ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Rural, Karnataka / VR GOKULAM - Block 'B'

Registration approved Residential/Group Housing project

VR GOKULAM - Block 'B'

By VR BUILDERS & DEVELOPERS

RG-KA-07018 · RERA PRM/KA/RERA/1250/304/PR/190809/002789

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Mar 2022Possession promisedmoved 9 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 26 documents Report an error

VR GOKULAM - Block 'B' is a Residential/Group Housing project by VR BUILDERS & DEVELOPERS in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/190809/002789 on 9 Aug 2019. Possession is promised by 15 Mar 2022. The completion date has moved by 9 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVR GOKULAM - Block 'B'
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/190809/002789
  • ReraGenie IDRG-KA-07018

Builder

  • NameVR BUILDERS & DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryRamesh Naidu
  • OthersRamesh Naidu

Key dates

this monthRegisteredAug 2019First promiseJun 2021Revised toMar 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Aug 2019
  • Promised completion15 Mar 2022
  • Revised completionRevised to 15 Mar 2022 (originally 15 Jun 2021)
  • Buildings1 building record
  • Documents filed26 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VR GOKULAM Block-B---84084

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingYes-
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,844 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 10.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSathish Babu Associates
EngineerSathish Babu Associates

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2021 → Mar 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
CMP/221017/0010106-VR BUILDERS & DEVELOPERS17/10/2022

Documents filed26

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/190809/002789 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Partnership Certificate and Deed.pdf-
Plan sanction letter-
Plan Uploaded-
Plan Sanction letter and Renewal Letter-
Old sale deed-
Gokulplan-
Approvedbuildingplan-
Project Specifications - Uploaded-
Gokulam Ec New-
Affidavit 3 -1-
Rera Affidavit Land Owner and Promoter-
Katha-
JDAANDGPA-
EC New New Gokulam-
Convertion order uploaded-
Bescom NOC Gokulam-
Water Noc Gokulam-
Polutation Noc Gokulam-
Plan Uploaded-
Form B - uploaded-
Prospectus/BrochureFile: VR Gokulam Brochure_27-08-19.pdf-
Advertisement Copy 1File: VR Gokulam Brochure_27-08-19.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1250_304_PR_190809_002789.xlsx-
Occupancy CertificateFile: gokulam completion certificate (1).pdf-
Completion certificate issued by the competent authorityFile: gokulam completion certificate (1).pdf-
Registered conveyance deed for an individual unitFile: Sale deed Praveen-231 gokulam_compressed.pdf-

How this compares with Bengaluru Rural

20%of Bengaluru Rural projects moved their completion datethis one moved by 9 months
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep VR GOKULAM - Block 'B' on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmVR GOKULAM - Block 'B'Other 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: VR BUILDERS & DEVELOPERS

VR BUILDERS & DEVELOPERS has 1 registration on RERA Karnataka, including VR GOKULAM - Block 'B'. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if VR GOKULAM - Block 'B' is delayed beyond 15 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of VR GOKULAM - Block 'B'?

The registered promoter entity is VR BUILDERS & DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in VR GOKULAM - Block 'B'?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VR GOKULAM - Block 'B'?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at VR GOKULAM - Block 'B'?

The professionals named in the filing: Architect: Sathish Babu Associates; Engineer: Sathish Babu Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VR GOKULAM - Block 'B'?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VR GOKULAM - Block 'B'. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VR GOKULAM - Block 'B' to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.