Registered Litigation declared Residential / Group Housing project

Verona

By Sahyog Homes Limited

RG-MH-09448 · RERA P51800003040 · Last updated on MahaRERA portal: 26 Mar 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 6 cases
  • 84 complaints at MahaRERA
  • Completion date moved by 53 months
  • 2 extensions taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 53 months from the original
6 of 11Construction stages donefurthest along: Staircases, 98%
91 of 290Units unsoldnot recorded sold or booked
84Complaints at MahaRERAon this registration
Jump to the 197 documents Report an error

Verona is a Residential / Group Housing project by Sahyog Homes Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003040 on 4 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 53 months from the original filing. 199 of the 290 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 84 complaints are on record with the regulator.

At a glance

Project

  • NameVerona
  • TypeResidential / Group Housing
  • Location
    • Relief Road
    • Oshiwara
    • Andheri
    • Mumbai Suburban
    • 400102
  • Pincode400102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003040
  • ReraGenie IDRG-MH-09448

Builder

  • NameSahyog Homes Limited
  • Entity typeCompany
  • DirectorsRajiv Goel, Yogesh Jadhav, Rahul Jain
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredAug 2017First promiseJul 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Jul 2023)
  • Buildings1 building record
  • Documents filed197 files

Current status

69%199 of 290 units booked
65.5%Work done, per cost certificate

Figures as on 26 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Verona S3-S4NA42382900290

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 98%.

Verona S3-S4: 78% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 26 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes-
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed268

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots268
Closed/Covered268

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,554 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Sankalp Siddhi Developers Pvt LtdBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority Brihanmumbai
Permissible FSI23061.78
Proposed, not sanctioned20,435 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround and First Floor Maurya Estate Link Road Andheri West Mumbai 400053
Estimated costRs 238.00 cr
Cost incurredRs 155.98 cr
Work done65.54%
BuildingWingEstimatedIncurred
Verona S3-S4NARs 229.19 crRs 155.98 cr
-NARs 8.81 cr-

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEllora Project Consultants Pvt Ltd
ArchitectSagar Gogri
ArchitectPradip Deshmukh
ArchitectCreation TOWN PLANNER & ARCHITECT ENGINEERS
EngineerRajesh Laxman Patil
EngineerRamboll India Pvt. Ltd.
EngineerMohan Khot
EngineerMohan Khot Project Mangement Cosultant
Chartered AccountantV.P. Agrawal & Co.
Chartered AccountantShah & Bhosale
PartnerRole in project
Sahyog Homes Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017250Jul 2023 → Dec 2024

Reason as filed by the promoterReasons for delay: The list containing the reasons for delay in completion of project is enclosed herewith and summarised as under: 1) Delay due to reasons beyond the control of promoter viz. delay in getting permissions from the concerned authorities. 2) Covid -19 situation and financial crises due to it 3) Project is supposed to be completed by Sankalp Siddhi Developers Pvt.Ltd. in lieu of consideration as per Development Agreement dated 9.07.2012. Sankalps failed to fulfill its obligation under the Development Agreement dated 9.07.2012.

EXT51800025954Jul 2023 → Dec 2027

Reason as filed by the promoterAs per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. As per HEARING DATED 3rd March 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31/12/2027. The order is Other Tab for your reference

Litigation declared6

CaseCourtStatus
965/2014High Court BombayOngoing
6437/2015High Court BombayOngoing
1213/2011City Civil Court DindoshiOngoing
407/2012Metropolitan Magistrate AndheriNot heard
8026, 8027, 8028/2018Revenue and Textile Minister MantralayaFor filing Reply
8026, 8027, 8028/2018Revenue and Textile Minister MantralayaOngoing

Complaints filed with MahaRERA84

Case no.ComplainantRespondentFiled
CC006000000194046MRS. ASIFA MOINUDDIN SHAIKHSAHYOG HOMES LIMITED28/09/2020
CC006000000194806Sahyog Homes LimitedShashi Udhas04/11/2020
CC006000000194807Sahyog Homes LimitedEshan Aggarwal Through Guardian Manav Agarwal04/11/2020
CC006000000194808Sahyog Homes LimitedShashi Udhas04/11/2020
CC006000000194809Sahyog Homes LimitedManav Aggarwal04/11/2020
CC006000000194810Sahyog Homes LimitedShirin Agarwal & Anr04/11/2020
CC006000000194812Sahyog Homes LimitedManav Aggarwal04/11/2020
CC006000000194814Sahyog Homes LimitedShashi Udhas04/11/2020
CC006000000194815Sahyog Homes LimitedManav Aggarwal04/11/2020
CC006000000197403Sahyog Homes LimitedQaeed Kuwajerwala through CA Husein Kuwajerwala24/06/2021
CC006000000197404Sahyog Homes LimitedKarimi Nuruddin Mantri & Anr. through CA Husein Kuwajerwala24/06/2021
CC006000000197405Sahyog Homes LimitedNazira Hasnain Lala & anr. through Husein Kuwajerwala24/06/2021
CC006000000197406Sahyog Homes LimitedHusein Kuwajerwala & Anr24/06/2021
CC006000000197407Sahyog Homes LimitedHusein Kuwajerwala and anr.24/06/2021
CC006000000197408Sahyog Homes LimitedKarimi Nuruddin Mantri & Anr. through CA Husein Kuwajerwala24/06/2021
CC006000000197409Sahyog Homes LimitedNafisa Gulamabbas Kapasi & Anr24/06/2021
CC006000000056265MR. KRISHNA KISHORE AGARWAL AND VEENA AGARWALSAHYOG HOMES LIMITED01/10/2018
CC006000000055409Mr. Shrivatsa Moraje & Mrs. Nayana RaoSahyog Homes Ltd.16/12/2019
CC006000000056251Arif AnsariSahyog Homes Ltd19/09/2018
CC006000000057399Vishal JainSahyog Homes Limited22/12/2018
CC006000000057433Viloo Keki ItaliaSahyog Homes Limited25/12/2018
CC006000000057751Prabhudesai SulabhaKeshav Porwal24/01/2019
CC006000000397946sulabha shridhar prabhudesaiSahyog Homes Ltd25/10/2023
CC006000000398028sulabha shridhar prabhudesaiSahyog Homes31/10/2023
CC006000000057760SHIRIN AGARWALSAHYOG HOMES LIMITED28/01/2019
CC006000000057761ESHAN AGGARWALSAHYOG HOMES LIMITED28/01/2019
CC006000000057767MANAV AGGARWALSAHYOG HOMES28/01/2019
CC006000000057844MANAV AGGARWALSAHYOG HOMES LIMITED28/01/2019
CC006000000057804MANAV AGGARWALSAHYOG HOMES LIMITED28/01/2019
CC006000000057843SHASHI UDHASSAHYOG HOMES LIMITED28/01/2019
CC006000000057848SHASHI UDHASSAHYOG HOMES LIMITED28/01/2019
CC006000000057849SHASHI UDHASSAHYOG HOMES LIMITED28/01/2019
CC006000000068144Nafisa Gulamabbas KapasiSahyog Homes03/03/2019
CC006000000058131Qaeed KuwajerwalaSahyog Homes Limited03/03/2019
CC006000000058137Husein K KuwajerwalaSahyog Homes Limited03/03/2019
CC006000000058139Tina Kumar DarireSahyog Homes Limited03/03/2019
CC006000000058140Karimi Nuruddin MantriSahyog Homes Limited03/03/2019
CC006000000058134Hina Karim MantriSahyog Homes Limited03/03/2019
CC006000000058136Nazira Hasnain LalaSahyog Homes Limited05/03/2019
CC006000000058142Zeenat Z MantriSahyog homes Limited05/03/2019
CC006000000068141Sonam KapoorSahyog Homes Limited03/03/2019
CC006000000068143Rhea KapoorSahyoig Homes Limited03/03/2019
CC006000000068164Narendra Maganlal UpadhyayM/s Sahyog homes & M/s Sankalp Siddhi Pvt Ltd03/05/2019
CC006000000192380SUSHIL RAJPALSAHYOG HOMES LIMITED01/02/2020
CC006000000192464Vikas BhauwalaSahyog Homes Limited19/02/2020
CC006000000197518Sahyog Homes LimitedManav Agarwal06/07/2021
CC006000000197519Sahyog Homes LimitedManav Agarwal06/07/2021
CC006000000197521Sahyog Homes LimitedShirin Agarwal06/07/2021
CC006000000197522Sahyog Homes LimitedManav Agarwal06/07/2021
CC006000000197523Sahyog Homes LimitedEshan Agarwal06/07/2021
CC006000000197524Sahyog Homes LimitedShashi Udhas06/07/2021
CC006000000197525Sahyog Homes LimitedPradeep Udhas06/07/2021
CC006000000197526Sahyog Homes LimitedShashi Udhas06/07/2021
CC006000000197527Sahyog Homes LimitedSonam Kapoor06/07/2021
CC006000000197528Sahyog Homes LimitedRhea Kapoor06/07/2021
CC006000000197529Sahyog Homes LimitedZeenat Mantri06/07/2021
CC006000000197115Hafiza Nisarahmed TamboliSAHYOG HOMES LIMITED01/06/2021
CC006000000198580Rohit KhannaSahyog Homes Limited07/10/2021
CC006000000198876Ramawatar SharmaSahyog Homes Limited15/11/2021
CC006000000198995Santosh Kumar JainSahyog Homes Limited07/12/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed197

