ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / VITHAI RESIDENCY

Registered No litigation declared Residential / Group Housing project

VITHAI RESIDENCY

By SHRINIVASA DEVELOPER

RG-MH-14736 · RERA P51500048858 · Last updated on MahaRERA portal: 13 Feb 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
30 of 110Construction stages doneacross 10 buildings; furthest along: Stilt Floor, 80%
0Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

VITHAI RESIDENCY is a Residential / Group Housing project by SHRINIVASA DEVELOPER in Aurangabad, Maharashtra, registered with MahaRERA as P51500048858 on 24 Jan 2023. Possession is promised by 31 Dec 2027.

At a glance

Project

  • NameVITHAI RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • GUT NO 91
    • PISADEVI
    • Aurangabad
    • 431008
  • Pincode431008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500048858
  • ReraGenie IDRG-MH-14736

Builder

  • NameSHRINIVASA DEVELOPER
  • Entity typePartnership
  • PartnersSACHIN BHARATRAO PANDHARE, ASHISH FAKIRCHAND KALE, MAHENDRA RAMRAO DHAKNE, ARUN VITTHAL KALE, VARSHA GAJENDRA DHAKNE

Key dates

this monthRegisteredJan 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Jan 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings10 building records
  • Documents filed96 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E TYPE BUILDINGNA20000
F TYPE BUILDINGNA20000
G TYPE BUILDINGNA20000
H TYPE BIUILDINGNA20000
I TYPE BUILDINGNA20000
J TYPE BUILDINGNA20000
A TYPE BUILDINGNA20000
B TYPE BUILDINGNA10000
C TYPE BUILDINGNA20000
D TYPE BUILDINGNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building10

As on 13 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Stilt Floor, at 80%.

E TYPE BUILDING50%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
F TYPE BUILDING49%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G TYPE BUILDING50%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor70%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
H TYPE BIUILDING47%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor70%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
I TYPE BUILDING49%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
J TYPE BUILDING32%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor70%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A TYPE BUILDING45%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B TYPE BUILDING48%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor60%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C TYPE BUILDING50%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D TYPE BUILDING53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed166

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots166
Closed/Covered8
Open Space158
BuildingClosed/CoveredOpen SpaceTotal
E TYPE BUILDING11819
F TYPE BUILDING12021
G TYPE BUILDING12021
H TYPE BIUILDING12021
I TYPE BUILDING145
J TYPE BUILDING123
A TYPE BUILDING01616
B TYPE BUILDING01818
C TYPE BUILDING12021
D TYPE BUILDING12021

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MANDA VITTHAL KALEPisadeviAurangabad

Approvals and building plan

Sanctioning authoritycidco
Permissible FSI5586.85
Proposed, not sanctioned5,587 sq m
Buildings approved10
Buildings sanctioned10

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchT V CENTRE AURANGABAD 431003

