VIDYA NAGRI
RG-MH-96529 · RERA P50400052189 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 36 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Wardha registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VIDYA NAGRI is a Plotted project by Pramod Wamanrao Kolhe in Wardha, Maharashtra, registered with MahaRERA as P50400052189 on 27 Jul 2023. Possession is promised by 31 Mar 2027. The completion date has moved by 36 months from the original filing. 14 of the 22 units on this registration are recorded sold or booked.
At a glance
Project
- NameVIDYA NAGRI
- TypePlotted
- Location
- 599/1
- Kelzar
- Seloo
- Wardha
- 442104
- Pincode442104
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50400052189
- ReraGenie IDRG-MH-96529
Builder
- NamePramod Wamanrao Kolhe
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on27 Jul 2023
- Promised completion31 Mar 2027
- Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2024)
- BuildingsNot stated in filing
- Documents filed81 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 36% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 94% |
| Landscaping & Tree Planting | Yes | 87% |
| Street Lighting | Yes | 87% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 15% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Pramod Wamanrao Kolhe | Nagpur (M Corp.) | Nagpur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 1.39 cr | Rs 1.04 cr |
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Niranjan Kande |
| Architect | Nikhil D Pohane |
| Engineer | Niranjan Kande |
| Engineer | CHAITANYA PRAMOD ZADE |
| Chartered Accountant | Suren Duragkar Duragkar |
| Chartered Accountant | CA Saloni Bang Bang |
| Chartered Accountant | SUMIT AGRAWAL |
| Chartered Accountant | SONAM THAKUR |
| Chartered Accountant | HEMMANI DURAGKAR |
| Partner | Role in project |
|---|---|
| Pramod Wamanrao Kolhe | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay in completion of the current project.
Reason as filed by the promoterWe the undersigned hereby request you to extend the RERA Registration timing up to 31st March 2027. As per your requirement our builder’s M/s Kolhe Ventures (Prop. Shri Pramod W. Kolhe) talked with us regarding extension of time. The work is Partly completed or completion of the balance project will need additional time as the proprietor had medical issues and was not able to purse the balance work on the project. Hence, the builder has requested for extension to complete the project. Also the area is under Gram Panchayat Jurisdiction the sale of the balance project will also need additional t
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Jul 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Mar 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2027
Documents filed81
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certiicate Q1 FY 26-27.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Engineer Certificate Q1 FY 2026-27 Updated.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: CA Certificate Q1 FY 26-27 (2).pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: Architect certificate Scanned final.pdf | 9 Apr 2026 |
| Withdrawal Update Form 2File: Engineer certificate final.pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: CA Certificate form 3.pdf | 9 Apr 2026 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE FORM 1.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: ENGINEER CERTIFICATE FROM 2.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: CA CERTIFICATE Q3 FORM 3.pdf | 20 Jan 2026 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE.pdf | 20 Oct 2025 |
| Withdrawal Update Form 2File: Engineers certificate.pdf | 20 Oct 2025 |
| Withdrawal Update Form 3File: CA CERTIFICATE.pdf | 20 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form 2A Signed.pdf | 30 Sep 2025 |
| Form 5 (FY 2024-2025)File: Form_5-1[1]_merged.pdf | 20 Sep 2025 |
| Withdrawal Update Form 1File: Signed scanned copy of Architect Certificate June 2025.pdf | 29 Jul 2025 |
| Withdrawal Update Form 2File: Signed Scanned copy of Engineeru0027s Certificate June 2025.pdf | 29 Jul 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 29 Jul 2025 |
| Withdrawal Update Form 1File: Signed scanned copy of Architect Certificate June 2025.pdf | 18 Jul 2025 |
| Withdrawal Update Form 1File: Signed scanned copy of Architect Certificate June 2025.pdf | 18 Jul 2025 |
| Withdrawal Update Form 1File: Signed scanned copy of Architect Certificate June 2025.pdf | 18 Jul 2025 |
| Withdrawal Update Form 1File: Signed scanned copy of Architect Certificate June 2025.pdf | 18 Jul 2025 |
| Withdrawal Update Form 1File: Signed scanned copy of Architect Certificate June 2025.pdf | 18 Jul 2025 |
| Withdrawal Update Form 2File: Signed Scanned copy of Engineeru0027s Certificate June 2025.pdf | 18 Jul 2025 |
| Withdrawal Update Form 2File: Signed Scanned copy of Engineeru0027s Certificate June 2025.pdf | 18 Jul 2025 |
| Withdrawal Update Form 2File: Signed Scanned copy of Engineeru0027s Certificate June 2025.pdf | 18 Jul 2025 |
| Withdrawal Update Form 2File: Signed Scanned copy of Engineeru0027s Certificate June 2025.pdf | 18 Jul 2025 |
| Withdrawal Update Form 2File: Signed Scanned copy of Engineeru0027s Certificate June 2025.pdf | 18 Jul 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 18 Jul 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 18 Jul 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 18 Jul 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 18 Jul 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 18 Jul 2025 |
