Home / Browse projects / Pune, Maharashtra / Xrbia Abode

Registration lapsed No litigation declared Others project

Xrbia Abode

By Xrbia Abode Developers Private Limited

RG-MH-09667 · RERA P52100001412 · Last updated on MahaRERA portal: 11 Jan 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 43 months past the filed date
  • 19 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2023Possession promised43 months past this date
86 of 121Construction stages doneacross 11 buildings; furthest along: Sanitary Fittings within the flats /..., 90%
19Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

Xrbia Abode is a Others project by Xrbia Abode Developers Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100001412 on 28 Jul 2017. Possession was promised by 29 Mar 2023 and is now 43 months past that date. The completion date has moved by 12 months from the original filing. 19 complaints are on record with the regulator.

At a glance

Project

  • NameXrbia Abode
  • TypeOthers
  • Location
    • Jambhul
    • Mawal
    • Pune
    • 410507
  • Pincode410507
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001412
  • ReraGenie IDRG-MH-09667

Builder

  • NameXrbia Abode Developers Private Limited
  • Entity typeCompany

Key dates

43 months past promisethis monthRegisteredJul 2017First promiseMar 2022Revised toMar 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Jul 2017
  • Promised completion29 Mar 2023
  • Revised completionRevised to 29 Mar 2023 (originally 30 Mar 2022)
  • Buildings11 building records
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA90000
B1NA90000
B2NA80000
B3NA90000
C1NA90000
D1NA90000
D2NA90000
E1NA80000
F1NA90000
G1NA90000
G2NA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building11

As on 11 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

86 of 121 construction stages are filed complete across 11 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

A191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B284%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
B383%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
C168%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
D191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F164%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises51%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
G179%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
G291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes65%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes25%
Street LightingYes0%
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes5%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed45

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots45
Closed/Covered45
BuildingClosed/CoveredTotal
A166
B166
B355
C155
D155
D255
F133
G155
G255

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area33,136 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Miracle Shelters LLPPune (M Corp.)Pune

Approvals and building plan

Permissible FSI37154.28
Proposed, not sanctioned35,419 sq m
Buildings approved11
Buildings sanctioned11

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShivaji Nagar, Congress Bhavan Road, Pune

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAjay Gade
EngineerS R Consultants
EngineerS.S.Patane And Associates
PartnerRole in project
Xrbia Abode Developers Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011501Mar 2022 → Mar 2023

Reason as filed by the promoter6 Buildings Out of 11 Buildings have recived Completion / Occupancy Certificate. Work Got Delayed Due to Heavy Rains and Covid19 Related Lockdown , migration of labourers.

