Windsor County Phase IV Wing H
RG-MH-38833 · RERA P52100052041 · Last updated on MahaRERA portal: 18 Oct 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 6 months past the filed date
- Litigation declared, 2 cases
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Windsor County Phase IV Wing H is a Residential / Group Housing project by Windsor Shelters in Pune, Maharashtra, registered with MahaRERA as P52100052041 on 19 Jul 2023. Possession was promised by 30 Apr 2026 and is now 6 months past that date. 46 of the 124 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameWindsor County Phase IV Wing H
- TypeResidential / Group Housing
- Location
- Taware Colony
- Araneshwar
- AMBEGAON Bk
- Haveli
- Pune
- 411046
- Pincode411046
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100052041
- ReraGenie IDRG-MH-38833
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Jul 2023
- Promised completion30 Apr 2026
- Revised completionNone
- Buildings1 building record
- Documents filed102 files
Current status
Figures as on 18 Oct 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Windsor County Phase IV Wing H | NA | 11 | 11 | 80 | 44 | 124 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
Windsor County Phase IV Wing H: 87% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Progress on shared amenities15
As on 18 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 95% |
| Water Supply | Yes | 85% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 80% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 90% |
| Fire protection and fire safety requirements | Yes | 95% |
| Electrical meter room, sub-station, receiving station | Yes | 95% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 98% |
Parking filed5
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership17
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MR. MAHESH T RATHI | Pune (M Corp.) | Pune |
| MR. SHRINIWAS L RASKONDA | Pune (M Corp.) | Pune |
| Shriniwas Laxman Raskonda | AMBEGAON Bk | Pune |
| Mahesh Tejraj Rathi | AMBEGAON Bk | Pune |
| SHARAD DIGAMBAR KALBHOR | Chinchwad | Pune |
| AJAY ASHOK BASWEKAR | Dhankawadi | Pune |
| SHYAM VINAYAK NARWA | Peth | Pune |
| UDAY SAMBHAJI JAGTAP | Dhankawadi | Pune |
| SHWETA SHRINIWAS RASKONDA | Market Yard | Pune |
| ASHWINI AJAY BASWEKAR | Dhankawadi | Pune |
| CHAITRALI UDAY JAGTAP | Dhankawadi | Pune |
| KUSUM DIGAMBER KALBHOR | Chinchwad | Pune |
| SAPNA MAHESH RATHI | Pashan | Pune |
| MAHESH NARSING WABLE | Dhankawadi | Pune |
| VASANT ANANDRAO RAMPURE | Dhankawadi | Pune |
| ATUL VASANTRAO RAMPURE | Dhankawadi | Pune |
| AMIT VASANTRAO RAMPURE | Dhankawadi | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Windsor County Phase IV Wing H | NA | Rs 25.38 cr | Rs 25.38 cr |
| - | NA | Rs 1.78 cr | Rs 1.78 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vinod Khanjode |
| Engineer | Arun Ghokhale |
| Engineer | cHETAN pANDIT |
| Engineer | SHASHIKANT WAIKAR |
| Chartered Accountant | Mukesh Jain |
| Chartered Accountant | MEHTA JOSHI & COMPANY |
| Partner | Role in project |
|---|---|
| Windsor Shelters | - |
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 293/2011/2011 | CIVIL COURT PUNE | PENDING |
| 293/2011/2011 | 69-Judge small causes court Pune | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Jul 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Mar 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed102
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 H Bld Architect Certificate RERA June-2025.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE H BLDG SEP 2025.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: CA CERITIFICATE H BLDG SEP 2025.pdf | 18 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 H Bld Architect Certificate RERA June-2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: FORM 2 ENGINNER CERTIFICATE H BLDG-JUNE-2025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: MGM Form 3 H Bld June 2025.pdf | 13 Oct 2025 |
| Form 1File: Form 1 H Bld Architect Certificate RERA June-2025.pdf | 23 Jul 2025 |
| Form 2File: FORM 2 ENGINNER CERTIFICATE H BLDG-JUNE-2025.pdf | 23 Jul 2025 |
| Form 3File: MGM Form 3 H Bld June 2025.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE H BLDG JUNE -2025.pdf | 23 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert H Bld Mar 2025.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Rera Form 3 H Bld Mar 2025.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Cert H Bld Mar 2025.pdf | 19 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: H Bld Eng Cert Quality assurance Mar 2025.pdf | 19 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 H wing 2023-2024 (1).pdf | 19 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: H Bld Form 5 (2024-2025).pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: H bld Engineer cert Mar 2025.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: H wing Architect Cert-Dec 2024.pdf | 14 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: H wing CA Certificate-Dec 2024_.pdf | 14 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: H wing Engineer Cert-Dec 2024.pdf | 14 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: H wing Disclosure - Dec 2024.pdf | 14 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: H wing Architect Cert-Dec 2024.pdf | 14 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: H wing CA Certificate-Dec 2024_.pdf | 14 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: H wing Engineer Cert-Dec 2024.pdf | 14 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: H wing Disclosure - Dec 2024.pdf | 14 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate 2024_compressed (1).pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 2024.pdf | 20 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOUSRE SEPT24.pdf | 20 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate 2024_compressed (1).pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 2024.pdf | 20 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOUSRE SEPT24.pdf | 20 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate H wing - Sep 2024.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate H wing - Sep 2024.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect file.pdf | 17 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate H wing June 2024.pdf | 16 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure H wing June 2024.pdf | 16 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate H wing June 2024.pdf | 16 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE (2).pdf | 20 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM2AWINGH.pdf | 20 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM2AWINGH.pdf | 20 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA_Certificate_Rera.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGGCERTIFICATEMARCH24HBLDG.pdf | 19 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOUSURE H WING MARCH24.pdf | 18 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate H March 24.pdf | 18 Apr 2024 |
| Other - LegalFile: Allotment cum Declaration.pdf | 15 Mar 2024 |
| Other - LegalFile: Annexture A Declaration Cum Undertaking H bld .pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE DEC23.pdf | 18 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE DEC 23.pdf | 18 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD INVENTORY DEC23_compressed.pdf | 18 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 DEC23.pdf | 18 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 5 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2.pdf | 5 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY.pdf | 5 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 .pdf | 5 Jan 2024 |
| Other - TechnicalFile: Appedex F OC Copy.pdf | 13 Jul 2023 |
| Other - TechnicalFile: Appedex F OC Copy.pdf | 13 Jul 2023 |
| Layout approvalFile: 2 Copy of Layout Approval (in case of layout).pdf | 11 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: 2 Copy of Layout Approval (in case of layout).pdf | 11 Jul 2023 |
| Layout approvalFile: Architect Affidavit cum Declaration of Plot Area.pdf | 7 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: Architect Affidavit cum Declaration of Plot Area.pdf | 7 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: decleration of Commencement certificate.pdf | 7 Jul 2023 |
| Other - TechnicalFile: decleration of Commencement certificate.pdf | 7 Jul 2023 |
| Other - TechnicalFile: Architect Affidavit cum Declaration of Plot Area.pdf | 7 Jul 2023 |
| Other - TechnicalFile: WS Declaration for Area.pdf | 7 Jul 2023 |
| Declaration about Commencement CertificateFile: Format D.pdf | 27 Jun 2023 |
| Declaration in FORM BFile: Affidavit cum Declaration Form B_compressed.pdf | 27 Jun 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation of Agreement.pdf | 21 Jun 2023 |
| Proforma of Agreement for saleFile: Final draft agreement H wing.pdf | 20 Jun 2023 |
| Copy of the legal title reportFile: Affidavit Cum Declaration RERA.pdf | 8 Jun 2023 |
| Other - LegalFile: Affidavit cum Declaration Form B_compressed.pdf | 8 Jun 2023 |
| Other - LegalFile: Final draft agreement for H wing (1).pdf | 8 Jun 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: WC Society formation Certifiacte_compressed.pdf | 7 Jun 2023 |
| Copy of the legal title reportFile: Title Report Rera.PDF | 11 May 2023 |
| Copy of the legal title reportFile: Title Report 2_compressed.pdf | 11 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3_compressed.pdf | 11 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Rera.pdf | 28 Apr 2023 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 28 Apr 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment Letter.pdf | 28 Apr 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Discloser of Intrest Annexure A.pdf | 12 Apr 2023 |
| CERSAI detailsFile: Cersai Report.pdf | 11 Apr 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Windsor County phase-1 | Ambegaon Bk | 323 | Completed | Dec 2015 | Late, Apr 2016 |
| Maple woodz phase-1 | wagholi | 258 | Completed | Jun 2015 | Late, Nov 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 102 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Windsor County Phase IV Wing H on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Araneshwar13,700+ in Pune
Filed coordinates, straight-line distance. 192 registered projects within 2 km.
Sai Nagari Phase I
Saikedareshwar Developers LLP
SAI NAGARI Phase V
Saikedareshwar Developers LLP
Sai Nagari Phase II
Saikedareshwar Developers LLP
Sai Nagari Phase IV
Saikedareshwar Developers LLP
Sai Nagari Phase III
Saikedareshwar Developers LLP
Bella Casa - Phase 1
Kakkad Infra LLP
Builder: Windsor Shelters
Windsor Shelters has 5 registrations on MahaRERA, including Windsor County phase-2 and Windsor County Phase -3. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Windsor County Phase IV Wing H shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Windsor County Phase IV Wing H is delayed beyond 30 Apr 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Windsor County Phase IV Wing H?
The registered promoter entity is Windsor Shelters, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Windsor County Phase IV Wing H?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Windsor County Phase IV Wing H?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Windsor County Phase IV Wing H?
The professionals named in the filing: Architect: Vinod Khanjode; Engineer: Arun Ghokhale; Engineer: cHETAN pANDIT; Engineer: SHASHIKANT WAIKAR; Chartered Accountant: Mukesh Jain; Chartered Accountant: MEHTA JOSHI & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Windsor County Phase IV Wing H?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.