Godrej Royale Woods

By Godrej Projects North Star LLP

RG-KA-48767 · RERA PRM/KA/RERA/1250/303/PR/200515/003411 · Last updated on RERA Karnataka portal: 11 Mar 2020

Source: official RERA Karnataka filing

Red flags

  • 11 complaints at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Jan 2026Possession promisedmoved 9 months from the original
11Complaints at RERA Karnatakaon this registration
Jump to the 61 documents Report an error

Godrej Royale Woods is a Residential/Group Housing project by Godrej Projects North Star LLP in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/200515/003411 on 15 May 2020. Possession is promised by 29 Jan 2026. The completion date has moved by 9 months from the original filing. 11 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Royale Woods
  • TypeResidential/Group Housing
  • Location
    • Devanahalli
    • Bengaluru Rural
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/303/PR/200515/003411
  • ReraGenie IDRG-KA-48767

Builder

  • NameGodrej Projects North Star LLP
  • Entity typeOther
  • Authorized SignatoryUday Bhaskar
  • OthersAkila Jayaraman

Key dates

this monthRegisteredMay 2020First promiseApr 2025Revised toJan 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 May 2020
  • Promised completion29 Jan 2026
  • Revised completionRevised to 29 Jan 2026 (originally 29 Apr 2025)
  • Buildings6 building records
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 1 - PLUMERIA---2510251
TOWER 2 - MAHOGANY---3200320
TOWER 3 - RAINTREE---2980298
TOWER 4 - PINE---2980298
TOWER 5 - OAK---3200320
TOWER 6 - BANYAN---1910191

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 11 Mar 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 11 Mar 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area52,620 sq m
Named landowners1
LandownerVillageDistrict
Suresh Bhatia--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 476.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKarl Wadia
EngineerAmudhalingam S

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApr 2025 → Jan 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka11

Case no.ComplainantRespondentFiled
CMP/210322/0007815-Godrej Projects North Star LLP22/03/2021
CMP/210907/0008310-Godrej Projects North Star LLP07/09/2021
00371/2024-Godrej Projects North Star LLP10/04/2024
00385/2024-Godrej Projects North Star LLP15/04/2024
00658/2024-Godrej Projects North Star LLP02/07/2024
00676/2024-Godrej Projects North Star LLP09/07/2024
00906/2024-Godrej Projects North Star LLP18/09/2024
00634/2026-Godrej Projects North Star LLP02/06/2026
00649/2026-Godrej Projects North Star LLP03/06/2026
00709/2026-Godrej Projects North Star LLP19/06/2026
00809/2026-Godrej Projects North Star LLP14/07/2026

Documents filed61

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/200515/003411 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Title Documents in respect of Sy.No. 63/1File: Final Title Document - 61, 63-1 & 63-2.pdf11 Mar 2020
Conversion Order - Sy.No. 60(p) and 63/1File: Conversion Order - 60 - 63-1.pdf11 Mar 2020
Admission Deed - Owner has brought Land and Developer is Constructing in LLPFile: Admission Deed-22.03.2018.pdf11 Mar 2020
Latest Upto date ECFile: Latest EC.pdf11 Mar 2020
Approved Ground Floor PlanFile: Ground Floor-Layout.pdf11 Mar 2020
Approved Typical Floor PlanFile: Typical Floor Level Plan.pdf11 Mar 2020
Approved Section and ElevationFile: section.pdf11 Mar 2020
Legal Opinion - Sy.No. 60File: Survey_No_60.pdf11 Mar 2020
Legal Opinion - Sy.No. 61File: Survey_No_61.pdf11 Mar 2020
Legal Opinion - Sy.No. 63/1File: Survey_No_63_1.pdf11 Mar 2020
Legal Opinion - Sy.No. 63/2File: Survey_No_63_2.pdf11 Mar 2020
Legal Opinion - Sy.No. 64/1File: Survey_No_64_1.pdf11 Mar 2020
Legal Opinion - Sy.No. 65/1File: Survey_No_65_1.pdf11 Mar 2020
DP Approval letter-
Approved DP-
Agreemnet For Sale-
Agreemnet For Sale-
Sale Deeds and RTC-
Section-
Approved DP-
Allotment Letter-
Project Brochure -
Projects Specification-
EC 01-
Affidavit - No Advertisement-
Joint Affidavit-
Katha-
Development Agreement-
Sale Deeds-
Conversion orders Chikkasanne-
Relinquishment Deed-
Fire NoC Bhatia-
Batia Property AAI NOC-
Panchayath - Water Letter-
MoEF EC-
Unnamed document-
Section-
Section-
Balance Sheet 2018 - 2019File: Balance Sheet 2018-19.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Profit Loss 2018-19.pdf-
Cash Flow Statement 2018 - 2019File: Cash Floor 2018-19.pdf-
Auditor's Report 2018 - 2019File: Auditor Report .pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR AY-2018-19.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR AY 2017-18.pdf-
Form-B-
Prospectus/BrochureFile: Brochure.pdf-
Advertisement Copy 1File: Advertisment Copy.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1250_303_PR_200515_003411.xlsx-
Loan raised documentFile: BANK NOC.pdf-
Stability CertificateFile: Stability Certificate.pdf-
NOC issued by the Fire Force department after completion of workFile: Fire NOC.pdf-
Occupancy CertificateFile: OC - GODREJ ROYALE WOODS.pdf-
Consent for operation issued by KSPCBFile: KSPCB NOC.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift License.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM - NOC.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Water NOC.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect Form-5 Closure Certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Form-4 CC CA Certificate.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Closure Affidavit.pdf-
Engineer Form-6 Closure CertificateFile: Engineer Form-6 Closure Certificate.pdf-
AAI NOCFile: AAI NOC.pdf-

How this compares with Bengaluru Rural

20%of Bengaluru Rural projects moved their completion datethis one moved by 9 months
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Godrej Royale Woods on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmGodrej Royale WoodsOther 31Dot size: filed unitsN

Filed coordinates, straight-line distance. 31 registered projects within 2 km.

Builder: Godrej Projects North Star LLP

Godrej Projects North Star LLP has 1 registration on RERA Karnataka, including Godrej Royale Woods. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Godrej Royale Woods is delayed beyond 29 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Godrej Royale Woods?

The registered promoter entity is Godrej Projects North Star LLP. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Godrej Royale Woods?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Royale Woods?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Godrej Royale Woods?

The professionals named in the filing: Architect: Karl Wadia; Engineer: Amudhalingam S. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Royale Woods?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Royale Woods. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Royale Woods to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.