Home / Browse projects / Aurangabad, Maharashtra / VITHAI RESIDENCY
VITHAI RESIDENCY
RG-MH-14736 · RERA P51500048858 · Last updated on MahaRERA portal: 13 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VITHAI RESIDENCY is a Residential / Group Housing project by SHRINIVASA DEVELOPER in Aurangabad, Maharashtra, registered with MahaRERA as P51500048858 on 24 Jan 2023. Possession is promised by 31 Dec 2027.
At a glance
Project
- NameVITHAI RESIDENCY
- TypeResidential / Group Housing
- Location
- GUT NO 91
- PISADEVI
- Aurangabad
- 431008
- Pincode431008
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500048858
- ReraGenie IDRG-MH-14736
Builder
- NameSHRINIVASA DEVELOPER
- Entity typePartnership
- PartnersSACHIN BHARATRAO PANDHARE, ASHISH FAKIRCHAND KALE, MAHENDRA RAMRAO DHAKNE, ARUN VITTHAL KALE, VARSHA GAJENDRA DHAKNE
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Jan 2023
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings10 building records
- Documents filed96 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| E TYPE BUILDING | NA | 2 | 0 | 0 | 0 | 0 |
| F TYPE BUILDING | NA | 2 | 0 | 0 | 0 | 0 |
| G TYPE BUILDING | NA | 2 | 0 | 0 | 0 | 0 |
| H TYPE BIUILDING | NA | 2 | 0 | 0 | 0 | 0 |
| I TYPE BUILDING | NA | 2 | 0 | 0 | 0 | 0 |
| J TYPE BUILDING | NA | 2 | 0 | 0 | 0 | 0 |
| A TYPE BUILDING | NA | 2 | 0 | 0 | 0 | 0 |
| B TYPE BUILDING | NA | 1 | 0 | 0 | 0 | 0 |
| C TYPE BUILDING | NA | 2 | 0 | 0 | 0 | 0 |
| D TYPE BUILDING | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building10
As on 13 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Stilt Floor, at 80%.
E TYPE BUILDING50%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 65% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
F TYPE BUILDING49%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
G TYPE BUILDING50%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 70% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
H TYPE BIUILDING47%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 70% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 45% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
I TYPE BUILDING49%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
J TYPE BUILDING32%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 70% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A TYPE BUILDING45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B TYPE BUILDING48%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 60% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C TYPE BUILDING50%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 55% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D TYPE BUILDING53%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed166
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| E TYPE BUILDING | 1 | 18 | 19 |
| F TYPE BUILDING | 1 | 20 | 21 |
| G TYPE BUILDING | 1 | 20 | 21 |
| H TYPE BIUILDING | 1 | 20 | 21 |
| I TYPE BUILDING | 1 | 4 | 5 |
| J TYPE BUILDING | 1 | 2 | 3 |
| A TYPE BUILDING | 0 | 16 | 16 |
| B TYPE BUILDING | 0 | 18 | 18 |
| C TYPE BUILDING | 1 | 20 | 21 |
| D TYPE BUILDING | 1 | 20 | 21 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MANDA VITTHAL KALE | Pisadevi | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DHANANJAY DOIFODE BABURAO DOIFODE |
| Engineer | PRADEEP MOTE VISHNU MOTE |
| Chartered Accountant | CAAG AND ASSOCIATES |
| Chartered Accountant | GHOUS MOHUDDIN QUAZI |
| Partner | Role in project |
|---|---|
| SHRINIVASA DEVELOPER | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Nov 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Nov 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed96
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTITECEH ENGINEER 3112024.pdf | 13 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificat 3112024.pdf | 13 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 311202024.pdf | 13 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: BOOKING INVETORY.pdf | 13 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTITECEH CERNTIFICATE 30062024.pdf | 18 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 30062024.pdf | 18 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFTCAE 30092024.pdf | 18 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: BOOKING 30062024.pdf | 18 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: CA CERTITCAE 30092024.pdf | 18 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: BOOKING 30092024.pdf | 18 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFTCA 30062024.pdf | 18 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTITCAE 30092024.pdf | 18 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTITECEH CENT 30092024.pdf | 18 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTITECEH CERNTIFICATE 30062024.pdf | 18 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTITECEH CENT 30092024.pdf | 18 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFTCA 30062024.pdf | 18 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTITCAE 30092024.pdf | 18 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 30062024.pdf | 18 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFTCAE 30092024.pdf | 18 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: BOOKING 30062024.pdf | 18 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: CA CERTITCAE 30092024.pdf | 18 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: BOOKING 30092024.pdf | 18 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate 01-04-24 - converted.pdf | 7 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 31-12-23 (1) - converted.pdf | 24 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate 31-03-24 (1).pdf | 24 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 01-04-24.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate 01-04-24.pdf | 29 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality certificate 01-04-24.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sold booked Inventory 01-04-24.pdf | 29 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate 05-02-24.pdf | 16 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 31-12-23.pdf | 16 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: supervisor certificate.pdf | 16 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold booking 31-12-23.pdf | 16 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: CA Certificate 31-12-23.pdf | 16 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect cartificat.pdf | 10 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate (1).pdf | 10 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-9-2023.pdf | 10 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering cartificat.pdf | 10 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: New Doc 30-06-23.pdf | 10 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-9-23.pdf | 10 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: New Doc 10-04-2023.pdf | 10 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 31-03-2023.pdf | 10 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 30-06-2023-1.pdf | 10 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scan 02_0001 (2 files merged).pdf | 10 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-1.pdf | 10 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: supar vision.pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: DISC MAR23.pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: DISC JUN23.pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: DISC SEP23.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 31-03-2023.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 30-06-2023-1.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 30-09-2024.pdf | 20 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-1.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-9-2023.pdf | 13 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: New Doc 30-06-23.pdf | 13 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-9-23.pdf | 13 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect cartificat.pdf | 4 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate (1).pdf | 4 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering cartificat.pdf | 4 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: New Doc 10-04-2023.pdf | 4 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: supervision certificate (1).pdf | 4 Oct 2023 |
| Proforma of Agreement for saleFile: 65 R New ATS - 2023.pdf | 12 Jan 2023 |
| Proforma of Allotment letterFile: Allotment Dhakne 65 R.pdf | 12 Jan 2023 |
| Deviation Report with respect to Allotment letterFile: DEVI ALLO.pdf | 12 Jan 2023 |
| Deviation Report with respect to model copy of AgreementFile: DEVI AFS.pdf | 12 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOUER INTERST SACHIN PANDHARE.pdf | 3 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOUSR INTEREST MAHENDRA DHAKNE.pdf | 3 Jan 2023 |
| Other - TechnicalFile: FORM NO B DEVELOPERS.pdf | 3 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: NO INCOME CERTIFICATE FINANCE.pdf | 22 Dec 2022 |
| Details of encumbrances concerned to LegalFile: NO INCOME CERTIFICATE FINANCE.pdf | 22 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate 2211.pdf | 25 Nov 2022 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCE WITH PROJECT DETAILS.pdf | 23 Nov 2022 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCE WITH PROJECT DETAILS.pdf | 23 Nov 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: ACCOUNT DETAIL NEW FROMAT.pdf | 23 Nov 2022 |
| Copy of the legal title reportFile: SEARCH REPORT.pdf | 11 Nov 2022 |
| CERSAI detailsFile: cersai report.pdf | 11 Nov 2022 |
| Layout approvalFile: LAYOUT.pdf | 9 Nov 2022 |
| Building plan approvalFile: PLAN 1.pdf | 9 Nov 2022 |
| Building plan approvalFile: PLAN 2.pdf | 9 Nov 2022 |
| Building plan approvalFile: PLAN 3.pdf | 9 Nov 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 96 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep VITHAI RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PISADEVI1,400+ in Aurangabad
Filed coordinates, straight-line distance. 15 registered projects within 2 km.
SARA NIWARA
Sara Infrastructures
Sawangi City Phase-2
Aryaman Infra
JANKI HEIGHTS
SHREE BALAJI BUILDCON
Rajgad- Swaraj Nagar
M S M Infra
Swapna Srushti 1
M/s Nisha Associates
KISAN PARK
KALYANRAO KISANRAO AUTADE
See every Aurangabad project, with the district possession charts
Builder: SHRINIVASA DEVELOPER
SHRINIVASA DEVELOPER has 1 registration on MahaRERA, including VITHAI RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if VITHAI RESIDENCY is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VITHAI RESIDENCY?
The registered promoter entity is SHRINIVASA DEVELOPER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VITHAI RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VITHAI RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VITHAI RESIDENCY?
The professionals named in the filing: Architect: DHANANJAY DOIFODE BABURAO DOIFODE; Engineer: PRADEEP MOTE VISHNU MOTE; Chartered Accountant: CAAG AND ASSOCIATES; Chartered Accountant: GHOUS MOHUDDIN QUAZI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VITHAI RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback