Home / Browse projects / Chandrapur, Maharashtra / VST5-TULIP

Registration lapsed No litigation declared Residential / Group Housing project

VST5-TULIP

By VIDARBHA TOWN DEVELOPERS

RG-MH-43498 · RERA P50900017446 · Last updated on MahaRERA portal: 14 Apr 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 43 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Chandrapur registration emailed to you, free during the pilot beta.
Mar 2023Possession promised43 months past this date
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 36 documents Report an error

VST5-TULIP is a Residential / Group Housing project by VIDARBHA TOWN DEVELOPERS in Chandrapur, Maharashtra, registered with MahaRERA as P50900017446 on 13 Aug 2018. Possession was promised by 30 Mar 2023 and is now 43 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameVST5-TULIP
  • TypeResidential / Group Housing
  • Location
    • VIDARBHA ESTATE 5 MOUZA DEVADA
    • DEVADA
    • Dewada
    • Chandrapur
    • 442402
  • Pincode442402
  • RERA no.P50900017446
  • ReraGenie IDRG-MH-43498

Builder

  • NameVIDARBHA TOWN DEVELOPERS
  • Entity typePartnership
  • PartnerAMIT AMAL KARMAKAR
  • Other registrations14 more →
  • Completed6 of 15
  • No longer live9 lapsed, de-registered or revoked

Key dates

43 months past promisethis monthRegisteredAug 2018First promiseMar 2022Revised toMar 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on13 Aug 2018
  • Promised completion30 Mar 2023
  • Revised completionRevised to 30 Mar 2023 (originally 30 Mar 2022)
  • Buildings2 building records
  • Documents filed36 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TULIP-1NA30000
TULIP-2NA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Apr 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

TULIP-1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TULIP-2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Apr 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Open Space10
BuildingOpen SpaceTotal
TULIP-155
TULIP-255

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,823 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1823.0
Proposed, not sanctioned1,823 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWADI NAGPUR

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVINIT SHRIVASTAVA
PartnerRole in project
VIDARBHA TOWN DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50900011642Mar 2022 → Mar 2023

Reason as filed by the promoter1) Major Setback for delay for project is due to Lockdown for corona Pandemic. As promoter and our staff were positive of corona and was unable to attend the office due to quarantine period and severe fever. 2) Our Project is in remote area in Chandrapur, which creates lots of problems for procurements of labours. Labour’s working on the site returned to their villages and staying away from work sites due to fear over corona virus infection. After The step -by-step, upliftment of lockdown norms, our labours force were not willing to come at site for working due to fear of corona diseases. 3) T

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jul 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jul 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Jul 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed36

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: TULIP FORM -1 ARTICHECT CERTIFICATE.pdf14 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM NO 2 NEW.pdf14 Apr 2022
CERSAI detailsFile: TULIP CERSAI REPORT.pdf14 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Certificate136539.pdf14 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: vst-5 tulip 20-21.pdf9 Sep 2021
Declaration about Commencement CertificateFile: circular no 32 tulip.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: TULIP QUATER 1 30-06-2019.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: TULIP QUATER 2 30-09-2019.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: TULIP QUATER 3 31-12-2019.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: TULIP QUATER 4 31-03-2020.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: TULIP QUATER 1 30-06-2020.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: TULIP QUATER 2 30-09-2020.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: TULIP QUATER 3 31-12-2020.pdf23 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: TULIP QUATER 4 31-03-2021.pdf23 Aug 2021
Disclosure of sold/ booked inventoryFile: circular no 29 tulip.pdf23 Aug 2021
Certificates of CA (Form 3)File: Rera Form 3 Certificate - TULIP PROJECT.pdf23 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Rera Form 5 Certificate 18-19 - TULIP PROJECT.pdf23 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Rera Form 5 Certificate 19-20 - TULIP PROJECT.pdf23 Aug 2021
Building plan approvalFile: DOD.pdf7 Jul 2018
Layout approvalFile: AMALGAMTION PLAN.pdf7 Jul 2018
Layout approvalFile: AMALGAMATION ORDER.pdf7 Jul 2018
Building plan approvalFile: BUILDING PERMIT.pdf7 Jul 2018
Building plan approvalFile: BUILDING SANCTION PLAN.pdf7 Jul 2018
Building plan approvalFile: BUILDING SANCTION PLAN 1.pdf7 Jul 2018
Copy of the legal title reportFile: ADVOCATE REPORT.pdf7 Jul 2018
Details of encumbrancesFile: ADVOCATE REPORT.pdf7 Jul 2018
Copy of Layout Approval (in case of layout)File: AMALGAMTION PLAN.pdf7 Jul 2018
Copy of Layout Approval (in case of layout)File: AMALGAMATION ORDER.pdf7 Jul 2018
Building Plan Approval (IOD)File: DOD.pdf7 Jul 2018
Building Plan Approval (IOD)File: BUILDING PERMIT.pdf7 Jul 2018
Building Plan Approval (IOD)File: BUILDING SANCTION PLAN.pdf7 Jul 2018
Building Plan Approval (IOD)File: BUILDING SANCTION PLAN 1.pdf7 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: ADVOCATE REPORT.pdf7 Jul 2018
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION.pdf7 Jul 2018
Certificates of CA (Form 3)File: FORM NO 3 CA CERTIFICATE.pdf7 Jul 2018
Proforma of Allotment letterFile: LETTER OF ALLOTMENT.pdf7 Jul 2018

How this compares with Chandrapur

10%of Chandrapur projects moved their completion datethis one moved by 12 months
39%of Chandrapur registrations have lapsed or been cancelledthis one is among them

Computed across the 220+ Chandrapur projects on ReraGenie, from their own filings.

Keep VST5-TULIP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DEVADA220+ in Chandrapur

Builder: VIDARBHA TOWN DEVELOPERS

VIDARBHA TOWN DEVELOPERS has 15 registrations on MahaRERA, including VST3-AAKASH and VST3- AAKASJ GANGA 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Chandrapur district page.

Frequently asked questions

What does it mean that VST5-TULIP shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VST5-TULIP is delayed beyond 30 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VST5-TULIP?

The registered promoter entity is VIDARBHA TOWN DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VST5-TULIP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VST5-TULIP?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VST5-TULIP?

The professionals named in the filing: Architect: VINIT SHRIVASTAVA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VST5-TULIP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VST5-TULIP. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VST5-TULIP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.