Home / Browse projects / Pune, Maharashtra / VENKATESH ANANDMAYI

Registered No litigation declared Residential / Group Housing project

VENKATESH ANANDMAYI

By SHREE VENKATESH ENTERPRISES

RG-MH-40403 · RERA P52100055046 · Last updated on MahaRERA portal: 14 Jul 2026

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 9 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2027Possession promisedmoved 12 months from the original
10 of 20Construction stages doneacross 2 buildings; furthest along: Internal walls, 99%
53 of 92Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 117 documents Report an error

VENKATESH ANANDMAYI is a Residential / Group Housing project by SHREE VENKATESH ENTERPRISES in Pune, Maharashtra, registered with MahaRERA as P52100055046 on 26 Feb 2024. Possession is promised by 30 Sep 2027. The completion date has moved by 12 months from the original filing. 39 of the 92 units on this registration are recorded sold or booked, and 10 of 20 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameVENKATESH ANANDMAYI
  • TypeResidential / Group Housing
  • Location
    • SINHAGAD COLLEGE ROAD
    • AMBEGAON BUDRUK
    • AMBEGAON Bk
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100055046
  • ReraGenie IDRG-MH-40403

Builder

  • NameSHREE VENKATESH ENTERPRISES
  • Entity typePartnership
  • GSTIN27AETFS0357P1Z4
  • PartnersANKUSH BHIMRAO ASABE, LAHURAJ BHIMRAO ASABE, GAJANAN MOTIRAM PANJARKAR, PIYUSHA ANKUSH ASABE, PRATIK SHAILESH KOTMIRE, SHUBHAM SAHEBRAO DANDGE
  • Declared earlier projects9 →

Key dates

this monthRegisteredFeb 2024First promiseSep 2026Revised toSep 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Feb 2024
  • Promised completion30 Sep 2027
  • Revised completionRevised to 30 Sep 2027 (originally 30 Sep 2026)
  • Buildings2 building records
  • Documents filed117 files

Current status

42%39 of 92 units booked
73.4%Work done, per cost certificate

Figures as on 14 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VENKATESH ANANDMAYI WING BNA141246046
VENKATESH ANANDMAYI WING A-141246046

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 20 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 99%.

VENKATESH ANANDMAYI WING B97%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises87%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.86%
VENKATESH ANANDMAYI WING A54%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises12%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes70%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed214

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots214
Closed/Covered168
Stilt / Ground21
Basement25
BuildingClosed/CoveredStilt / GroundBasementTotal
VENKATESH ANANDMAYI WING B840084
VENKATESH ANANDMAYI WING A842125130

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,200 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Jun 2025
LandownerVillageDistrict
UMA PRABHAKAR MUSALEMarket YardPune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI7692.4
Proposed, not sanctioned7,692 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJANGLI MAHARAJ ROAD DISTT. PUNE, MAHARASHTRA 411004
Estimated costRs 24.67 cr
Cost incurredRs 18.12 cr
Work done73.44%
BuildingWingEstimatedIncurred
VENKATESH ANANDMAYI WING BNARs 11.88 crRs 11.88 cr
VENKATESH ANANDMAYI WING ANARs 11.88 crRs 5.56 cr
-NARs 91.04 lakhRs 68.28 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJAY E AMLE
EngineerMahendra Rampure
EngineerNIKHIL MILIND GHOLAP
Chartered AccountantSunilkumar Wadhwani
Chartered AccountantAvinash Jeevan Utgikar
PartnerRole in project
SHREE VENKATESH ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA12052620931Sep 2026 → Sep 2027

Reason as filed by the promoterWing A of project Venkatesh Anandmayi the FSI and TDR utilization is not done on time due to this reason we require Project Extension by 30-Sept-27.