| Form 1File: Architect Certificate Jan-Mar 25.pdf | 17 Jun 2025 |
| Form 2File: Engineer Certificate Jan-Mar 25.pdf | 17 Jun 2025 |
| Form 3File: CA CERTIFICATE Jan- Mar 25.pdf | 17 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventory.pdf | 17 Jun 2025 |
| Form 5 (FY 2023-2024)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf | 17 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Oct-Dec 24 (1).pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Jan-Mar 25.pdf | 6 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q3_compressed.pdf | 6 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Jan- Mar 25.pdf | 6 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Oct-Dec 24.pdf | 6 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Jan-Mar 25.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect certificate.pdf | 27 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 CA Certificate Kolhe Ventures_compressed.pdf | 27 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA Certificate_compressed.pdf | 27 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate.pdf | 27 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf | 27 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 eng certificate.pdf | 19 Jun 2024 |
| Declaration in FORM BFile: Form B Declaration.pdf | 12 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 12 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 - ENGINEERS CERTIFICATE_compressed.pdf | 12 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold inventory.pdf | 12 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf | 12 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jul to Sept 23_compressed.pdf | 24 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Oct to Dec 23_compressed.pdf | 24 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Jan to Mar 24_compressed.pdf | 24 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kolhe Ventures_Form 3 Final.pdf | 23 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account.pdf | 21 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: Financial Encumbrance.pdf | 20 Jul 2023 |
| Details of encumbrances concerned to LegalFile: Financial Encumbrance.pdf | 20 Jul 2023 |
| CERSAI detailsFile: Cersai.pdf | 20 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 20 Jul 2023 |
| Proforma of Agreement for saleFile: Proforma_of_Agreement_for_sale.pdf | 20 Jul 2023 |
| Copy of the legal title reportFile: PRAMOD KOLHE SEARCH REPORT_compressed.pdf | 16 Jul 2023 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 16 Jul 2023 |
| Deviation Report with respect to Allotment letterFile: Allotment Deviation.pdf | 16 Jul 2023 |
| Deviation Report with respect to model copy of AgreementFile: Agreement Deviation.pdf | 16 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form_1 Kelzar.pdf | 29 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Form_2 Kelzar.pdf | 29 Mar 2023 |
| Declaration in FORM BFile: Form B.pdf | 27 Mar 2023 |
| Layout approvalFile: LAYOUT MAP_compressed.pdf | 20 Mar 2023 |
| Building plan approval or NA orderFile: NA Order for plotted development_compressed.pdf | 20 Mar 2023 |
| PAN CardFile: Pan.pdf | 20 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: Legal Encumbrance (2).pdf | 20 Mar 2023 |
| Details of encumbrances concerned to LegalFile: Legal Encumbrance (2).pdf | 20 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: LAYOUT MAP_compressed.pdf | 20 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: NA Order for plotted development_compressed.pdf | 20 Mar 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order for plotted development_compressed.pdf | 20 Mar 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Wardha
Computed across the 290+ Wardha projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 81 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VIDYA NAGRI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kelzar290+ in Wardha
KESARIYA NAGARI
RAKESH M. MADE
KINGS VILLAGE
VYANKATESH ASSETS MAXIMIZER ASSETS PRIVATE
DEHU AALANDI PARK
DAMOHAR MAHADEORAO MANKAR
SHREE KRISHNA NAGAR
ARTH LAND DEVELOPERS
GANESH NAGAR
Sanjay Tejmal Ostwal
KIRANGE NAGARI
VISHVANATH RAMA KIRANGE
See every Wardha project, with the district possession charts
Builder: Pramod Wamanrao Kolhe
Pramod Wamanrao Kolhe has 1 registration on MahaRERA, including VIDYA NAGRI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Wardha district page.
Frequently asked questions
What are my rights if VIDYA NAGRI is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VIDYA NAGRI?
The registered promoter entity is Pramod Wamanrao Kolhe, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VIDYA NAGRI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VIDYA NAGRI?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VIDYA NAGRI?
The professionals named in the filing: Architect: Niranjan Kande; Architect: Nikhil D Pohane; Engineer: Niranjan Kande; Engineer: CHAITANYA PRAMOD ZADE; Chartered Accountant: Suren Duragkar Duragkar; Chartered Accountant: CA Saloni Bang Bang. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VIDYA NAGRI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback