VKLAL VISHNU PHASE I
By VEEKAYLAL INVESTMENT COMPANY PRIVATE LIMITED
RG-MH-70894 · RERA P51800011626 · Last updated on MahaRERA portal: 3 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 10 cases
- 4 complaints at MahaRERA
- Completion date moved by 36 months
- 2 extensions taken
- Rs 10.00 crore secured on the land, in favour of ADITYA BIRLA FINANCE LTD
Clear
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VKLAL VISHNU PHASE I is a Residential / Group Housing project by VEEKAYLAL INVESTMENT COMPANY PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011626 on 31 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 63 of the 66 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.
At a glance
Project
- NameVKLAL VISHNU PHASE I
- TypeResidential / Group Housing
- Location
- SN Dubey street
- Dahisar
- Borivali
- Mumbai Suburban
- 400068
- Pincode400068
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800011626
- ReraGenie IDRG-MH-70894
Builder
- NameVEEKAYLAL INVESTMENT COMPANY PRIVATE LIMITED
- Entity typeCompany
- DirectorsAnita Haresh Nanwani, Haresh Khiamal Nanwani
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed166 files
Current status
Figures as on 3 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VKLAL VISHNU PHASE I | NA | 25 | 22 | 66 | 0 | 66 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
VKLAL VISHNU PHASE I: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed8
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| KHUSHI BUILDERS AND DEVELOPERS | Borivali | Mumbai Suburban |
| TYABJI ESTATE PRIVATE LIMITED | - | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| VKLAL VISHNU PHASE I | NA | Rs 46.35 cr | Rs 55.01 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Jitendra Patel |
| Engineer | Jayesh Khanvilkar |
| Engineer | ARIF RUPALWALA |
| Chartered Accountant | Hardik Natvarlal Thakkar |
| Partner | Role in project |
|---|---|
| VEEKAYLAL INVESTMENT COMPANY PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe promoters seek extension on the project completion date as the construction work got slowed and delayed due to unforeseen circumstances in the post Covid period due to multiple reasons beyond control of the promoters such as acute shortage of building materials, delayed delivery of building materials from the suppliers, too much increased and variation in raw material rates demanded by raw material suppliers post covid which drastically influenced the tight project budget leading to find new suppliers to keep project viable which consumed considerable time along with inconsistent labour su
Reason as filed by the promoterproject is completed awaiting for OC from Concerned Authority
Litigation declared10
| Case | Court | Status |
|---|---|---|
| C/RTS/9/1994/1994 | DY COLLECTOR | Ongoing |
| 474/2011 | CITY CIVIL COURT | Ongoing |
| 1692/2016 | CITY CIVIL COURT | Ongoing |
| CRR NO 526 2012 IN SUIT NO 3415 1947/2012 | HIGH COURT BOMBAY | Closed |
| NM NO 1077 2014/2014 | HIGH COURT BOMBAY | Ongoing |
| Suit No 58 of 2022/2022 | CITY CIVIL COURT DINDOSHI | Ongoing |
| Suit No 3183 of 1988/1988 | HIGH COURT BOMBAY | Ongoing |
| Suit No 3235 of 1991/1991 | HIGH COURT BOMBAY | Closed |
| C/RTS/9/1994/1994 | DY. Collector | Ongoing |
| APPEAL (L) NO.-13363 OF 2025/2025 | High Court of Bombay | Ongoing |
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000209815 | SHOEB AHMED SHAIKH | VKLAL Vishnu | 25/01/2022 |
| CC006000000439678 | Meghal Rajan Save | Veekaylal Investment Co. Pvt. Ltd. | 16/03/2024 |
| CC006000000480131 | Hemchandra Vijay More | Veekaylal Investment Co. Pvt. Ltd | 20/04/2024 |
| CC12400928 | Prathmesh Suresh Shirambekar | VEEKAYLAL INVESTMENT COMPANY PRIVATE LIMITED | 28/11/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Jun 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed166
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 166 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: RERA Form - 1 Q-1-FY26-27-Vishnu.pdf | 3 Aug 2026 |
| Withdrawal Update Form 2File: QUARTER 1 ( FY-26-27 ).pdf | 3 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 - Vishnu Phase I - Q1 -26-27 (2).pdf | 3 Aug 2026 |
| Withdrawal Update Form 1File: Form-1-Vishnu Phase-Q1-FY25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Vishnu Phase I - Q3 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Vishnu Phase I - Q3 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Vishnu Phase I - Q3 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Vishnu Phase I - Q4 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Vishnu Phase I - Q4 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Vishnu Phase I - Q1 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Vishnu Phase I - Q4 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Vishnu Phase I - Q4 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Vishnu Phase I - Q1 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Vishnu Phase I - Q2 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Vishnu Phase I - Q4 -25-26.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Vishnu Phase I - Q4 -25-26.pdf | 22 May 2026 |
| Form 2A (FY 2023-2024)File: FORM-2A-RERA-23-24-Vishnu.PDF | 9 Jan 2026 |
| Form 2A (FY 2024-2025)File: FORM-2A-RERA-24-25-Vishnu.PDF | 9 Jan 2026 |
| Form 5 (FY 2023-2024)File: VishnuFY202324.pdf | 8 Jan 2026 |