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
SM12600132Ram GawaliSHREE VENKATESH ENTERPRISES09/02/2026
SM12600248Ram GawaliSHREE VENKATESH ENTERPRISES06/04/2026
SM12600303Ram GawaliSHREE VENKATESH ENTERPRISES07/05/2026
SM12600308Ram GawaliSHREE VENKATESH ENTERPRISES07/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jun 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2027

Documents filed117

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE-ANANDMAYI-JUN-26.pdf14 Jul 2026
Withdrawal Update Form 2File: ENGG CERTIFICATE-ANANDMAYI-JUN-26.pdf14 Jul 2026
Withdrawal Update Form 3File: CA CERTIFICATE - ANANDMAYI-JUN-2026.pdf14 Jul 2026
Building plan approvalFile: 2-5.pdf13 Jun 2026
Building plan approvalFile: 3-5.pdf13 Jun 2026
Building plan approvalFile: 4-5.pdf13 Jun 2026
Building plan approvalFile: 5-5.pdf13 Jun 2026
Layout approvalFile: 1-5-LAYOUT.pdf28 May 2026
Building plan approvalFile: 2-5.pdf28 May 2026
Building plan approvalFile: 3-5.pdf28 May 2026
Building plan approvalFile: 4-5.pdf28 May 2026
Building plan approvalFile: 5-5.pdf28 May 2026
Withdrawal Update Form 1File: Arch Certificate - VENKATESH ANANDMAYI-07-01-2026.pdf16 May 2026
Withdrawal Update Form 2File: Enginner Certificate -VENKATESH ANANDMAYI- 07-01-2026.pdf16 May 2026
Withdrawal Update Form 3File: CA CERTIFICATE ANANDMAYI SEPT-25.pdf16 May 2026
Form 5 (FY 2025-2026)File: FORM 5-ANANDMAYI-MAR-26-15-5-2026.pdf14 May 2026
Form 2A (FY 2025-2026)File: FORM 2A-ANANDMAYI-MAR-26-12-5-2026.pdf12 May 2026
Withdrawal Update Form 1File: ARCH CERTIFICATE ANANDMAYI-MAR-2026.pdf24 Apr 2026
Withdrawal Update Form 1File: Arch Certificate - VENKATESH ANANDMAYI-07-01-2026.pdf24 Apr 2026
Withdrawal Update Form 2File: ENGG CERTIFICATE -ANANDMAYI-MAR-2026.pdf24 Apr 2026
Withdrawal Update Form 2File: Enginner Certificate -VENKATESH ANANDMAYI- 07-01-2026.pdf24 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE ANANDMAYI-MAR-2026.pdf24 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE - ANANDMAYI -7-1-2026.pdf24 Apr 2026
Layout approvalFile: 1-5.pdf9 Jan 2026
Building plan approvalFile: 2-5.pdf9 Jan 2026
Building plan approvalFile: 3-5.pdf9 Jan 2026
Building plan approvalFile: 4-5.pdf9 Jan 2026
Building plan approvalFile: 5-5.pdf9 Jan 2026
Declaration and undertaking (Annexure A)File: ANNEXURE A- DECLARATION-CUM-UNDERTAKING-ORDER 50.pdf9 Jan 2026
Form 2A (FY 2024-2025)File: FORM 2A VENKATESH ANANDMAYI MAR-2025-LATEST FORMAT.pdf9 Jan 2026
Withdrawal Update Form 1File: ARCH CERTIFICATE -ANANDMAYI -SEPT-25.pdf17 Oct 2025
Withdrawal Update Form 2File: ENGG CERTIFICATE ANANDMAYI-SEPT-25.pdf17 Oct 2025
Withdrawal Update Form 3File: CA CERTIFICATE ANANDMAYI SEPT-25.pdf17 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5- ANANDMAYI-15-10-2025.pdf14 Oct 2025
Withdrawal Update Form 1File: ARCH CERTIFICATE ANANDMAYI-JUN-2025.pdf17 Jul 2025
Withdrawal Update Form 2File: ENGG CERTIFICATE ANANDMAYI-JUN-2025.pdf17 Jul 2025
Withdrawal Update Form 3File: CA CERTIFICATE ANANDMAYI-JUN-25.pdf17 Jul 2025
Form 1File: ARCH CERTIFICATE VENKATESH ANANDMAYI.pdf25 Jun 2025
Form 2File: ENGG CERTIFICATE - ANANDMAYI.pdf25 Jun 2025
Form 3File: CA CERTIFICATE VENKATESH ANANDMAYI.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSER OF SOLD UNSOLD INVENTORY ANANDMAYI.pdf25 Jun 2025
