PLAN 1 (1).pdf | 31 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: PLAN 1 (1).pdf | 31 Dec 2024 |
| Declaration in FORM BFile: Form B - Rs 100 stamp paper.pdf | 31 Dec 2024 |
| Certificates of CA (Form 3)File: FORM 3 - CA CERTIFICATE FINAL.pdf | 31 Dec 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 31 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Site Supervisor.pdf | 31 Dec 2024 |
| Declaration about Commencement CertificateFile: Form D.pdf | 30 Dec 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 30 Dec 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B-on Bank letterhead.pdf | 30 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 28 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 4 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 4 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 05.pdf | 4 Dec 2024 |
| Layout approvalFile: layout.pdf | 5 Nov 2024 |
| Building plan approvalFile: plan (1).pdf | 5 Nov 2024 |
| Building plan approvalFile: Issue letter.pdf | 5 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 5 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 5 Nov 2024 |
| Building Plan Approval (IOD)File: plan (1).pdf | 5 Nov 2024 |
| Building Plan Approval (IOD)File: Issue letter.pdf | 5 Nov 2024 |
| Other - LegalFile: Rera Declaration.pdf | 6 Feb 2024 |
| Other - LegalFile: Rera Declaration.pdf | 6 Feb 2024 |
| Declaration in FORM BFile: Form B.pdf | 14 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Revalidated CC.pdf | 11 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD NEW.pdf | 11 Aug 2023 |
| Certificates of CA (Form 3)File: CA NEW (1).pdf | 11 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 7 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 01.pdf | 7 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 02.pdf | 7 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf | 7 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf | 7 Jul 2023 |
| CERSAI detailsFile: Cersai Global.pdf | 7 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 7 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.pdf | 7 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA BANK LETTER.pdf | 7 Jul 2023 |
| Declaration about Commencement CertificateFile: CC DECL.pdf | 8 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch_compressed (1).pdf | 8 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng march.pdf | 8 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng sept.pdf | 8 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Certificate 1_compressed.pdf | 8 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Certificate 2_compressed.pdf | 8 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 8 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 2017-18.pdf | 8 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19.pdf | 8 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20.pdf | 8 Oct 2021 |
| Building plan approvalFile: Revise IOD 01-06-15.pdf | 31 Jul 2017 |
| Layout approvalFile: Layout Plan-2.pdf | 31 Jul 2017 |
| Layout approvalFile: Layout Plan-3.pdf | 31 Jul 2017 |
| Layout approvalFile: Layout Plan-4.pdf | 31 Jul 2017 |
| Layout approvalFile: Layout Plan-1.pdf | 31 Jul 2017 |
| PAN CardFile: Global Developers Pan Card.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Ttile Certificate.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Encumberance Certificate.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout Plan-1.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout Plan-2.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout Plan-3.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout Plan-4.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Revise IOD 01-06-15.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Affidavit Global Developers.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE - Form 1.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate - Form 2.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: Form 3.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Allotment letter and Sale Deed.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 79 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Yashwant Height on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dahisar West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 250 registered projects within 2 km.
ICON
RAGHU LEELA REALTORS PRIVATE LIMITED
ORNATE SOLITAIRE
ORNATE DAHISAR DEVELOPERS
EMPIRE HEIGHTS
EMPIRE REALTY
SHAKTI DHAM-WING A, VRINDAVAN-WING B RESIDENTI
DHARTI DEVELOPERS
RAGHUKUL CHSL
RAMNIYATI REALITIES LLP
Earth Residency Wing C and Wing D
Earth Estate Developers Pvt Ltd
See every Mumbai Suburban project, with the district possession charts
Builder: M.P. GLOBAL HEIGHT PRIVATE LIMITED
M.P. GLOBAL HEIGHT PRIVATE LIMITED has 1 registration on MahaRERA, including Yashwant Height. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Yashwant Height is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Yashwant Height?
The registered promoter entity is M.P. GLOBAL HEIGHT PRIVATE LIMITED, a company as per the filing. Its CIN U45201MH2021PTC370176 and GSTIN 27AAPCM1127J1ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Yashwant Height?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Yashwant Height?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Yashwant Height?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Yashwant Height?
The professionals named in the filing: Architect: Atul A Rana. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Yashwant Height?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback