Valid until 31 Mar 2023 Residential/Group Housing project

VRUNDAVAN RESIDENCY

By RADHE DEVELOPERS

RG-GJ-63798 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05346/EX1/101122 · Last updated on GujRERA portal: 30 Mar 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • Separate project account declared
Mar 2023Possession promisedmoved 6 months from the original
45 of 45Construction stages doneacross 6 buildings; every applicable stage filed complete
29 of 123Units unsoldnot recorded sold or booked
Jump to the 46 documents Report an error

VRUNDAVAN RESIDENCY is a Residential/Group Housing project by RADHE DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05346/EX1/101122 on 30 Apr 2019. Possession is promised by 31 Mar 2023. The completion date has moved by 6 months from the original filing. 94 of the 123 units on this registration are recorded sold or booked, and 45 of 45 construction stages are filed complete.

At a glance

Project

  • NameVRUNDAVAN RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • SURVEY NO 887
    • PLOT NO. 216
    • OPP. PANDAV VAN
    • VAVOL
    • Vavol
    • Gandhinagar
    • 382016
  • Pincode382016
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05346/EX1/101122
  • ReraGenie IDRG-GJ-63798

Builder

  • NameRADHE DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations8 more →
  • Past their filed date6

Key dates

this monthRegisteredApr 2019First promiseSep 2022Revised toMar 2023

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2023
  • Registered on30 Apr 2019
  • Promised completion31 Mar 2023
  • Revised completionRevised to 31 Mar 2023 (originally 1 Sep 2022)
  • Buildings6 building records
  • Documents filed46 files

Current status

76%94 of 123 units booked
93.8%Of the estimated cost spent so far

Figures as on 30 Mar 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING A---28028
WING B---28028
WING C---28028
UNIT 1 TO 9---909
UNIT 10 TO 21---12012
UNIT 22 TO 39---18018

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 30 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

45 of 45 construction stages are filed complete across 6 buildings.

WING A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
WING B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
WING C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
UNIT 1 TO 9100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
UNIT 10 TO 21100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
UNIT 22 TO 39100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 30 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,957 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 17.19 cr
Cost incurredRs 16.12 cr
Spent of the estimate93.75%
BuildingWingEstimatedIncurred
WING ANARs 2.87 crRs 2.69 cr
WING BNARs 2.87 crRs 2.69 cr
WING CNARs 2.87 crRs 2.69 cr
UNIT 1 TO 9NARs 2.87 crRs 2.69 cr
UNIT 10 TO 21NARs 2.87 crRs 2.69 cr
UNIT 22 TO 39NARs 2.87 crRs 2.69 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNIRMAN ASSOCIATES
Engineer912 CONSULTANTS

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05346/EX1/101122Applied Sep 2022; approved Nov 2022

Documents filed46

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05346/EX1/101122 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)30 Mar 2023
Engineer's certificate annexure30 Mar 2023
Accountant's certificate (Form 3)30 Mar 2023
Architect's certificate (Form 1)29 Mar 2023
Site photograph, WING A29 Mar 2023
Site photograph, WING B29 Mar 2023
Site photograph, WING C29 Mar 2023
Site photograph, UNIT 1 TO 929 Mar 2023
Site photograph, UNIT 10 TO 2129 Mar 2023
Site photograph, UNIT 22 TO 3929 Mar 2023
RERA registration certificate30 Apr 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

76%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 6 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep VRUNDAVAN RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vavol1,600+ in Gandhinagar

2 kmVRUNDAVAN RESIDENCYOther 80Dot size: filed unitsN

Filed coordinates, straight-line distance. 80 registered projects within 2 km.

Builder: RADHE DEVELOPERS

RADHE DEVELOPERS has 9 registrations on GujRERA, including RADHE HEIGHTS and RATNARAJ GREEN. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if VRUNDAVAN RESIDENCY is delayed beyond 31 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VRUNDAVAN RESIDENCY?

The registered promoter entity is RADHE DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VRUNDAVAN RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VRUNDAVAN RESIDENCY?

The professionals named in the filing: Architect: NIRMAN ASSOCIATES; Engineer: 912 CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRUNDAVAN RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRUNDAVAN RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRUNDAVAN RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.