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDHANANJAY DOIFODE BABURAO DOIFODE
EngineerPRADEEP MOTE VISHNU MOTE
Chartered AccountantCAAG AND ASSOCIATES
Chartered AccountantGHOUS MOHUDDIN QUAZI
PartnerRole in project
SHRINIVASA DEVELOPER-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTITECEH ENGINEER 3112024.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificat 3112024.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 311202024.pdf13 Feb 2025
Disclosure of sold/ booked inventoryFile: BOOKING INVETORY.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTITECEH CERNTIFICATE 30062024.pdf18 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 30062024.pdf18 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFTCAE 30092024.pdf18 Nov 2024
Disclosure of sold/ booked inventoryFile: BOOKING 30062024.pdf18 Nov 2024
Disclosure of sold/ booked inventoryFile: CA CERTITCAE 30092024.pdf18 Nov 2024
Disclosure of sold/ booked inventoryFile: BOOKING 30092024.pdf18 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFTCA 30062024.pdf18 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTITCAE 30092024.pdf18 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTITECEH CENT 30092024.pdf18 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTITECEH CERNTIFICATE 30062024.pdf18 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTITECEH CENT 30092024.pdf18 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFTCA 30062024.pdf18 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTITCAE 30092024.pdf18 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 30062024.pdf18 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFTCAE 30092024.pdf18 Nov 2024
Disclosure of sold/ booked inventoryFile: BOOKING 30062024.pdf18 Nov 2024
Disclosure of sold/ booked inventoryFile: CA CERTITCAE 30092024.pdf18 Nov 2024
Disclosure of sold/ booked inventoryFile: BOOKING 30092024.pdf18 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate 01-04-24 - converted.pdf7 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 31-12-23 (1) - converted.pdf24 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate 31-03-24 (1).pdf24 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 01-04-24.pdf29 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate 01-04-24.pdf29 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality certificate 01-04-24.pdf29 May 2024
Disclosure of sold/ booked inventoryFile: Sold booked Inventory 01-04-24.pdf29 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate 05-02-24.pdf16 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 31-12-23.pdf16 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: supervisor certificate.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold booking 31-12-23.pdf16 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: CA Certificate 31-12-23.pdf16 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect cartificat.pdf10 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate (1).pdf10 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-9-2023.pdf10 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering cartificat.pdf10 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: New Doc 30-06-23.pdf10 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-9-23.pdf10 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: New Doc 10-04-2023.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 31-03-2023.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 30-06-2023-1.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scan 02_0001 (2 files merged).pdf10 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-1.pdf10 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: supar vision.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: DISC MAR23.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: DISC JUN23.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: DISC SEP23.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 31-03-2023.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 30-06-2023-1.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 30-09-2024.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-1.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-9-2023.pdf13 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: New Doc 30-06-23.pdf13 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-9-23.pdf13 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect cartificat.pdf4 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate (1).pdf4 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering cartificat.pdf4 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: New Doc 10-04-2023.pdf4 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: supervision certificate (1).pdf4 Oct 2023
Proforma of Agreement for saleFile: 65 R New ATS - 2023.pdf12 Jan 2023
Proforma of Allotment letterFile: Allotment Dhakne 65 R.pdf12 Jan 2023
Deviation Report with respect to Allotment letterFile: DEVI ALLO.pdf12 Jan 2023
Deviation Report with respect to model copy of AgreementFile: DEVI AFS.pdf12 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOUER INTERST SACHIN PANDHARE.pdf3 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOUSR INTEREST MAHENDRA DHAKNE.pdf3 Jan 2023
Other - TechnicalFile: FORM NO B DEVELOPERS.pdf3 Jan 2023
Details of encumbrances concerned to FinanceFile: NO INCOME CERTIFICATE FINANCE.pdf22 Dec 2022
Details of encumbrances concerned to LegalFile: NO INCOME CERTIFICATE FINANCE.pdf22 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate 2211.pdf25 Nov 2022
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE WITH PROJECT DETAILS.pdf23 Nov 2022
Details of encumbrances concerned to LegalFile: ENCUMBRANCE WITH PROJECT DETAILS.pdf23 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: ACCOUNT DETAIL NEW FROMAT.pdf23 Nov 2022
Copy of the legal title reportFile: SEARCH REPORT.pdf11 Nov 2022
CERSAI detailsFile: cersai report.pdf11 Nov 2022
Layout approvalFile: LAYOUT.pdf9 Nov 2022
Building plan approvalFile: PLAN 1.pdf9 Nov 2022
Building plan approvalFile: PLAN 2.pdf9 Nov 2022
Building plan approvalFile: PLAN 3.pdf9 Nov 2022

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep VITHAI RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PISADEVI1,400+ in Aurangabad

2 kmVITHAI RESIDENCYCompleted 1Lapsed / revoked 3Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: SHRINIVASA DEVELOPER

SHRINIVASA DEVELOPER has 1 registration on MahaRERA, including VITHAI RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if VITHAI RESIDENCY is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VITHAI RESIDENCY?

The registered promoter entity is SHRINIVASA DEVELOPER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VITHAI RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VITHAI RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VITHAI RESIDENCY?

The professionals named in the filing: Architect: DHANANJAY DOIFODE BABURAO DOIFODE; Engineer: PRADEEP MOTE VISHNU MOTE; Chartered Accountant: CAAG AND ASSOCIATES; Chartered Accountant: GHOUS MOHUDDIN QUAZI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VITHAI RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VITHAI RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VITHAI RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.