Vijay Capital
RG-MH-85371 · RERA P52100047476 · Last updated on MahaRERA portal: 16 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vijay Capital is a Others project by Vijay Properties in Pune, Maharashtra, registered with MahaRERA as P52100047476 on 2 Nov 2022. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing.
At a glance
Project
- NameVijay Capital
- TypeOthers
- Location
- Pune-Nashik Highway
- Borhadewadi
- Moshi
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100047476
- ReraGenie IDRG-MH-85371
Builder
- NameVijay Properties
- Entity typeOthers
- Named personsKamal Raghunath Alhat, Rohidas Raghunath Alhat, Shobha Ashok Jadhav, Vandana Pradeep Shinde, Narayan Raghunath Alhat, Satish Patel, Sanjay Lilachand Jain, Dharmaji Maruti Alhat, Shashikala Dharmaji Alhat, Rahul Dharmaji Alhat, Deepali Rahul Alhat, Uddhav Maruti Alhat and 16 more
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on2 Nov 2022
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
- Buildings1 building record
- Documents filed93 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Vijay Capital | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 50%.
Vijay Capital: 56% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 16 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed177
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SuPa Associates Sudhir Surdi |
| Engineer | Vijay Patel |
| Engineer | SK Consultants & Engineers |
| Chartered Accountant | Khandelwal Jain & Associates |
| Chartered Accountant | Rutuja Narsingh & Associates |
| Chartered Accountant | NB Sayed & Associates |
| Partner | Role in project |
|---|---|
| Vijay Properties | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. As we have 0 sold units, we do not require consents.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Aug 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Aug 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed93
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 - Vijay Capital as on March 2026.pdf | 16 Jun 2026 |
| Form 2File: Form 2 - Vijay Capital as on March 2026.pdf | 16 Jun 2026 |
| Form 3File: Form 3 - Vijay Capital as on March 2026.pdf | 16 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Vijay Capital as on March 2026.pdf | 16 Jun 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - Vijay Capital for FY 2024-25.pdf | 5 Jun 2026 |
| Form 1File: Form 1 - Vijay Capital as on June 2025.pdf | 13 May 2026 |
| Form 2File: Form 2 - Vijay Capital as on June 2025.pdf | 13 May 2026 |
| Form 3File: Form 3 - Vijay Capital as on June 2025.pdf | 13 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Vijay Capital as on June 2025.pdf | 13 May 2026 |
| Form 1File: Form 1 - Vijay Capital as on Dec 2025.pdf | 13 May 2026 |
| Form 2File: Form 2 - Vijay Capital as on Dec 2025.pdf | 13 May 2026 |
| Form 3File: Form 3 - Vijay Capital as on Dec 2025.pdf | 13 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Vijay Capital as on Dec 2025.pdf | 13 May 2026 |
| Form 1File: Form 1 - Vijay Capital as on Dec 2025.pdf | 13 May 2026 |
| Form 2File: Form 2 - Vijay Capital as on Dec 2025.pdf | 13 May 2026 |
| Form 3File: Form 3 - Vijay Capital as on Dec 2025.pdf | 13 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Vijay Capital as on Dec 2025.pdf | 13 May 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Vijay Capital as on 31-03-2024.pdf | 16 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Vijay Capital as on 30-06-2024.pdf | 16 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Vijay Capital as on 30-09-2024.pdf | 16 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Vijay Capital as on 31-12-2024.pdf | 16 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Vijay Capital as on March 2024.pdf | 16 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Vijay Capital as on June 2024.pdf | 16 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Vijay Capital as on Sep 2024.pdf | 16 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Vijay Capital as on Dec 2024.pdf | 16 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Vijay Capital for FY 2023-24.pdf | 16 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 19 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf | 19 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 19 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf | 17 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 17 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fffffffffffff.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29.pdf | 5 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 VIJAY CAPITAL as on Dec 2023.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 VIJAY CAPITAL Sept 2023.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 VIJAY CAPITAL December 2023.pdf | 4 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 VIJAY CAPITAL - 2022-23.pdf | 4 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Vijay Capital as on Sep 2023.pdf | 2 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Vijay Capital as on Sep 2023.pdf | 2 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Format N.pdf | 26 Feb 2024 |
| Declaration in FORM BFile: FORM B VIJAY PROPERTIES.pdf | 19 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 VC.pdf | 19 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 19 Feb 2024 |
| CERSAI detailsFile: DECLARATION of Cersai.pdf | 19 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 of Vijay Capital as on 31st March 2023.pdf | 4 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE VIJAY CAPITAL Q1.pdf | 16 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Vijay Capital as on June 2023.pdf | 4 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Vijay Capital as on 30-06-2023.pdf | 4 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29 - Vijay Capital 14062023.pdf | 14 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate_compressed.pdf | 6 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Vijay Capital as on December 2022.pdf | 6 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Vijay Capital as on March 2023.pdf | 6 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Vijay Capital as on December 2022.pdf | 6 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Vijay Capital as on March 2023.pdf | 6 Jun 2023 |
| Proforma of Agreement for saleFile: AFS - Vijay - 20 10 22.pdf | 21 Oct 2022 |
| Deviation Report with respect to model copy of AgreementFile: Final Deviation - Vijay.pdf | 21 Oct 2022 |
| CERSAI detailsFile: CERSAI Declaration.pdf | 12 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Signed.pdf | 12 Oct 2022 |
| Proforma of Allotment letterFile: AFS-DECLARATION.pdf | 19 Sep 2022 |
| Deviation Report with respect to Allotment letterFile: ALLOTMENT DEVAITION declaration.pdf | 19 Sep 2022 |
| Other - TechnicalFile: Queries_Answer.pdf | 19 Sep 2022 |
| Declaration in FORM BFile: B-Form-R.pdf | 17 Sep 2022 |
| Copy of the legal title reportFile: LTR.pdf | 2 Sep 2022 |
| Details of encumbrances concerned to LegalFile: lEGAL ENCRUMBRANCES DECLARATION.pdf | 2 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold booked inventory 20220825.pdf | 2 Sep 2022 |
| Proforma of Allotment letterFile: Vijay-Capital_Allotment Letter.pdf | 2 Sep 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Escro Bank Account Declaration.pdf | 2 Sep 2022 |
| Copy of the legal title reportFile: 2022-LTR.pdf | 24 Aug 2022 |
| Details of encumbrances concerned to FinanceFile: D-ENCUMB.pdf | 24 Aug 2022 |
| Declaration about Commencement CertificateFile: CC-DECLARATION.pdf | 24 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-A-2022.pdf | 24 Aug 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2A EngCertificate-QUALITY.pdf | 24 Aug 2022 |
| Layout approvalFile: S-1.pdf | 20 Aug 2022 |
| Building plan approvalFile: S-1.pdf | 20 Aug 2022 |
| Building plan approvalFile: S-2.pdf | 20 Aug 2022 |
| Building plan approvalFile: S-3.pdf | 20 Aug 2022 |
| Building plan approvalFile: S-4.pdf | 20 Aug 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 93 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Vijay Capital on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Borhadewadi13,700+ in Pune
Filed coordinates, straight-line distance. 195 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: Vijay Properties
Vijay Properties has 1 registration on MahaRERA, including Vijay Capital. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Vijay Capital is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vijay Capital?
The registered promoter entity is Vijay Properties, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vijay Capital?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Vijay Capital?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vijay Capital?
The professionals named in the filing: Architect: SuPa Associates Sudhir Surdi; Engineer: Vijay Patel; Engineer: SK Consultants & Engineers; Chartered Accountant: Khandelwal Jain & Associates; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: NB Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vijay Capital?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback