This is a sample gujarat buyer report, generated from the real GujRERA filing for The One World, Rajkot. About this sample · What the reports cover
or press Ctrl+P / Cmd+P
ReraGenie Buyer Report · Sample
Report date: 12 November 2026
Latest RERA filing: 29 June 2024
Rajkot · Rajkot district · PIN 360006

The One World

by The One World Enterprise  ·  GujRERA PR/GJ/RAJKOT/RAJKOT/Others/MAA03421/140918  ·  ReraGenie RG-GJ-09938
Registered
14 Sep 2018
date of registration as filed
Possession promised
30 Jun 2024
unmoved since registration
Units booked
511 of 574
89% as filed
Latest RERA filing
29 Jun 2024
866 days before the report date

01At a glance

  • The One World is a 574 unit project of 5 buildings on 9,758 sq m at Rajkot, Rajkot, registered 14 September 2018 by The One World Enterprise.
  • It is 89% booked (511 of 574 units as filed), above the 50% median of the 167 projects of all ages with sales data within 2 km.
  • The possession promise of 30 Jun 2024 has not moved since registration, and no extension has been filed.
  • The engineer's certificate records 100% of the Rs 82.0 crore estimated cost as incurred.
  • This report does not read GujRERA's complaint or court case records for this project; the section on complaints and court cases says where to look.
Source: GujRERA project filing PR/GJ/RAJKOT/RAJKOT/Others/MAA03421/140918, as updated on 12 November 2026.

02Red flags and clear checks

On the record

The promised completion date has passed. GujRERA files no completion status, so this report cannot say whether the project was completed. see 03
Complaints and court cases are not read from GujRERA for this report, so their absence here is not a clear check. see 11

Clear

The possession promise has not moved in the 98 months since registration, in a pincode whose median slip is 0 months.
89% booked, above the 50% median of projects within 2 km that file sales.
Red means the condition has happened. Amber is a caution on record. These are filed facts, not opinions.

03The possession story

As per the promoter's filings up to 29 Jun 2024

No extension, no slip

Registration to the currently filed completion date
Registered Sep 2018Promised Jun 2024
How to read it: One line of time, registration on the left. Amber is the stretch between the first promised completion and the current one; red is time past the current promise with no completion filed.
Source: registration and extension records of the GujRERA filing. No extension application exists on this project.

Context from the corpus, which the GujRERA page cannot show:

  • The median possession slip across the 155 registered projects in PIN 360006 is zero months. This project has matched it so far.
Source: completion dates across the published GujRERA filings.

04Within 2 km of the project

Using the coordinates in the filing, every registered project within a 2 km radius is compared, a tighter and more honest vicinity than a whole pincode: 167 projects are registered there, of which 167 file sales figures.

167
registered projects within 2 km
50%
median bookings among the 167 that file sales, across all ages
89%
this project
Neighbours within 2 kmDistUnitsSoldPossession
The One World · this report0.057489%Jun 2024
Moondelight0.02060%Jun 2022
Viral Heights0.115572.9%Mar 2023
Time Square II0.19376.3%Jul 2021
Shivam 20.115100%Dec 2020
Earth Orchid0.1140%May 2027
Matru Arpan0.1100%Mar 2019
Pratishtha-A0.11060%Jan 2021
Rk Iconic0.260374.6%Jul 2027
Time Square0.2800%Mar 2018
The nearest neighbours that file unit counts, by distance from the coordinates each promoter filed. Sales as filed; projects that have not filed unit counts are excluded from the table and the median.

05Sanctions, units and sales, building by building

As per the promoter's filings up to 29 Jun 2024
BuildingFloors sanctionedUseUnitsSold + bookedUnsold% booked% construction
COMMERCIAL - Anot filedCommercial170166497.6%100%
COMMERCIAL - Bnot filedCommercial1641531193.3%100%
RESIDENTIAL - Anot filedResidential80631778.8%100%
RESIDENTIAL - Bnot filedResidential80661482.5%100%
RESIDENTIAL - Cnot filedResidential80631778.8%100%
Whole projectnot filed240 res · 334 comm5745116389%100%
    Source: building sanction table and floor wise inventory disclosure of the GujRERA filing. Percent booked is sold plus booked over sanctioned units. Most promoters do not file the building level split; where it is absent this section shows project totals only.

