Home / Browse projects / Pune, Maharashtra / VISION 24DEGREE
VISION 24DEGREE
By VISION CREATIVE ENTERPRISE LLP
RG-MH-05594 · RERA P52100066503 · Last updated on MahaRERA portal: 10 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Rs 50.00 crore secured on the land, in favour of TATA CAPITAL HOUSING FINANCE LIMITED
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VISION 24DEGREE is a Others project by VISION CREATIVE ENTERPRISE LLP in Pune, Maharashtra, registered with MahaRERA as P52100066503 on 11 Jun 2024. Possession is promised by 31 Dec 2027. 76 of the 322 units on this registration are recorded sold or booked, and 4 of 33 construction stages are filed complete.
At a glance
Project
- NameVISION 24DEGREE
- TypeOthers
- Location
- SURVEY NO. 143/1 (P)
- WADMUKHWADI
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100066503
- ReraGenie IDRG-MH-05594
Builder
- NameVISION CREATIVE ENTERPRISE LLP
- Entity typePartnership
- PartnersNITESHKUMAR SURESHBHAI PATEL, MANISH SURESHBHAI PATEL, CHETANKUMAR AMBALAL PATEL, JAYKUMAR BIPINBHAI PATEL, RAMESHKUMAR VITTHALBHAI PATEL
- Authorized PartnersVIPULKUMAR CHIMANLAL BHAVANI, JAYESHKUMAR SHANTILAL PATEL
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on11 Jun 2024
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings3 building records
- Documents filed115 files
Current status
Figures as on 10 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 20 | 18 | 115 | 5 | 120 |
| B WING | NA | 24 | 22 | 77 | 0 | 77 |
| C WING | NA | 24 | 22 | 125 | 0 | 125 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 10 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 75%.
A WING10%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 10% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B WING16%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 75% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C WING18%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 10 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed627
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A WING | 258 | 0 | 258 |
| B WING | 127 | 12 | 139 |
| C WING | 181 | 49 | 230 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A WING | NA | Rs 48.60 cr | Rs 7.32 cr |
| C WING | NA | Rs 47.41 cr | Rs 7.01 cr |
| B WING | NA | Rs 22.52 cr | Rs 3.28 cr |
| - | NA | Rs 12.70 cr | Rs 1.89 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PATIL & BUGADE ASSOCIATES |
| Engineer | SAURABH VIJAY BENDALE |
| Engineer | NARENDRA PANDURANG KULKARNI |
| Engineer | Rameshwar Chitale |
| Chartered Accountant | BANKIM PATEL & ASSOCIATES |
| Chartered Accountant | S N K & CO. |
| Partner | Role in project |
|---|---|
| VISION CREATIVE ENTERPRISE LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 May 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 May 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 May 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed115
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 ARCHITECTS CERTIFICATE 30 06 2026.pdf | 10 Jul 2026 |
| Withdrawal Update Form 2File: RERA FORM 02 VCELLP.pdf | 10 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 VCELLP 30 06 2026.pdf | 10 Jul 2026 |
| Form 5 (FY 2025-2026)File: FORM 05 24 DEGREE.pdf | 8 Jul 2026 |
| Layout approvalFile: Plan 1 of 9.pdf | 23 May 2026 |
| Building plan approvalFile: Plan 1 of 9.pdf | 23 May 2026 |
| Building plan approvalFile: Plan 2 of 9.pdf | 23 May 2026 |
| Building plan approvalFile: Plan 3 of 9.pdf | 23 May 2026 |
| Building plan approvalFile: Plan 4 of 9.pdf | 23 May 2026 |
| Building plan approvalFile: Plan 5 of 9.pdf | 23 May 2026 |
| Building plan approvalFile: Plan 6 of 9.pdf | 23 May 2026 |
| Building plan approvalFile: Plan 7 of 9.pdf | 23 May 2026 |
| Building plan approvalFile: Plan 8 of 9.pdf | 23 May 2026 |
| Building plan approvalFile: Plan 9 of 9.pdf | 23 May 2026 |
| Form 2A (FY 2024-2025)File: Form 2A FY-2024-2025.pdf | 19 May 2026 |
| Form 2A (FY 2025-2026)File: Form 2A FY-2025-2026.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: V 24Degree VCELLP Rera Form 1.pdf | 17 Apr 2026 |
| Withdrawal Update Form 2File: Form 02 VCE LLP.pdf | 17 Apr 2026 |
| Withdrawal Update Form 3File: VCE LLP FORM 3.pdf | 17 Apr 2026 |
| Withdrawal Update Form 1File: Vision Creative Enterprise Llp Form 1 31 12 2025.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Vision Creative Enterprise LLP- Form 2 - FY 2025-26 -Q3.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: V C ENTEPRISE LLP- FORM 3.pdf | 20 Jan 2026 |
| Withdrawal Update Form 1File: V C ENTERPRISES LLP FORM NO 1 ARCHITECT CERTIFICATE 30 09 2025.pdf | 14 Oct 2025 |
| Withdrawal Update Form 1File: V C ENTERPRISES LLP FORM NO 1 ARCHITECT CERTIFICATE 30 09 2025.pdf | 14 Oct 2025 |
| Withdrawal Update Form 2File: V C ENTERPRISES LLP ENGINEER CERTIFICATE FORN NO 2 30 09 2025.pdf | 14 Oct 2025 |
| Withdrawal Update Form 2File: V C ENTERPRISES LLP ENGINEER CERTIFICATE FORN NO 2 30 09 2025.pdf | 14 Oct 2025 |
| Withdrawal Update Form 3File: V C ENTERPRISES LLP CA CERTIFICATE FORN NO 3 30 09 2025.pdf | 14 Oct 2025 |
| Withdrawal Update Form 3File: V C ENTERPRISES LLP CA CERTIFICATE FORN NO 3 30 09 2025.pdf | 14 Oct 2025 |
| Form 5 (FY 2024-2025)File: Annual Audit Report of Statutory CA 24 Degree 2024 25.pdf | 26 Sep 2025 |