Complaints filed with MahaRERA19

Case no.ComplainantRespondentFiled
CC005000000022915POOJA NAGESH MUSALE & MR MAGESH RAMESH MUSALEXERBIA ABODE DEVELOPERS PVT LTD & MIRACLE SHELTERS PVT LTD17/06/2019
CC005000000022014FIROZ AZIZ SHAIKHXRBIA DEVELOPERS LIMITED11/09/2018
CC005000000022386Seeta Bajrang KachiXrbia Abode Dev.Pvt.Ltd.24/03/2019
CC005000000022664Satbir SinghXrbia Abode Developers Pvt.Ltd15/02/2019
CC005000000023041Ritesh Suresh DoiphodeXRBIA DEVELOPERS LTD.20/05/2019
CC005000000043693Vaishali Sanjay JadhavXRBIA ABODE DEVELOPERS PVT LTD23/11/2019
CC005000000075200VIJAY DATTATRAY CHAVANXrbia Developers Limited10/02/2021
CC005000000054151sATYABHAMA VIJAY BHADORIAXRBIA ABODE DEVELOPERS PVt. Ltd.14/03/2020
CC005000000064542Shaheen Amirali BatliwalaXrbia Abode Developers Private Limited24/08/2020
CC005000000085501Afsana Kayyum ShaikhKishor Hindgaonkar26/04/2021
CC005000000095882Arun Ranchhoddas AsharXbria Abode Developers Private Limited through its authorised signatory Karan Rajivkumar Karnawat13/08/2021
CC005000000096113Yogesh hulleXRBIA DEVELOPER11/10/2021
CC005000000147182Anju Sopchand BarewarXrbia Abode Developers Pvt Ltd01/06/2022
CC005000000310426Kavita Harichandra SurywanshiXrbia Abode Developers Pvt. Ltd. Through its Authorized Signatory Mr. Gajanan Sadashiv Dongare23/02/2024
CC005000000340792Harsha DalviXrbia Abode Developers Pvt. Ltd.17/04/2024
CC12400826Soma Chabu GawariXrbia Abode Developers Private Limited20/11/2024
CC12502430Satish SalianXrbia Abode Developers Private Limited17/07/2025
CC12502736ATUL ASHOK MOREXrbia Abode Developers Private Limited05/08/2025
CC12601365SUNITA RAMSINGH SAHANIXrbia Abode Developers Private Limited12/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_310321.pdf11 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Abode_Arch_Qtr 4_21-22.pdf2 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Declaration for Ext_Revert to RERA Query_070322.pdf7 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Declaration for Ext_Revert to RERA Query_070322.pdf7 Mar 2022
CERSAI detailsFile: Xrbia Abode_CERSAI_Search_Report_200231753257_For_Asset_Based_Search_07_03_2022_11_47_55_97 Mar 2022
Declaration about Commencement CertificateFile: Abode_CC_Declaration.pdf15 Aug 2021
Disclosure of sold/ booked inventoryFile: Abode_Sold Unit Declaration_090821.pdf15 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Xrbia Abode_Form 5_31032020.pdf3 Jun 2021
Details of encumbrancesFile: AbodeDeclarationofEncumbarancesSBI.pdf28 May 2020
Details of encumbrancesFile: AbodeDeclarationof.pdf18 May 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Abode.pdf6 Apr 2020
Certificates of CA (Form 5)File: Form 5 Abode.pdf21 Dec 2019
Details of encumbrancesFile: Abode SBI Release.pdf21 Nov 2019
Details of encumbrancesFile: AbodeEncubarancesDeclaration.pdf27 Dec 2018
Certificates of CA (Form 5)File: Abode_Form 5.pdf30 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencment_PMRDA.pdf26 Mar 2018
Declaration in FORM BFile: Form B_Promoter_Notorised.pdf27 Jul 2017
OtherFile: Proposed Layout.pdf24 Jul 2017
OtherFile: Dclaration of Future Buildings.pdf21 Jul 2017
Details of encumbrancesFile: Xrbia _Abode_Encumbarances.pdf17 Jul 2017
Building plan approvalFile: Commencment_PMRDA.pdf15 Jul 2017
Layout approvalFile: Sanction Plan.pdf15 Jul 2017
Copy of the legal title reportFile: TSR.pdf15 Jul 2017
Copy of Layout Approval (in case of layout)File: Sanction Plan.pdf15 Jul 2017
Building Plan Approval (IOD)File: Commencment_PMRDA.pdf15 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf15 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf15 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf15 Jul 2017
Proforma of Allotment letterFile: Draft Agreement and Allotment Letter.pdf15 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Xrbia Abode on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Jambhul13,700+ in Pune

2 kmXrbia AbodeCompleted 13Lapsed / revoked 11Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: Xrbia Abode Developers Private Limited

Xrbia Abode Developers Private Limited has 1 registration on MahaRERA, including Xrbia Abode. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Xrbia Abode shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Xrbia Abode is delayed beyond 29 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Xrbia Abode?

The registered promoter entity is Xrbia Abode Developers Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Xrbia Abode?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Xrbia Abode?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Xrbia Abode?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Xrbia Abode?

The professionals named in the filing: Architect: Ajay Gade; Engineer: S R Consultants; Engineer: S.S.Patane And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Xrbia Abode?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Xrbia Abode. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Xrbia Abode to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.