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 197 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2019-2020)File: Form 2A - 2019 - 2020.pdf26 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A - 2024 - 2025.pdf26 Mar 2026
Form 2A (FY 2020-2021)File: Form 2A - 2020 - 2021.pdf26 Mar 2026
Form 2A (FY 2021-2022)File: Form 2A - 2021 - 2022.pdf26 Mar 2026
Form 2A (FY 2022-2023)File: Form - 2A - 2022 - 2023.pdf26 Mar 2026
Withdrawal Update Form 1File: Form 1 - Dec 2025.pdf23 Mar 2026
Withdrawal Update Form 1File: Form 1 - Sep 2025.pdf23 Mar 2026
Withdrawal Update Form 1File: Form 1 - Dec 2025.pdf23 Mar 2026
Withdrawal Update Form 2File: Form 2 - Dec 2025.pdf23 Mar 2026
Withdrawal Update Form 2File: Form 2 - Dec 2025.pdf23 Mar 2026
Withdrawal Update Form 2File: Form 2 - Dec 2025.pdf23 Mar 2026
Withdrawal Update Form 3File: Form 3 - Dec 2025.pdf23 Mar 2026
Withdrawal Update Form 3File: Form 3 - Sep 2025.pdf23 Mar 2026
Withdrawal Update Form 3File: Form 3 - Dec 2025.pdf23 Mar 2026
Withdrawal Update Form 1File: Form 1 - Jun 2025.pdf6 Mar 2026
Withdrawal Update Form 1File: Form 1 - Sep 2025.pdf6 Mar 2026
Withdrawal Update Form 1File: Form 1 - Sep 2025.pdf6 Mar 2026
Withdrawal Update Form 2File: Form 2 Engineer Certi_Verona_30062024.pdf6 Mar 2026
Withdrawal Update Form 2File: Form 2 - Sep 2025.pdf6 Mar 2026
Withdrawal Update Form 2File: Form 2 - Sep 2025.pdf6 Mar 2026
Withdrawal Update Form 3File: Form 3 - Jun 2025.pdf6 Mar 2026
Withdrawal Update Form 3File: Form 3 - Sep 2025.pdf6 Mar 2026
Withdrawal Update Form 3File: Form 3 - Sep 2025.pdf6 Mar 2026
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory VERONA.pdf21 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect Certificate_30032025.pdf16 Apr 2025
Certificates of CA (Form 3)File: Form-3 CA Certificate.pdf16 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engineer Certificate.pdf16 Apr 2025
Declaration in FORM BFile: 6 (1).pdf19 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: From 5 18-19.pdf19 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf19 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf19 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf19 Mar 2025
Disclosure of sold/ booked inventoryFile: Circular 29 Dec 2024.pdf19 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf19 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf19 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf19 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf19 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf19 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf19 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf19 Mar 2025
OtherFile: Order_RC_340 of 2025_Extension_Verona.pdf7 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 2024.pdf23 Jan 2025
Certificates of CA (Form 3)File: Form 3 Dec 2024.pdf23 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 2024.pdf23 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Sept 2024.pdf2 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A - Quantity assurance certificate FY 2023-24.pdf2 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - CA Certificate.pdf2 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_ VERONA_07102024.pdf14 Oct 2024
Certificates of CA (Form 3)File: Form 3_ C A Certificate 10102024.pdf14 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_ VERONA_07102024.pdf14 Oct 2024
