Home / Browse projects / Pune, Maharashtra / Vinayak Hills Bldg A1-A16

Registration lapsed No litigation declared Residential / Group Housing project

Vinayak Hills Bldg A1-A16

By Vinayak Promoters and Builders

RG-MH-10922 · RERA P52100001402 · Last updated on MahaRERA portal: 3 Jun 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 41 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2023Possession promised41 months past this date
39 of 88Construction stages doneacross 8 buildings; furthest along: Internal walls, 95%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

Vinayak Hills Bldg A1-A16 is a Residential / Group Housing project by Vinayak Promoters and Builders in Pune, Maharashtra, registered with MahaRERA as P52100001402 on 28 Jul 2017. Possession was promised by 30 May 2023 and is now 41 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameVinayak Hills Bldg A1-A16
  • TypeResidential / Group Housing
  • Location
    • Chikhalse
    • Mawal
    • Pune
    • 410405
  • Pincode410405
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001402
  • ReraGenie IDRG-MH-10922

Builder

  • NameVinayak Promoters and Builders
  • Entity typePartnership
  • PartnersRamesh Yugraj Kavediya, Sambhav Ramesh Kavediya
  • Declared earlier projects3 →

Key dates

41 months past promisethis monthRegisteredJul 2017First promiseMay 2022Revised toMay 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Jul 2017
  • Promised completion30 May 2023
  • Revised completionRevised to 30 May 2023 (originally 30 May 2022)
  • Buildings8 building records
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1-A2NA50000
A3-A4NA50000
A5-A6NA50000
A7-A8NA50000
A9-A10NA50000
A11-A12NA50000
A13-A14NA50000
A15-A16NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 3 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

39 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Internal walls, at 95%.

A1-A291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A3-A491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A5-A691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A7-A860%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A9-A1042%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A11-A120%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A13-A140%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A15-A160%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 3 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes70%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes20%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes80%
Open ParkingYes80%
Retaining WallYes80%

Parking filed560

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots560
Closed/Covered256
Open Space304
BuildingClosed/CoveredOpen SpaceTotal
A1-A2323870
A3-A4323870
A5-A6323870
A7-A8323870
A9-A10323870
A11-A12323870
A13-A14323870
A15-A16323870

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,384 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9904.51
Proposed, not sanctioned9,905 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCamp Pune

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr. Jitendra Thakkar
EngineerMr. Jayant V Inamdar
PartnerRole in project
Vinayak Promoters and Builders-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011987May 2022 → May 2023

Reason as filed by the promoterReason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay in grant of any NOC/permission/license/ connection installation of any services such as lifts, electricity & water connections & meters to the scheme/unit /road NOC or completion certificate from Appropriate Authority the Promoters/Owners having complied with all requirements. c. Delay by local authority in issuing or granting necessary plinth checking completion or O

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Declaration on Commencement.pdf3 Jun 2022
Form 2AFile: 2_2A-010719 to 300919.pdf3 Jun 2022
Form 2AFile: 3_2A-011019 to 311219.pdf3 Jun 2022
Form 2AFile: 4_2A-010120 to 310320.pdf3 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 1_2A-010420 to 300620.pdf3 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2_2A-010720 to 300920.pdf3 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 3_2A-011020 to 311220.pdf3 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 4_2A-010121 to 310321.pdf3 Jun 2022
CERSAI detailsFile: CERSAI_Search_Report_200238303948_For_Asset_Based_Search_27_05_2022_15_23_44_086.pdf3 Jun 2022
Disclosure of sold/ booked inventoryFile: Inventory Updation (2).pdf3 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: VINAYAK - FORM 5 2018-2019.pdf3 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: VINAYAK - FORM 5 2019-2020.pdf3 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: VINAYAK - FORM 5 2020-2021.pdf3 Jun 2022
Form 2AFile: form 2a (1).pdf13 Jun 2019
Certificates of CA (Form 5)File: RERA AUDIT FORM 5 - VINAYAK HILLS-.pdf30 Oct 2018
Proforma of Allotment letterFile: 1_20180516_AllotmentAgreement.pdf16 May 2018
Certificates of CA (Form 3)File: 7_CA_Cert.pdf25 Jul 2017
Building plan approvalFile: 4_SANCTIONED PLAN 1 OF 5.PDF24 Jul 2017
Layout approvalFile: 4_SANCTIONED PLAN 1 OF 5.PDF24 Jul 2017
PAN CardFile: 1_Entity PAN.pdf24 Jul 2017
Copy of the legal title reportFile: 3_Legal Title Report.pdf24 Jul 2017
Details of encumbrancesFile: 10_IndexII.pdf24 Jul 2017
Copy of Layout Approval (in case of layout)File: 4_SANCTIONED PLAN 1 OF 5.PDF24 Jul 2017
Building Plan Approval (IOD)File: 4_SANCTIONED PLAN 1 OF 5.PDF24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 12_Commencement Certificates.pdf24 Jul 2017
Declaration in FORM BFile: 2_FormB-ilovepdf-compressed.pdf24 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5_ArchitectCertificate.pdf24 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6_EnggCert.pdf24 Jul 2017
Proforma of Allotment letterFile: 9_AllotmentAgreement.pdf24 Jul 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Strawberry AvenueWai Panchgani Road Khanapur Mouje Kanjal Taluka Wai District Satara-CompletedDec 2015Late, Jul 2016
ROMAN HILLSSomatane Phata Pune Mumbai Bypass Road Taluka Maval District Pune32CompletedJul 2015Late, Dec 2015
Green Block BSurvey no 555 3 4 Pune Road Near Government Seed Farm Solapur 41300159CompletedJul 2015Late, Oct 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vinayak Hills Bldg A1-A16 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chikhalse13,700+ in Pune

2 kmVinayak Hills Bldg A1-A1Lapsed / revoked 3Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Vinayak Promoters and Builders

Vinayak Promoters and Builders has 1 registration on MahaRERA, including Vinayak Hills Bldg A1-A16. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Vinayak Hills Bldg A1-A16 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Vinayak Hills Bldg A1-A16 is delayed beyond 30 May 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vinayak Hills Bldg A1-A16?

The registered promoter entity is Vinayak Promoters and Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vinayak Hills Bldg A1-A16?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vinayak Hills Bldg A1-A16?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vinayak Hills Bldg A1-A16?

The professionals named in the filing: Architect: Mr. Jitendra Thakkar; Engineer: Mr. Jayant V Inamdar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vinayak Hills Bldg A1-A16?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vinayak Hills Bldg A1-A16. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vinayak Hills Bldg A1-A16 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.