| Form 1File: Architect’s Certificate of Percentage of Completion of Work VCE LLP FORM 01.pdf | 8 Sep 2025 |
| Form 2File: Engineer’s Certificate on Cost Incurred on Project VCELLP 31 3 2025.pdf | 8 Sep 2025 |
| Form 3File: CA Certificate on Project Cost And Fund withdrawal VCELLP 31 3 2025.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf | 8 Sep 2025 |
| Withdrawal Update Form 1File: Architect’s Certificate of Percentage of Completion of Work.pdf | 8 Sep 2025 |
| Withdrawal Update Form 2File: 20250906132715.pdf | 8 Sep 2025 |
| Withdrawal Update Form 3File: V C ENTERPRISES LLP FORM NO 03.pdf | 8 Sep 2025 |
| Building plan approvalFile: 01 SANCTION PLAN.pdf | 5 Sep 2025 |
| Building plan approvalFile: 02 SANCTION PLAN.pdf | 5 Sep 2025 |
| Building plan approvalFile: 03 SANCTION PLAN.pdf | 5 Sep 2025 |
| Building plan approvalFile: 04 SANCTION PLAN.pdf | 5 Sep 2025 |
| Building plan approvalFile: 05 SANCTION PLAN.pdf | 5 Sep 2025 |
| Building plan approvalFile: 06 SANCTION PLAN.pdf | 5 Sep 2025 |
| Building plan approvalFile: 07 SANCTION PLAN.pdf | 5 Sep 2025 |
| Building plan approvalFile: 08 SANCTION PLAN.pdf | 5 Sep 2025 |
| Building plan approvalFile: 09 SANCTION PLAN.pdf | 5 Sep 2025 |
| Form 1File: FORM 01 JUNE 24 (VCE LLP).pdf | 4 Aug 2025 |
| Form 2File: FORM 02 JUNE 24 (VCE LLP).pdf | 4 Aug 2025 |
| Form 3File: FORN NO - 03 NEW 30-06-2024 VCELLP.pdf | 4 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY JUNE 24 (VCE LLP).pdf | 4 Aug 2025 |
| Form 1File: FORM 01 VCE LLP 30 SEP 2024.pdf | 4 Aug 2025 |
| Form 2File: FORM 02 VCE LLP 30 SEP 2024.pdf | 4 Aug 2025 |
| Form 3File: FORM 03 VCE LLP 30 SEP 2024.pdf | 4 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY SEP 2024.pdf | 4 Aug 2025 |
| Form 1File: FORM NO 01 V C ENTERPRISES LLP.pdf | 4 Aug 2025 |
| Form 2File: FORM NO 02 V C ENTERPRISES LLP.pdf | 4 Aug 2025 |
| Form 3File: V C ENTERPRISE LLP FORM NO 3.pdf | 4 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY DEC 24.pdf | 4 Aug 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Saparate bank account.pdf | 19 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: V C ENTERPRISES LLP FORM NO 01.pdf | 18 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: V C ENTERPRISES LLP FORM NO 03.pdf | 18 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: V C ENTERPRISES LLP FORM NO 02.pdf | 18 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: VCELLP SOLD UNSOLD UNITES.pdf | 18 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate on Project Cost And Fund withdrawal VCELLP 31 3 2025.pdf | 17 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate on Cost Incurred on Project VCELLP 31 3 2025.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate of Percentage of Completion of Work VCE LLP FORM 01.pdf | 14 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO 01 V C ENTERPRISES LLP.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: V C ENTERPRISE LLP FORM NO 3.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM NO 02 V C ENTERPRISES LLP.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate of Percentage of Completion of Work.pdf | 16 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate on Project Cost And Fund withdrawal.pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate on Cost Incurred on Project.pdf | 16 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate of Percentage of Completion of Work.pdf | 18 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate on Cost Incurred on Project.pdf | 15 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD_UNSOLD INVENTORY (VISION 24DEGREE).pdf | 15 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate on Project Cost And Fund withdrawal.pdf | 15 Jul 2024 |
| Other - TechnicalFile: Declaration-Cum-Undertaking_Rera_Vision 24degree .pdf | 28 May 2024 |
| Layout approvalFile: Wadmukhwadi _ IOD _ Sheet_1_3.pdf | 27 May 2024 |
| Layout approvalFile: Wadmukhwadi _ IOD _ Sheet_2_3.pdf | 27 May 2024 |
| Layout approvalFile: Wadmukhwadi _ IOD _ Sheet_3_3.pdf | 27 May 2024 |
| Building plan approvalFile: 1_8 Sheet.pdf | 27 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 115 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VISION 24DEGREE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near WADMUKHWADI13,700+ in Pune
Filed coordinates, straight-line distance. 124 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: VISION CREATIVE ENTERPRISE LLP
VISION CREATIVE ENTERPRISE LLP has 1 registration on MahaRERA, including VISION 24DEGREE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if VISION 24DEGREE is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VISION 24DEGREE?
The registered promoter entity is VISION CREATIVE ENTERPRISE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VISION 24DEGREE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VISION 24DEGREE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VISION 24DEGREE?
The professionals named in the filing: Architect: PATIL & BUGADE ASSOCIATES; Engineer: SAURABH VIJAY BENDALE; Engineer: NARENDRA PANDURANG KULKARNI; Engineer: Rameshwar Chitale; Chartered Accountant: BANKIM PATEL & ASSOCIATES; Chartered Accountant: S N K & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VISION 24DEGREE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback