Home / Browse projects / Bengaluru Rural, Karnataka / Provident Botanico
Provident Botanico
RG-KA-65055 · RERA PRM/KA/RERA/1250/304/PR/210324/006726 · Last updated on RERA Karnataka portal: 31 Mar 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Provident Botanico is a Residential/Group Housing project by Provident Housing Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/210324/006726 on 21 Mar 2024. Possession is promised by 30 Sep 2028. 1,202 of the 1,275 units on this registration are recorded sold or booked, and 5 of 17 construction stages are filed complete.
At a glance
Project
- NameProvident Botanico
- TypeResidential/Group Housing
- Location
- Hosakote
- Bengaluru Rural
- 562114
- Pincode562114
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1250/304/PR/210324/006726
- ReraGenie IDRG-KA-65055
Builder
- NameProvident Housing Limited
- Entity typeCompany
- CINU45200KA2008PLC048273
- GSTIN29AAECP8877D1ZW
- Authorized SignatoryJatin Ujjini C S
- CeoMallanna Sasalu
- DirectorsNani R Choksey, Ashish R Puravankara
- Project HeadKarthikeyan
- Other registrations11 more →
- No longer live1 withdrawn or revoked
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on21 Mar 2024
- Promised completion30 Sep 2028
- Revised completionNone
- Buildings9 building records
- Documents filed256 files
Current status
Figures as on 31 Mar 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 1 | - | - | - | 148 | 0 | 148 |
| Tower 2 | - | - | - | 148 | 0 | 148 |
| Tower 3 | - | - | - | 149 | 0 | 149 |
| Tower 4 | - | - | - | 138 | 0 | 138 |
| Tower 5 | - | - | - | 128 | 0 | 128 |
| Tower 6 | - | - | - | 128 | 0 | 128 |
| Tower 7 | - | - | - | 148 | 0 | 148 |
| Tower 8 | - | - | - | 144 | 0 | 144 |
| Tower 9 | - | - | - | 144 | 0 | 144 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 31 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 17 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 53%.
Building: 39% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 53% |
| Masonry Construction | 53% |
| Plastering inside , outside & Ceiling | 10% |
| Joinery: Doors, Windows, Ventilators etc | 10% |
| Basic work of Water supply, Sanitary and Electrification | 10% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 10% |
| Railing and Grill fixing | 10% |
| Electrification, Water supply and Sanitary Finishing | 10% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 31 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | Yes | 0% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership22
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| San Marina Infortech Pvt Ltd | - | - |
| Building Solutions And Co | - | - |
| San Marina Infortech Pvt Ltd | - | - |
| Building Solutions And Co | - | - |
| San Marina Infotech Pvt Ltd | - | - |
| Building Solutions And Co | - | - |
| Building Solutions And Co | - | - |
| San Marina Infotech Pvt Ltd | - | - |
| Building Solutions And Co | - | - |
| Building Solutions And Co | - | - |
| Susheel Rati | - | - |
| Sanmarina Infotech Pvt Ltd | - | - |
| Sanmarina Info Tech pvt Ltd | - | - |
| Sanmarina Infotech Pvt Ltd | - | - |
| Building Solution and Co | - | - |
| Building Solution and Co | - | - |
| Susheel rati | - | - |
| Sanmarina Infotech Pvt Ltd | - | - |
| Sanmarina Infotech Pvt Ltd | - | - |
| Sanmarina Infotech Pvt Ltd | - | - |
| Sanmarina Infotech Pvt Ltd | - | - |
| Soumya Nallari | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 474.33 cr | Rs 201.96 cr |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 91.58 cr | Rs 40.31 cr |
| On-site expenditure-Site Overhead | Rs 40.61 cr | Rs 26.02 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | INDRAJIT.S.KEMBHAVI |
| Engineer | H P Yogesh |
| Chartered Accountant | V D S R & CO LLP CHARTERED ACCOUNTANTS |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed256
As listed on the registration, under the names the promoter filed them with; the newest 80 of 256 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/210324/006726 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Botanico Form4 RERA Dec25_compressed.pdf | 31 Mar 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Botanico Architect Certificate Dec25_compressed.pdf | 31 Mar 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Botanico Engineer Certificate Dec25.pdf | 31 Mar 2026 |
| Hissa TippaniFile: 08 Hissa survey Tippani 257.pdf | 20 Mar 2024 |
| Architect Certificate with COAFile: Architect Certificate COA.pdf | 20 Mar 2024 |
| Agreement for saleFile: ATS - BOTANICO.pdf | 20 Mar 2024 |
| Bank AffidavitFile: Bank Affidavit.pdf | 20 Mar 2024 |
| BESCOM NOCFile: BESCOM Self Attested.pdf | 20 Mar 2024 |
| Carpet area and BHK BreakupsFile: Botanico Area Statement-signedoff 14-03-2024-.pdf | 20 Mar 2024 |
| Signed specificationsFile: Botanico Specification signedoff 14-03-2024.pdf | 20 Mar 2024 |
| CDP DemarcatedFile: CDP WITH BOUNDARY.pdf | 20 Mar 2024 |