Certificates of CA (Form 3)File: Form 3_ C A Certificate 10102024.pdf14 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certi Verona_30062024.pdf6 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certi_Verona_30062024.pdf6 Jul 2024
Certificates of CA (Form 3)File: Form 3 C A Certificate - Verona.pdf6 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate.pdf8 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Engineer Certificate.pdf8 Apr 2024
Certificates of CA (Form 3)File: Form 3- CA Certificate.pdf8 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-5 dt 010424 (VERONA).pdf2 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 VERONA_31122023.pdf10 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2_Verona_S3_S4.pdf10 Jan 2024
Certificates of CA (Form 3)File: CA Cert Form3 VERONA.pdf10 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf10 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf10 Oct 2023
Certificates of CA (Form 3)File: CA Certificate_1.pdf10 Oct 2023
OtherFile: Declaration_Co-Promoter 10102023.pdf10 Oct 2023
Declaration in FORM BFile: Declaration Form B New.pdf1 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A.pdf1 Aug 2023
Disclosure of sold/ booked inventoryFile: D.pdf1 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf7 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf7 Jul 2023
Certificates of CA (Form 3)File: Verona CA Certi.pdf7 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VERONA_Form 1 Architect Certificate.pdf7 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Verona.pdf7 Apr 2023
Certificates of CA (Form 3)File: CA Certificate Form 3 - Verona.pdf7 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold-Booked Inventory - Verona.pdf18 Jan 2023
Proforma of Agreement for saleFile: Verona-AFS Proforma as on 17-01-2023.pdf18 Jan 2023
Proforma of Allotment letterFile: Allotment_VERONA.pdf18 Jan 2023
Declaration about Commencement CertificateFile: Declaration Commencement Certificate_Verona.pdf16 Jan 2023
PAN CardFile: SHL-PAN CARD (1).pdf12 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2.pdf12 Jan 2023

How this compares with Mumbai Suburban

69%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 53 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Verona on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Oshiwara6,700+ in Mumbai Suburban

2 kmVeronaCompleted 120Lapsed / revoked 69Abeyance 1Other 133Dot size: filed unitsN

Filed coordinates, straight-line distance. 323 registered projects within 2 km.

Builder: Sahyog Homes Limited

Sahyog Homes Limited has 2 registrations on MahaRERA, including Oshi and Verona. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Verona is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Verona?

The registered promoter entity is Sahyog Homes Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Verona?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Verona?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Verona?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Verona?

The professionals named in the filing: Architect: Ellora Project Consultants Pvt Ltd; Architect: Sagar Gogri; Architect: Pradip Deshmukh; Architect: Creation TOWN PLANNER & ARCHITECT ENGINEERS; Engineer: Rajesh Laxman Patil; Engineer: Ramboll India Pvt. Ltd.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Verona?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Verona. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Verona to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.