    06Parking

    As per the promoter's filings up to 29 Jun 2024
    • The filing records 2 covered parking spaces, over 15,479 sq m of covered parking area.
    • What is not filed. GujRERA files these figures as numbers the promoter enters and does not join them to the unit table, so this report states no spaces per unit and no comparison with any requirement. The figures are provision as filed, not a check that the approved plan was followed.
    • What to ask for. The sanctioned parking count from the approved building plan, and the clause in your agreement that identifies your space and whether it is covered or open.
    Source: the project details and the accountant's Form 3 of the GujRERA filing.

    07Construction and money

    As per the promoter's filings up to 29 Jun 2024

    45 of 45 construction stages are filed complete.

    100% of the filed cost is spent

    Rs crore, promoter filed
    Estimated82.0Incurred82.0100.0% of estimate, as filed in the latest quarterly update

    Construction by building

    Promoter's filed work done share of cost
    COMMERCIAL - A · 170 units100%COMMERCIAL - B · 164 units100%RESIDENTIAL - A · 80 units100%RESIDENTIAL - B · 80 units100%RESIDENTIAL - C · 80 units100%
    • Shared amenities are filed as complete across the checklist: water, sewerage, drains, lighting and fire safety.
    • Parking is filed. The figures are in the parking section above, as the promoter filed them.
    • Progress works out to 1.02% a month on the filed activity checklist, over the 98 months this registration has run.
    Source: cost, activity and parking tables of the GujRERA filing. These are the promoter's own figures, reported quarterly to the regulator, not an independent inspection.

    08Who you are dealing with

    Your agreement for sale is signed with the promoter entity below, exactly as named in the filing. The professionals certify construction progress and accounts, and their certificates are what unlock the promoter's money from the 70% account.

    RoleName, as filedRegistration on file
    PromoterTHE ONE WORLD ENTERPRISEPartnership firm
    ArchitectJawahar Ramjibai MoriCouncil of Architecture CA/1994/17224
    EngineerJay Harshadbhai Pujara004ERH10042800350
    • Match the name on your agreement to the filing. The entity above is printed exactly as GujRERA holds it, because this is the row to check your agreement for sale against. A different or additional entity there is a question to raise before signing.
    • Point of contact, as filed with GujRERA: The nominated contact, their filed email address (withheld on this public sample; a delivered report prints it). This is the contact the promoter nominated for this project, not a sales line, and it is what the filing gives you to put a question in writing.
    • This report does not read the promoter's CIN, LLPIN or GSTIN from the GujRERA record, so it says nothing about whether they exist. Ask for the certificate of incorporation or the partnership deed, and for the authorisation of whoever signs.
    • The architect and the engineer are named on Forms 1 and 2. The chartered accountant who signs Form 3 is not named in the filing as read here; the certificate itself is in the document list.
    Source: the promoter, personnel, point-of-contact and professionals tables of the GujRERA filing. Real estate agents registered on the project are deliberately not listed: they certify nothing, and listing them would publish a second set of private contact details to no purpose. The point of contact above is the one the promoter filed for this registration.

    09Land and title

    Who owns the land, as filed?

    This report does not read who owns the land from the GujRERA record: the register does not publish the landowner list. Ask for the title documents before any payment.

    Is the land mortgaged?

    Form 3 lists a loan from THE CO OPERATIVE BANK OF RAJKOT LTD: Rs 21.0 crore taken, Rs 21.0 crore repaid, a balance of nil, so it reads as fully repaid.

    What does the legal title report say?

    No legal title report is among this project's filed documents.

    Is anything disputed?

    This report does not read GujRERA's complaint or court case records, so it cannot say whether anything is disputed. Ask the promoter in writing, and check the project on the GujRERA portal.

    Source: land, encumbrance and CERSAI tables, the document register of the GujRERA filing, and the filed documents named above where they were read. A title search by your own lawyer remains prudent before any agreement.

    10Filing discipline and recent activity

    A promoter who keeps filing is a promoter still running the project. The last document here landed 866 days ago.

    • 29 Jun 2024CA certificate (Form 3), Architect certificate (Form 1), Engineer certificate (Form 2), Site photograph, COMMERCIAL - A, and 4 more
    • 14 Sep 2018RERA registration certificate
    Source: document register of the GujRERA filing, most recent first. This list refreshes at every data update.

    11Complaints and court cases, in plain words

    This report does not read GujRERA's complaint or court case records for this project. That is a limit of this report and not a finding: it says nothing about whether complaints or cases exist.

    • Open this project on the GujRERA portal and read its complaint and case information directly.
    • Ask the promoter in writing whether any complaint, order or court case concerning this project is pending or has been decided, and keep the reply.

    12What the documents say

    42 documents are on the filing. The checklist below shows what a buyer should expect on record for a project at this stage, and what is actually there.

    • ✓Commencement certificate. The permission to start construction.
    • •Legal title report. The lawyer's check of who owns the land.
    • ✓Professional certificates, Forms 1, 2 and 3, latest dated 29 Jun 2024. The architect, engineer and CA certificates that release money from the 70% account.
    • ✓Allotment or agreement proforma. The draft you should compare against the one you are given.
    • •Occupancy certificate. The completion signal: the building declared fit to move in.

    The checklist reads document titles as filed; a certificate inside a generically named scan will show as not found even when it exists. Absences marked not due are stage, not fault.

    This report lists the documents on file and does not read them. Read the ones that matter to your purchase, the title report and the sanction letters first.

    Source: document register of the GujRERA filing.

    13Booking pace

    ReraGenie records every change, so this section accumulates the project's booking history from the first day of coverage.

    First observation on record: 511 of 574 units sold or booked as of 12 November 2026. A single observation is a point, not a trend; the pace chart appears once the filed figure moves.

    511 bookings over the 98 months on the register works out to 5.2 a month.

    14What to verify before you book

    1. Ask in writing for the current completion timeline. The filed completion date has passed, and GujRERA files no completion status; the possession story section sets out the dates, and the interest delay earns you is under your rights below.
    2. Commission a title search and a CERSAI check. Form 3's loan list is the accountant's statement and not a title search, so whether the land is mortgaged is yours to establish.
    3. Ask for the legal title report. One is not among the filed documents.
    4. Have the carpet area and the price written into the agreement for sale. Whatever you are quoted comes from the promoter, and only the agreement makes it enforceable.
    5. Compare the agreement you are offered against the draft filed on GujRERA. The filed proforma is in the document list; a difference between the two is worth a question.
    Every item is tied to a condition on this filing, or to a gap every GujRERA filing shares, stated in the section it points to. It is a checklist of questions to ask, not a view on whether to buy.

    15Your rights under the RERA Act

    1. If possession is late, you may exit with interest. Section 18 lets you withdraw and recover everything paid plus interest at the rate the state's RERA rules prescribe. Stay invested instead and the promoter owes you that interest for every month of delay.
    2. 70% of your money is locked to this project. Collections must go to a designated account and be withdrawn only against certified construction and land cost.
    3. You buy carpet area, not built up area. The agreement must state RERA carpet area, and the price cannot rise if the area shrinks on completion.
    4. Five year defect liability. Structural or workmanship defects reported within five years of possession must be fixed by the promoter at no cost, within 30 days.
    5. No plan changes without consent. Altering your unit needs your consent. Altering the project's layout or common areas needs two thirds of all buyers.
    6. A complaint is cheap and direct. Any buyer can file against a project with the authority online for a nominal fee, and adjudicating officers can award compensation.
    A plain reading of the Real Estate (Regulation and Development) Act, 2016. The statutory text prevails over this summary.

    16What the filings do not contain

    This report never estimates a number the filing does not contain: where a fact is absent above, it is absent from the filing.