| COnverion 257-13File: COnversion 257-13.pdf | 20 Mar 2024 |
| COnverion 257-14File: Conversion 257-14.pdf | 20 Mar 2024 |
| COnverion 257-15File: Conversion 257-15.pdf | 20 Mar 2024 |
| COnverion 257-18File: Conversion 257-18.pdf | 20 Mar 2024 |
| COnverion 257-16File: Conversion 257-16.pdf | 20 Mar 2024 |
| Environmental Clearence SEIAAFile: ECLSEIAA_219079_460734_SIA_KA_INFRA2_427128_2023.pdf | 20 Mar 2024 |
| Guildine Value land calculation self attestedFile: Guidline Value self attested.pdf | 20 Mar 2024 |
| KSPCB NOCFile: KSPCB.pdf | 20 Mar 2024 |
| PAN Self AttestedFile: PHL PAN self Attested.pdf | 20 Mar 2024 |
| Sec 3 AffidavitFile: Sec 3 Affidavit Final.pdf | 20 Mar 2024 |
| Cost of Construction calculation SignedFile: Signed cost of construction.pdf | 20 Mar 2024 |
| EC 278-1File: Sy No 278 - 1 EC.pdf | 20 Mar 2024 |
| Village MapFile: Village map full.pdf | 20 Mar 2024 |
| Demarcated Village MapFile: PROVIDENT BOTANICO VILLAGE MAP.pdf | 20 Mar 2024 |
| Form 1File: Form -1 Provident Botanica sd.pdf | 20 Mar 2024 |
| JDA 257-19File: Sy no 257-19 JDA and POA.pdf | 20 Mar 2024 |
| 257-20 RTCFile: 257-20 RTC.pdf | 20 Mar 2024 |
| 36P 38 Sy No 278 Survey RecordFile: Survey record old No 36-P38 to Sy No 278.pdf | 20 Mar 2024 |
| Airport NOCFile: Airport NOC- BIAL.pdf | 20 Mar 2024 |
| STPFile: STP KSPCB Drawing_compressed.pdf | 20 Mar 2024 |
| Allotment LetterFile: ALLOTMENT LETTER BOTANICO (1).pdf | 20 Mar 2024 |
| ZR STRRFile: ZR STRR Nala_compressed.pdf | 20 Mar 2024 |
| Development PlanFile: Modified Development Sanction Plan.jpg | 20 Mar 2024 |
| RTC, survey 257/5 | - |
| Mutation, survey 257/5 | - |
| Encumbrance Certificate, survey 257/5 | - |
| Conversion/Alienation Order, survey 257/5 | - |
| Sale/Title/Gift Deed, survey 257/5 | - |
| JDA, survey 257/5 | - |
| Khatha, survey 257/5 | - |
| RTC, survey 257/6 | - |
| Mutation, survey 257/6 | - |
| Encumbrance Certificate, survey 257/6 | - |
| Conversion/Alienation Order, survey 257/6 | - |
| Sale/Title/Gift Deed, survey 257/6 | - |
| JDA, survey 257/6 | - |
| Khatha, survey 257/6 | - |
| RTC, survey 257/7 | - |
| Mutation, survey 257/7 | - |
| Encumbrance Certificate, survey 257/7 | - |
| Conversion/Alienation Order, survey 257/7 | - |
| Sale/Title/Gift Deed, survey 257/7 | - |
| JDA, survey 257/7 | - |
| Khatha, survey 257/7 | - |
| RTC, survey 257/8 | - |
| Mutation, survey 257/8 | - |
| Encumbrance Certificate, survey 257/8 | - |
| Conversion/Alienation Order, survey 257/8 | - |
| Sale/Title/Gift Deed, survey 257/8 | - |
| JDA, survey 257/8 | - |
| Khatha, survey 257/8 | - |
| RTC, survey 257/9 | - |
| Mutation, survey 257/9 | - |
| Encumbrance Certificate, survey 257/9 | - |
| Conversion/Alienation Order, survey 257/9 | - |
| Sale/Title/Gift Deed, survey 257/9 | - |
| JDA, survey 257/9 | - |
| Khatha, survey 257/9 | - |
| RTC, survey 257/10 | - |
| Mutation, survey 257/10 | - |
| Encumbrance Certificate, survey 257/10 | - |
| Conversion/Alienation Order, survey 257/10 | - |
| Sale/Title/Gift Deed, survey 257/10 | - |
| JDA, survey 257/10 | - |
| Khatha, survey 257/10 | - |
| RTC, survey 257/13 | - |
| Mutation, survey 257/13 | - |
| Encumbrance Certificate, survey 257/13 | - |
| Conversion/Alienation Order, survey 257/13 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Rural
Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.
Keep Provident Botanico on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Rural650+ in Bengaluru Rural
Filed coordinates, straight-line distance. 22 registered projects within 2 km.
GODREJ PARKSHIRE
Godrej Properties Limited
Sowparnika The Native
SOWPARNIKA HOMES PRIVATE LIMITED
SOWPARNIKA EUPHORIA IN THE EAST
SOWPARNIKA HOMES PRIVATE LIMITED
Brillio and Commercial at Brigade Valencia
Brigade Enterprises Ltd
Sowparnika Whispering Petals
SOWPARNIKA GREEN MEADOWS PRIVATE LIMITED
ONE RESIDENCES AT SOBHA ONE WORLD Ph5 W9,10,11
SOBHA LIMITED
See every Bengaluru Rural project, with the district possession charts
Builder: Provident Housing Limited
Provident Housing Limited has 12 registrations on RERA Karnataka, including Provident Capella 1 and Provident Capella 2. Its filings declare 6 earlier projects, 6 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.
Frequently asked questions
What are my rights if Provident Botanico is delayed beyond 30 Sep 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Provident Botanico?
The registered promoter entity is Provident Housing Limited, a company as per the filing. Its CIN U45200KA2008PLC048273 and GSTIN 29AAECP8877D1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Provident Botanico?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Provident Botanico?
The professionals named in the filing: Architect: INDRAJIT.S.KEMBHAVI; Engineer: H P Yogesh; Chartered Accountant: V D S R & CO LLP CHARTERED ACCOUNTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Provident Botanico?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback