Home / Browse projects / Raigarh, Maharashtra / XRBIA VANGANI - PH 1
XRBIA VANGANI - PH 1
RG-MH-63864 · RERA P52000008453 · Last updated on MahaRERA portal: 3 Aug 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 19 months past the filed date
- 26 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
XRBIA VANGANI - PH 1 is a Others project by Xrbia Developers Ltd in Raigarh, Maharashtra, registered with MahaRERA as P52000008453 on 19 Aug 2017. Possession was promised by 30 Mar 2025 and is now 19 months past that date. 26 complaints are on record with the regulator.
At a glance
Project
- NameXRBIA VANGANI - PH 1
- TypeOthers
- Location
- Khadyachapada
- Karjat
- Raigarh
- 410201
- Pincode410201
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000008453
- ReraGenie IDRG-MH-63864
Builder
- NameXrbia Developers Ltd
- Entity typeCompany
- Other registrations9 more →
- No longer live10 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Aug 2017
- Promised completion30 Mar 2025
- Revised completionNone
- Buildings16 building records
- Documents filed33 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A4 | NA | 8 | 0 | 0 | 0 | 0 |
| B1 | NA | 8 | 0 | 0 | 0 | 0 |
| B2 | NA | 8 | 0 | 0 | 0 | 0 |
| B3 | NA | 8 | 0 | 0 | 0 | 0 |
| C1 | NA | 8 | 0 | 0 | 0 | 0 |
| C2 | NA | 8 | 0 | 0 | 0 | 0 |
| C3 | NA | 8 | 0 | 0 | 0 | 0 |
| C4 | NA | 8 | 0 | 0 | 0 | 0 |
| C5 | NA | 8 | 0 | 0 | 0 | 0 |
| C6 | NA | 8 | 0 | 0 | 0 | 0 |
| D1 | NA | 8 | 0 | 0 | 0 | 0 |
| D2 | NA | 8 | 0 | 0 | 0 | 0 |
| D3 | NA | 8 | 0 | 0 | 0 | 0 |
| D4 | NA | 8 | 0 | 0 | 0 | 0 |
| E1 | NA | 8 | 0 | 0 | 0 | 0 |
| E2 | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building16
As on 3 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
64 of 176 construction stages are filed complete across 16 buildings. The stage furthest along is External plumbing and external plaster, at 84%.
A452%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 47% |
| Sanitary Fittings within the flats / premises | 47% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 53% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B154%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 44% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 76% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 13% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B258%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 57% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B356%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 49% |
| Sanitary Fittings within the flats / premises | 44% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 53% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C150%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 54% |
| Sanitary Fittings within the flats / premises | 17% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 78% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C251%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 48% |
| Sanitary Fittings within the flats / premises | 31% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 78% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C361%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 84% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C459%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 53% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 71% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C559%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C654%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 78% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 12% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D156%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 47% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 78% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 36% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D257%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 47% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 78% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D353%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 57% |
| Sanitary Fittings within the flats / premises | 31% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 78% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D442%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 5% |
| Sanitary Fittings within the flats / premises | 14% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 47% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E147%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 46% |
| Sanitary Fittings within the flats / premises | 27% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 47% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E257%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 53% |
| Sanitary Fittings within the flats / premises | 36% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities25
As on 3 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 20% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| GARDEN | Yes | 0% |
| FESTIVAL PLAZA | Yes | 0% |
| Club House | Yes | 0% |
| CAFETERIA | Yes | 0% |
| Gymnasium | Yes | 0% |
| KIDS PLAY AREA | Yes | 0% |
| MULTIPURPOSE HALL | Yes | 0% |
| POWER BACKUPFOR COMMON AREA AND LIFTS | Yes | 0% |
| SPORTS FACILITY | Yes | 0% |
| Swimming Pool | Yes | 0% |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| RAHUL R NAHAR | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ajay Gade |
| Partner | Role in project |
|---|---|
| Xrbia Developers Ltd | - |
Litigation declared1
| Case | Court | Status |
|---|---|---|
| REGULAR CIVIL SUIT NO 64/2001/2001 | Civil Judge Junior Division Karjat | For Evidence of Plaintiff |
Complaints filed with MahaRERA26
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000000529 | CHEATED BY BUILDER | M/S XRBIA DEVELOPERS LTD. | 10/09/2017 |
| CC006000000023554 | XRBIA DEVELOPERS LTD | Sharad Dattanand Kalyanpur | 03/03/2018 |
| CC006000000089619 | mahendra dhanaji pawar | xrbia developers Ltd | 07/06/2019 |
| CC006000000196352 | SUNIL SHANAKAR PHALAKE | RAHUL R NAHAR | 13/03/2021 |
| CC006000000195556 | JITESH GAJANAN THORAT | XRBIA DEVELOPERS LTD | 19/01/2021 |
| CC006000000196353 | SANDESH SHANKAR PATIL | RAHUL N NAHAR | 13/03/2021 |
| CC006000000199085 | PANDHARINATH K MULAYE | XERBIA DEVELOPERS LTD. | 19/11/2021 |
| CC006000000209446 | Rahul Nahar | Rahul Nahar | 17/12/2021 |
| CC006000000210563 | Vivek Sawant | XRbia | 28/03/2022 |
| CC006000000334110 | Sharad Kundlik Ghoderao | Xrbia Developers Limited | 26/01/2023 |
| CC006000000354398 | Joanna Dantis | Xrbia Developers Limited | 18/02/2023 |
| CC006000000375154 | Vivek Anil Sawant | Xrbia Developers Limited | 18/04/2023 |
| CC006000000395470 | Bhushan Adinath Vardhamane | Xrbia Developers Ltd | 22/05/2023 |
| CC006000000480314 | Rani Gonsalvez | XRBIA DEVELOPES | 17/05/2024 |
| CC006000000591395 | Amodh Rane | XRBIA DEVELOPERS | 02/08/2024 |
| CC12401096 | Vivek Anil Sawant | Xrbia Developers Ltd | 11/12/2024 |
| CC12502081 | Indrajit Rajkumar Kundu | Xrbia Developers Ltd | 25/06/2025 |
| CC12502078 | Ragini Rakesh Bhosle | Xrbia Developers Ltd | 25/06/2025 |
| CC12502162 | Deepak More | Xrbia Developers Ltd | 30/06/2025 |
| CC12502478 | OMKAR PRAKASH CHAVAN | Xrbia Developers Ltd | 19/07/2025 |
| CC12502543 | Priyanka Poojary | Xrbia Developers Ltd | 23/07/2025 |
| CC12502822 | Shilpa and Sandeep Surve Surve | Xrbia Developers Ltd | 12/08/2025 |
| CC12503273 | Shivprasad Shetye | Xrbia Developers Ltd | 14/09/2025 |
| CC12503597 | Dominic and Flavia Pereirra | Xrbia Developers Ltd | 09/10/2025 |
| CC12504131 | VIJAY GANGARAM PEVEKAR | Xrbia Developers Ltd | 24/11/2025 |
| CC12504674 | Ram Dattaram Dalvi | Xrbia Developers Ltd | 29/12/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed33
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Vangani P1 Form 5_Marh 22.pdf | 3 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Ph1_Arch_Qtr 1_22-23.pdf | 10 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Ph1_Arch_Qtr 3_21-22.pdf | 9 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Ph1_Arch_Qtr 4_21-22.pdf | 9 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Ph1_Arch_Qtr 2_22-23.pdf | 9 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Ph1_Arch_Qtr 3_22-23.pdf | 9 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Ph1_Engg_Qtr 3_21-22.pdf | 9 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Ph1_Engg_Qtr 4_21-22.pdf | 9 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Ph1_Engg_Qtr 1_22-23.pdf | 9 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Ph1_Engg_Qtr 2_22-23.pdf | 9 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Ph1_Engg_Qtr 3_22-23.pdf | 9 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Vangani-Ph 1-Form 5-310321.pdf | 25 Jan 2023 |
| Declaration about Commencement CertificateFile: Vangani_Ph 1-2_CC Declaration.pdf | 15 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Xrbia Vangani_Ph1_Sold Unit Declaration_090821.pdf | 15 Aug 2021 |
| Proforma of Allotment letterFile: Xrbia Vangani_Ph 1_Draft_.pdf | 5 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Vangani_Ph 1_Form 5_31032020.pdf | 28 May 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Vangani_Form 5_Ph 1.pdf | 30 Dec 2019 |
| Certificates of CA (Form 5)File: Vangani_Form_5_Ph 1.pdf | 3 Nov 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Vangani_Plot_1_NA_ORDER.pdf | 26 Mar 2018 |
| Building plan approvalFile: Vangani_PH_1_NA_ORDER.pdf | 31 Jul 2017 |
| Layout approvalFile: Vangani_PH_1_Sanction Plan.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: TSR_PH_1.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Details of encumbrances - Vangani Phase 1.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Vangani_PH_1_Sanction Plan.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Vangani_PH_1_NA_ORDER.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: FORM B_Affidavit Cum Declaration - Vangani Phase 1.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 1 - Architect's Certificate Vangani.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase 1 - Engineer's Certificate.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: XRBIA VANGANI PHASE 1-Final.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Declaration for RERA Agreement - Vangani Ph 1.pdf | 31 Jul 2017 |
| OtherFile: Vangani Ph 1 Declaration of Future Buildings.pdf | 31 Jul 2017 |
| OtherFile: Proposed Larger Layout.pdf | 31 Jul 2017 |
| OtherFile: Proposed _Vangani_Rera_Plot 1 FINAL.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 9 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 33 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep XRBIA VANGANI - PH 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Khadyachapada5,900+ in Raigarh
Filed coordinates, straight-line distance. 23 registered projects within 2 km.
Bellezza Woods
DOTOM BUILD SQUARE
Winds of Calm
Eiffel Lifespaces Pvt Ltd
PURANIK CITY SECTOR 2
Puranik Builders Limited
Foothills of Matheran P - 2
HOABL Impactum Land Private Limited
FLORENCE TOWN
BRIGHT DEVELOPERS
The Destination
DOVE BUILDMART PRIVATE LIMITED
See every Raigarh project, with the district possession charts
Builder: Xrbia Developers Ltd
Xrbia Developers Ltd has 10 registrations on MahaRERA, including First City and Xrbia Vangani Ph 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that XRBIA VANGANI - PH 1 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if XRBIA VANGANI - PH 1 is delayed beyond 30 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of XRBIA VANGANI - PH 1?
The registered promoter entity is Xrbia Developers Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in XRBIA VANGANI - PH 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against XRBIA VANGANI - PH 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for XRBIA VANGANI - PH 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at XRBIA VANGANI - PH 1?
The professionals named in the filing: Architect: Ajay Gade. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in XRBIA VANGANI - PH 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback