Home / Browse projects / Bengaluru Rural, Karnataka / WHISPERS OF BLISS
WHISPERS OF BLISS
RG-KA-89189 · RERA PRM/KA/RERA/1250/304/PR/110725/007910 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
WHISPERS OF BLISS is a Residential/Group Housing project by VENKATESWARA CREATORS in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/110725/007910 on 11 Jul 2025. Possession is promised by 15 Dec 2026. 1 of the 12 units on this registration are recorded sold or booked, and 8 of 17 construction stages are filed complete.
At a glance
Project
- NameWHISPERS OF BLISS
- TypeResidential/Group Housing
- Location
- Hosakote
- Bengaluru Rural
- PincodeNot stated
- RERA no.PRM/KA/RERA/1250/304/PR/110725/007910
- ReraGenie IDRG-KA-89189
Builder
- NameVENKATESWARA CREATORS
- Entity typePartnership Firm
- GSTIN29AAWFV8082F1Z9
- Authorized SignatoryGONUGUNTLA SOMASEKHARA RAO
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on11 Jul 2025
- Promised completion15 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed75 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WHISPERS OF BLISS | - | - | - | 12 | 0 | 12 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 17 construction stages are filed complete. The stage furthest along is Joinery: Doors, at 90%.
Building: 84% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| Sump Water facility | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 90% |
| Basic work of Water supply, Sanitary and Electrification | 90% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 90% |
| Railing and Grill fixing | 85% |
| Electrification, Water supply and Sanitary Finishing | 85% |
| Painting | 85% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 30% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 65% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 50% |
| Sewage and Drainage System | Yes | 50% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 50% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 50% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 35% |
| Electricity supply transformer and substation | Yes | 50% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 60% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 50% |
| Electricity | Yes | 50% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 55% |
| Club House | Yes | 75% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | Yes | 0% |
| Power Backup | Yes | 50% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 50% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 95% |
| Lifts | Yes | 60% |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | Yes | 95% |
| Outer Wall | Yes | 60% |
| Open parking areas | Yes | 60% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 50% |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| RAMESH REDDY | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 10.10 cr | Rs 6.00 cr |
| On-site expenditure-Site Overhead | Rs 80.00 lakh | Rs 49.33 lakh |
| Payment of taxes | Rs 60.00 lakh | Rs 11.00 lakh |
| On-site expenditure-Salaries of workers | Rs 50.00 lakh | Rs 3.15 lakh |
| On-site expenditure-Consultants Fees | Rs 32.72 lakh | Rs 15.72 lakh |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 20.00 lakh | Rs 4.39 lakh |
| Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for construction | Rs 8.00 lakh | Rs 15.30 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RINISH VALSAN |
| Engineer | MADAMANCHI SURENDRANADH |
| Chartered Accountant | KAMBALA VINEETH REDDY |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed75
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/110725/007910 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 _compressed.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: whispersofbliss_arch cert.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: engineer cert.pdf | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Rera form 4 signed q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Whispersofbliss_arch cert_june.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Whispersofbliss_eng cert_june.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Rera form 4 whispers of bliss final _compressed.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Whispersofbliss_arch cert.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: whispers of bliss (1).pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Venkateswara creators_0001.pdf | 15 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect certificate_whispers of bliss_Dec.pdf | 15 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate_whispers of bliss_Dec.pdf | 15 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 15 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 15 Jan 2026 |
| RELEASE DEEDFile: release deed.pdf | 1 Jul 2025 |
| Partitition DeedFile: PARTITION DEED.pdf | 1 Jul 2025 |
| Title DeedFile: sale deed 91.pdf | 1 Jul 2025 |
| Proforma AgreementFile: draft sale agreement new.pdf | 1 Jul 2025 |
| Proforma Leter of allotmentFile: draft allotment letter.pdf | 1 Jul 2025 |
| STP DrawingFile: stpdrawingsigned.pdf | 1 Jul 2025 |
| Cost of constructionFile: cost estimation whisperofbills.pdf | 1 Jul 2025 |
| Land CostFile: land cost caluclation.pdf | 1 Jul 2025 |
| Non Litigation AffidavitFile: NON - LITIGATION AFFIDAVIT.pdf | 1 Jul 2025 |
| Engineer CertificateFile: engineer certificate.pdf | 1 Jul 2025 |
| bescom nocFile: BESCOM Noc Venkateshwar creaters.pdf | 1 Jul 2025 |
| RTC, survey 158/24 | - |
| Mutation, survey 158/24 | - |
| Encumbrance Certificate, survey 158/24 | - |
| Conversion/Alienation Order, survey 158/24 | - |
| JDA, survey 158/24 | - |
| Khatha, survey 158/24 | - |
| Registration CertificateFile: Form C_Venkateswara.pdf | - |
| GST CertificateFile: gst certificate.pdf | - |
| Partnership DeedFile: partnership deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: FORM1_compressed.pdf | - |
| Certificate issued by Architect Form 2File: Whispers of Bilss_Form2 RERA cert.pdf | - |
| Certificate issued by Engineer Form 3File: whispers of bliss Eng cert.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: NON - LITIGATION AFFIDAVIT.pdf | - |
| Balance Sheet 2023 - 2024File: Balance sheet Fy 2023-24.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: PL FY 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: ACK924255081240724.pdf | - |
| COMMENCEMENT CERTIFICATE | - |
| plan approved | - |
| plan approved | - |
| Project constructions specifications | - |
| brochure | - |
| Sale Agreement Proforma | - |
| Allotment letter | - |
| FORM B - AFFIDAVIT CUM DECLARATION | - |
| SECTION 3 AFFIDAVIT | - |
| AFFIDAVIT CUM DECLARATION | - |
| SEARCH REPORT | - |
| WATER NOC | - |
| POLLUTION CONTROL BOARD NOC | - |
| no ptcl | - |
| PARTITION DEED | - |
| PDO FEES RECEIPT | - |
| SURVEY RECORDS | - |
| BUILDING PERMIT | - |
| RELEASE DEED AND SALE DEEDS | - |
| SINGLE SITE APPROVAL | - |
| CDP Plan | - |
| Village Map | - |
| FY 24-25 BS & PL | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Rural
Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.
Keep WHISPERS OF BLISS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Rural650+ in Bengaluru Rural
BARCA AT GODREJ MSR CITY
M S RAMAIAH VENTURES LLP
Ozone Urbana
Ozone Urbana Infra Developers Pvt Ltd
Pashmina Brookwoods
Shashwati Realty Pvt Ltd
Godrej Royale Woods
Godrej Projects North Star LLP
Prestige Jindal City-Phase II
PRESTIGE SOUTHCITY HOLDINGS
Provident Botanico
Provident Housing Limited
See every Bengaluru Rural project, with the district possession charts
Builder: VENKATESWARA CREATORS
VENKATESWARA CREATORS has 1 registration on RERA Karnataka, including WHISPERS OF BLISS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.
Frequently asked questions
What are my rights if WHISPERS OF BLISS is delayed beyond 15 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of WHISPERS OF BLISS?
The registered promoter entity is VENKATESWARA CREATORS, a partnership firm as per the filing. Its GSTIN 29AAWFV8082F1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in WHISPERS OF BLISS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at WHISPERS OF BLISS?
The professionals named in the filing: Architect: RINISH VALSAN; Engineer: MADAMANCHI SURENDRANADH; Chartered Accountant: KAMBALA VINEETH REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in WHISPERS OF BLISS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback