VRUNDAVAN RESIDENCY
RG-GJ-63798 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05346/EX1/101122 · Last updated on GujRERA portal: 30 Mar 2023
Source: official GujRERA filing
Red flags
- Completion date moved by 6 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
VRUNDAVAN RESIDENCY is a Residential/Group Housing project by RADHE DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05346/EX1/101122 on 30 Apr 2019. Possession is promised by 31 Mar 2023. The completion date has moved by 6 months from the original filing. 94 of the 123 units on this registration are recorded sold or booked, and 45 of 45 construction stages are filed complete.
At a glance
Project
- NameVRUNDAVAN RESIDENCY
- TypeResidential/Group Housing
- Location
- SURVEY NO 887
- PLOT NO. 216
- OPP. PANDAV VAN
- VAVOL
- Vavol
- Gandhinagar
- 382016
- Pincode382016
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05346/EX1/101122
- ReraGenie IDRG-GJ-63798
Builder
- NameRADHE DEVELOPERS
- Entity typePARTNERSHIP FIRM
- Other registrations8 more →
- Past their filed date6
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Mar 2023
- Registered on30 Apr 2019
- Promised completion31 Mar 2023
- Revised completionRevised to 31 Mar 2023 (originally 1 Sep 2022)
- Buildings6 building records
- Documents filed46 files
Current status
Figures as on 30 Mar 2023, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | - | - | - | 28 | 0 | 28 |
| WING B | - | - | - | 28 | 0 | 28 |
| WING C | - | - | - | 28 | 0 | 28 |
| UNIT 1 TO 9 | - | - | - | 9 | 0 | 9 |
| UNIT 10 TO 21 | - | - | - | 12 | 0 | 12 |
| UNIT 22 TO 39 | - | - | - | 18 | 0 | 18 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building6
As on 30 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
45 of 45 construction stages are filed complete across 6 buildings.
WING A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
WING B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
WING C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
UNIT 1 TO 9100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
UNIT 10 TO 21100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
UNIT 22 TO 39100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 30 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | No | Not applicable |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | Yes | 100% |
| Drinking water facilities | Yes | 100% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 100% |
| Letter box | Yes | 100% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING A | NA | Rs 2.87 cr | Rs 2.69 cr |
| WING B | NA | Rs 2.87 cr | Rs 2.69 cr |
| WING C | NA | Rs 2.87 cr | Rs 2.69 cr |
| UNIT 1 TO 9 | NA | Rs 2.87 cr | Rs 2.69 cr |
| UNIT 10 TO 21 | NA | Rs 2.87 cr | Rs 2.69 cr |
| UNIT 22 TO 39 | NA | Rs 2.87 cr | Rs 2.69 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NIRMAN ASSOCIATES |
| Engineer | 912 CONSULTANTS |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed46
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05346/EX1/101122 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineer's certificate (Form 2) | 30 Mar 2023 |
| Engineer's certificate annexure | 30 Mar 2023 |
| Accountant's certificate (Form 3) | 30 Mar 2023 |
| Architect's certificate (Form 1) | 29 Mar 2023 |
| Site photograph, WING A | 29 Mar 2023 |
| Site photograph, WING B | 29 Mar 2023 |
| Site photograph, WING C | 29 Mar 2023 |
| Site photograph, UNIT 1 TO 9 | 29 Mar 2023 |
| Site photograph, UNIT 10 TO 21 | 29 Mar 2023 |
| Site photograph, UNIT 22 TO 39 | 29 Mar 2023 |
| RERA registration certificate | 30 Apr 2019 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Gandhinagar
Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.
Keep VRUNDAVAN RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vavol1,600+ in Gandhinagar
Filed coordinates, straight-line distance. 80 registered projects within 2 km.
Swagat Twincity Highstreet & Swagat Kingsland
SWAGAT DEVELOPERS
EWS - 2
GANDHINAGAR URBAN DEVELOPMENT AUTHORITY
SAMVED GREENVALLEY
SNEHARPAN BUILDCON LLP
Swagat Queen's Land Phase - 1
SWAGAT INFRASTRUCTURE P L TD
PRAMUKH PARISAR
PRAMUKH KRUPA CORPORATION
NEELKANTH HEIGHTS
NEEVA DEVELOPERS
See every Gandhinagar project, with the district possession charts
Builder: RADHE DEVELOPERS
RADHE DEVELOPERS has 9 registrations on GujRERA, including RADHE HEIGHTS and RATNARAJ GREEN. Read the full track record. See more projects on the Gandhinagar district page.
Frequently asked questions
What are my rights if VRUNDAVAN RESIDENCY is delayed beyond 31 Mar 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of VRUNDAVAN RESIDENCY?
The registered promoter entity is RADHE DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in VRUNDAVAN RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at VRUNDAVAN RESIDENCY?
The professionals named in the filing: Architect: NIRMAN ASSOCIATES; Engineer: 912 CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VRUNDAVAN RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.