Home / Browse projects / Pune, Maharashtra / Xrbia Ambi - Ph - 2

Registration lapsed No litigation declared Others project

Xrbia Ambi - Ph - 2

By Xrbia Ambience Realty LLP

RG-MH-11690 · RERA P52100001487 · Last updated on MahaRERA portal: 15 Aug 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 43 months past the filed date
  • 3 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2023Possession promised43 months past this date
20 of 55Construction stages doneacross 5 buildings; furthest along: Excavation, 0%
3Complaints at MahaRERAon this registration
Jump to the 23 documents Report an error

Xrbia Ambi - Ph - 2 is a Others project by Xrbia Ambience Realty LLP in Pune, Maharashtra, registered with MahaRERA as P52100001487 on 28 Jul 2017. Possession was promised by 30 Mar 2023 and is now 43 months past that date. 3 complaints are on record with the regulator.

At a glance

Project

  • NameXrbia Ambi - Ph - 2
  • TypeOthers
  • Location
    • Ambi
    • Mawal
    • Pune
    • 410507
  • Pincode410507
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001487
  • ReraGenie IDRG-MH-11690

Builder

  • NameXrbia Ambience Realty LLP
  • Entity typePartnership
  • PartnersRushikesh Harishchandra Gadsing, Harishchandra Shatrughna Gadsing
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

43 months past promisethis monthRegisteredJul 2017PromisedMar 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Jul 2017
  • Promised completion30 Mar 2023
  • Revised completionNone
  • Buildings5 building records
  • Documents filed23 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA130000
A7NA130000
A8NA130000
A10NA130000
A4NA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 15 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Excavation, at 0%.

A10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A791%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A80%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A100%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities18

As on 15 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes47%
Water SupplyYes54%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes54%
Storm Water DrainsYes74%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes18%
Treatment And Disposal Of Sewage And Sullage WaterYes46%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes53%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes63%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes30%
Kids Play AreaYes0%
Sports FacilityYes6%
Swimming PoolYes0%

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Closed/Covered25
Open Space15
BuildingClosed/CoveredOpen SpaceTotal
A1639
A7639
A8639
A10639
A4134

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,113 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI21159.0
Proposed, not sanctioned15,869 sq m
Buildings approved4
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 1,2,Platinum Shree Chintamani CHS,Sector 14,Plot 18,Sanpada,Mumbai

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAjay Gade
EngineerSunil Mutalik And Associates
PartnerRole in project
Xrbia Ambience Realty LLP-

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000022751CA. SUHAS MALANKARXrbia Ambience Realty LLP05/03/2019
CC005000000043653Madhukar Sukhdev BhartiXrbia Ambience Realty LLP31/12/2019
CC005000000340691Nikita Hemant ShirdhankarXrbia Ambience Realty LLP30/03/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed23

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Xrbia Ambi_CC_Declaration.pdf15 Aug 2021
Disclosure of sold/ booked inventoryFile: Xrbia Ambi_Ph2_Sold Unit Declaration_090821.pdf15 Aug 2021
Proforma of Allotment letterFile: Xrbia Ambi_Ph 2_Draft_.pdf5 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Xrbia Ambi Ph 2_Form 5_31032020.pdf13 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Ambi Ph 2 Form 5 31032019.pdf6 Apr 2020
Details of encumbrancesFile: Ambi Ph 2 Declaration of SBI Encumbarance Release 070918.pdf21 Nov 2019
Certificates of CA (Form 5)File: Ambi Ph 2 Form 5 31032019.pdf24 Sep 2019
Details of encumbrancesFile: XRBIA AMBI -2.pdf2 Nov 2018
Certificates of CA (Form 5)File: Ambi_Form 5_Ph 2.pdf30 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf26 Mar 2018
Building plan approvalFile: Commencement Certificate.pdf26 Jul 2017
Layout approvalFile: SanctionPlan.pdf26 Jul 2017
Copy of the legal title reportFile: TSR.pdf26 Jul 2017
Details of encumbrancesFile: Affidavit Cum Declaration_Ph_2_Notorised.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: SanctionPlan.pdf26 Jul 2017
Building Plan Approval (IOD)File: Commencement Certificate.pdf26 Jul 2017
Declaration in FORM BFile: Affidavit Cum Declaration_Ph_2_Notorised.pdf26 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate_ph 2.pdf26 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate_Ambi_Ph 2.pdf26 Jul 2017
Certificates of CA (Form 3)File: CA Certificat - Ph 2_Reduced Size.pdf26 Jul 2017
Proforma of Allotment letterFile: Draft Agreement and Allotment Letter.pdf26 Jul 2017
OtherFile: Declartion of Proposed Buildings etc.pdf26 Jul 2017
OtherFile: Proposed Layout.pdf26 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Xrbia Ambi - Ph - 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ambi13,700+ in Pune

2 kmXrbia Ambi - Ph - 2Completed 17Lapsed / revoked 8Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 37 registered projects within 2 km.

Builder: Xrbia Ambience Realty LLP

Xrbia Ambience Realty LLP has 2 registrations on MahaRERA, including Xrbia Ambi - Ph - 1 and Xrbia Ambi - Ph - 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Xrbia Ambi - Ph - 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Xrbia Ambi - Ph - 2 is delayed beyond 30 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Xrbia Ambi - Ph - 2?

The registered promoter entity is Xrbia Ambience Realty LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Xrbia Ambi - Ph - 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Xrbia Ambi - Ph - 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Xrbia Ambi - Ph - 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Xrbia Ambi - Ph - 2?

The professionals named in the filing: Architect: Ajay Gade; Engineer: Sunil Mutalik And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Xrbia Ambi - Ph - 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Xrbia Ambi - Ph - 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Xrbia Ambi - Ph - 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.