| Form 5 (FY 2024-2025)File: VishnuFY202425.pdf | 8 Jan 2026 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Vishnu Q3 - FY 24-25.pdf | 4 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 - Vishnu Q3 - FY 24-25.PDF | 4 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 - Vishnu Q3 - FY 24-25.PDF | 4 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Vishnu Q3 - FY 24-25.pdf | 4 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Vishnu Sales Data.pdf | 14 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Vishnu - Q1 FY24-25.pdf | 30 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 - 30 Sept 2024.pdf | 30 Nov 2024 |
| Certificates of CA (Form 3)File: FORM 3 - Vishnu - Q1 FY 24-25.PDF | 30 Nov 2024 |
| Certificates of CA (Form 3)File: FORM 3 - Vishnu - Q2.PDF | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Vishnu - Q1 FY-24-25.pdf | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Vishnu - Q2 FY-24-25.pdf | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form 1 - 30 Sept 2024.pdf | 30 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5-Vishnu.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vishnu-Form-1-Q4-FY 23-24.pdf | 27 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vishnu-Form 2 -Q4-FY 23-24.pdf | 27 Jun 2024 |
| Certificates of CA (Form 3)File: Vishnu-Form 3-Q4 -FY 23-24 (1).pdf | 27 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 -Vishnu-Q3.pdf | 28 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 28 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3 - Vishnu Q3.PDF | 28 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3 - Vishnu Q3.PDF | 28 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Vishnu ( FY-23-24 ).pdf | 26 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA Form 2A - Vishnu Q1.pdf | 19 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Vishnu Phase I - Form 2A - Q2.pdf | 19 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Vishnu-Form 2A-31-03-23.pdf | 17 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Vishnu Q3.pdf | 4 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vishnu Phase I - Form 2 - Q2.pdf | 4 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3- Vishnu Q3.PDF | 4 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Site Supervisor Certificate - Vishnu Phase I - 31-03-2022.pdf | 2 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Vishnu Phase I - Form 2A - RERA Certificate - 2022-06-30 (1).pdf | 2 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Vishnu Phase I - Form 2A - RERA Certificate - 2022-06-30 (1).pdf | 2 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Vishnu-Form 2A - Site supervisor's certificate - 2022-09-30 (2).pdf | 2 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Vishnu-Form 2A - Site supervisor's certificate - 2022-09-30 (2).pdf | 2 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Phase I - Form 2A RERA Certificate - 2022-12-31 (1).pdf | 2 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Vishnu Phase I - Form 2A - RERA Certificate - 2022-12-31.pdf | 2 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vishnu Form 1 31-03-2022 (2).pdf | 12 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vishnu Form 1 2022-06-30 (2).pdf | 12 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vishnu Form 1 2022-06-30 (2).pdf | 12 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vishnu Form 1 2022-06-30 (2).pdf | 12 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vishnu Form 1 2022-09-30 (2).pdf | 12 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vishnu Form 1 31-12-2022.pdf | 12 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vishnu - Form 1 31-03-2023.pdf | 12 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vishnu Form 1 30-06-2023 (2).pdf | 12 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q1 - VISHNU.pdf | 8 Sep 2023 |
| Certificates of CA (Form 3)File: RERA Form 3 - Vishnu Q1.pdf | 5 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: JUNE 2022 (1).pdf | 8 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SEPT 2022.pdf | 8 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DEC 2022.pdf | 8 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MARCH 2023.pdf | 8 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 Vishnu Q1.pdf | 8 Aug 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 166 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VKLAL VISHNU PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dahisar6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 185 registered projects within 2 km.
ICON
RAGHU LEELA REALTORS PRIVATE LIMITED
ORNATE SOLITAIRE
ORNATE DAHISAR DEVELOPERS
EMPIRE HEIGHTS
EMPIRE REALTY
SHAKTI DHAM-WING A, VRINDAVAN-WING B RESIDENTI
DHARTI DEVELOPERS
RAGHUKUL CHSL
RAMNIYATI REALITIES LLP
Earth Residency Wing C and Wing D
Earth Estate Developers Pvt Ltd
See every Mumbai Suburban project, with the district possession charts
Builder: VEEKAYLAL INVESTMENT COMPANY PRIVATE LIMITED
VEEKAYLAL INVESTMENT COMPANY PRIVATE LIMITED has 2 registrations on MahaRERA, including VKLAL HARI PHASE I and VKLAL VISHNU PHASE I. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if VKLAL VISHNU PHASE I is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VKLAL VISHNU PHASE I?
The registered promoter entity is VEEKAYLAL INVESTMENT COMPANY PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VKLAL VISHNU PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VKLAL VISHNU PHASE I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VKLAL VISHNU PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VKLAL VISHNU PHASE I?
The professionals named in the filing: Architect: Jitendra Patel; Engineer: Jayesh Khanvilkar; Engineer: ARIF RUPALWALA; Chartered Accountant: Hardik Natvarlal Thakkar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VKLAL VISHNU PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback