Home / Browse projects / Pune, Maharashtra / Windsor County Phase IV Wing I

Registration lapsed No litigation declared Residential / Group Housing project

Windsor County Phase IV Wing I

By Windsor Shelters

RG-MH-27568 · RERA P52100034251 · Last updated on MahaRERA portal: 18 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
10 of 11Construction stages donefurthest along: Stilt Floor, 0%
21 of 132Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 115 documents Report an error

Windsor County Phase IV Wing I is a Residential / Group Housing project by Windsor Shelters in Pune, Maharashtra, registered with MahaRERA as P52100034251 on 30 Mar 2022. Possession was promised by 30 Sep 2025 and is now 13 months past that date. 111 of the 132 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameWindsor County Phase IV Wing I
  • TypeResidential / Group Housing
  • Location
    • Datta Nagar Road
    • Ambegaon Bk.
    • AMBEGAON Bk
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100034251
  • ReraGenie IDRG-MH-27568

Builder

  • NameWindsor Shelters
  • Entity typePartnership
  • PartnersShriniwas Laxman Raskonda, Mahesh Tejraj Rathi
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

13 months past promisethis monthRegisteredMar 2022PromisedSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on30 Mar 2022
  • Promised completion30 Sep 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed115 files

Current status

84%111 of 132 units booked
99.0%Work done, per cost certificate

Figures as on 18 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Windsor County Wing INA141211913132

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

Windsor County Wing I: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes95%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes99%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed97

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots97
Closed/Covered97

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,300 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Jul 2025
LandownerVillageDistrict
MR. Mahesh T RathiPune (M Corp.)Pune
Mr. Shriniwas L RaskondaPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Muncipal Corporation
Permissible FSI11240.79
Proposed, not sanctioned11,241 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLaxmi Archade , Ghorpadi
Estimated costRs 31.82 cr
Cost incurredRs 31.50 cr
Work done98.98%
BuildingWingEstimatedIncurred
Windsor County Wing INARs 29.36 crRs 29.05 cr
-NARs 2.47 crRs 2.44 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectViinod Khanjode
EngineerCHETAN PANDIT
EngineerSHASHIKANT WAIKAR
EngineerArun Ghokhale
Chartered AccountantMEHTA JOSHI & COMPANY
Chartered AccountantMGM & Company
PartnerRole in project
Windsor Shelters-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Apr 2025

Documents filed115

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 I Bld Architect Certificate RERA June-2025 .pdf18 Oct 2025
Withdrawal Update Form 2File: ENGG CERTIFICATE I BLDG SEP 2025.pdf18 Oct 2025
Withdrawal Update Form 3File: CA CERTIFICATE I BLDG SEP 2025.pdf18 Oct 2025
Withdrawal Update Form 1File: Form 1 I Bld Architect Certificate RERA June-2025 .pdf13 Oct 2025
Withdrawal Update Form 2File: FORM 2 ENGINNER CERTIFICATE I BLDG-JUNE-2025.pdf13 Oct 2025
Withdrawal Update Form 3File: MGM Form 3 I Bld June 2025.pdf13 Oct 2025
Form 1File: Form 1 I Bld Architect Certificate RERA June-2025 .pdf23 Jul 2025
Form 2File: FORM 2 ENGINNER CERTIFICATE I BLDG-JUNE-2025.pdf23 Jul 2025
Form 3File: MGM Form 3 I Bld June 2025.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE I BLDG JUNE -2025.pdf23 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert I bld March 2025.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Rera Form 3 - I Bld Mar 2025.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure I wing Mar 2025.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: I Bld Eng cert Quality assurance Mar 2025.pdf19 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: I Bld Form 5 (2024-2025).pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: I bld Engineer Cert Mar 2025.pdf18 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Complition Certificate I Bld.pdf3 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Complition Certificate I Bld.pdf3 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: I wing Architect Cert - Dec 2024.pdf14 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: I Wing CA certificate - Dec 2024_.pdf14 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: I wing Engineer Cert- Dec 2024.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: I wing disclosure- Dec 2024.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: I wing Architect Cert - Dec 2024.pdf14 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: I Wing CA certificate - Dec 2024_.pdf14 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: I wing Engineer Cert- Dec 2024.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: I wing disclosure- Dec 2024.pdf14 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA - I wing Sep 2024.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert - I wing Sep 2024.pdf11 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure - I wing Sep 2024.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert I wing Sep 2024.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert I wing Sep 2024.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA - I wing Sep 2024.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert - I wing Sep 2024.pdf11 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure - I wing Sep 2024.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert I wing Sep 2024.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA - I wing Sep 2024.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert - I wing Sep 2024.pdf11 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure - I wing Sep 2024.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert I bld Mar 2024.pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate I wing June 24.pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: I wing Disclosure June 24.pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate I wing Jun 2024.pdf12 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: WINDSOR SHELTERS FORM 3 CA CERTIFICATE JUNE 24 Q1.pdf12 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2AIWING.pdf20 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA_Certificate.pdf18 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA_Certificate.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Certificate.pdf15 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclouser .pdf15 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MGM Co _compressed (1).pdf15 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MGM Co _compressed (1).pdf15 Apr 2024
Other - LegalFile: Anexure A Declaration cum Undertaking RERA I Bld .pdf15 Feb 2024
Other - LegalFile: Anexure A Declaration cum Undertaking RERA I Bld .pdf15 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WINDSOR COUNTY I BULDING RERA 20 JAN 2024.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2 - I wing Dec 23.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2 - I wing Dec 23.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate Form 3.PDF19 Jan 2024
Disclosure of sold/ booked inventoryFile: DISCLOUSURE SOLD DEC23.pdf18 Jan 2024
Other - FinanceFile: LO BANK DETAILS DECLARATION.pdf18 Jan 2024
Proforma of Agreement for saleFile: RERA DRAFT AGREEMENT.pdf30 Dec 2023
Proforma of Agreement for saleFile: RERA DRAFT AGREEMENT.pdf30 Dec 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation Certificate.pdf30 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1 September 2023.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2 September 2023.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold - Booked Inventory Sept 2023.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 Sept 2023_compressed.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Discloser June 2023.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1.pdf25 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 250923_compressed.pdf25 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Form 2A C.pdf25 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Quality Form 2A.pdf25 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3.pdf25 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: mahesh rathi.pdf22 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: shriniwas raskonda.pdf22 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 (22-23).PDF22 Sep 2023
Details of encumbrances concerned to FinanceFile: encumbrances certificate i wing.pdf20 Sep 2023
Details of encumbrances concerned to LegalFile: encumbrances certificate i wing.pdf20 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf20 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf20 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cirtificate Form No 3.pdf20 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Certificate Form 5 FY 22 - 23 Compress.pdf16 Feb 2023

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Windsor County phase-1Ambegaon Bk323CompletedDec 2015Late, Apr 2016
Maple woodz phase-1wagholi258CompletedJun 2015Late, Nov 2015

How this compares with Pune

84%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Windsor County Phase IV Wing I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ambegaon Bk.13,700+ in Pune

2 kmWindsor County Phase IV Completed 163Lapsed / revoked 118Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: Windsor Shelters

Windsor Shelters has 5 registrations on MahaRERA, including Windsor County phase-2 and Windsor County Phase -3. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Windsor County Phase IV Wing I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Windsor County Phase IV Wing I is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Windsor County Phase IV Wing I?

The registered promoter entity is Windsor Shelters, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Windsor County Phase IV Wing I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Windsor County Phase IV Wing I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Windsor County Phase IV Wing I?

The professionals named in the filing: Architect: Viinod Khanjode; Engineer: CHETAN PANDIT; Engineer: SHASHIKANT WAIKAR; Engineer: Arun Ghokhale; Chartered Accountant: MEHTA JOSHI & COMPANY; Chartered Accountant: MGM & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Windsor County Phase IV Wing I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Windsor County Phase IV Wing I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Windsor County Phase IV Wing I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.