Form 1File: ARCH CERTIFICATE ANANDMAYI.pdf25 Jun 2025
Form 2File: ENGG CERTIFICATE ANANDMAYI.pdf25 Jun 2025
Form 3File: CA CERTIFICATE ANANDMAYI.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY ANANDMAYI.pdf25 Jun 2025
Form 1File: ARCH CERTIFICATE VENKATESH ANANDMAYI.pdf25 Jun 2025
Form 2File: ENGG CERTIFICATE ANANDMAYI-1-10-24.pdf25 Jun 2025
Form 3File: CA CERTIFICATE VENKATESH ANANDMAYI.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSER OF SOLD INVENTORY ANANDMAYI.pdf25 Jun 2025
Form 1File: ARCH CERTIFICATE VENKATESH ANANDMAYI.pdf25 Jun 2025
Form 2File: ENGG CERTIFICATE ANANDMAYI-1-1-25.pdf25 Jun 2025
Form 3File: CA CERTIFICATE ANANDMAYI-2-1-2025.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSER OF SOLD UNSOLD UNITS ANANDMAYI-1-1-25.pdf25 Jun 2025
Form 1File: ARCH CERTIFICATE ANANDMAYI.pdf25 Jun 2025
Form 2File: ENGG CERTIFICATE ANANDMAYI.pdf25 Jun 2025
Form 3File: CA CERTIFICATE ANANDMAYI.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSER OF SOLD UNSOLD INVENTORY ANANDMAYI.pdf25 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE ANANDMAYI.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE ANANDMAYI.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE ANANDMAYI.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD UNSOLD INVENTORY ANANDMAYI.pdf16 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A VENKATESH ANANDMAYI MAR-2025.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE VENKATESH ANANDMAYI.pdf11 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE ANANDMAYI-2-1-2025.pdf11 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE ANANDMAYI-1-1-25.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD UNSOLD UNITS ANANDMAYI-1-1-25.pdf11 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A VENKATESH ANANDMAYI DEC-2024.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE VENKATESH ANANDMAYI.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE VENKATESH ANANDMAYI.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE ANANDMAYI-1-10-24.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD INVENTORY ANANDMAYI.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 ANANDMAYI.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A VENKATESH ANANDMAYI SEPT-2024.pdf7 Oct 2024
Form 5 (FY 2023-2024)File: FORM 5 ANANDMAYI.pdf23 Sep 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE ANANDMAYI.pdf11 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE ANANDMAYI.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY ANANDMAYI.pdf11 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE ANANDMAYI.pdf11 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A VENKATESH ANANDMAYI JUNE-2024.pdf9 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE VENKATESH ANANDMAYI.pdf10 Apr 2024

Promoter's earlier projects9

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

9 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
VENKATESH GRAFFITI ELAN PHASE 2MUNDHWA MANJARI ROAD KESHAVNAGAR MUNDHWA PUNE 411036124CompletedJun 2024Sep 2023
VENKATESH GRAFFITI ELAN PHASE 1Sr No 32 2B Manjiri Mundhwa Road Keshav Nagar Mundhwa PUNE 411036125CompletedMay 2024Sep 2023
VENKATESH GRAFFITI GLOVER PHASE 3 - MHADAMUNDHWA MANJIRI ROAD KESHAV NAGAR MUNDHWA PUNE 41103660CompletedSep 2023Aug 2023
VENKATESH GRAFFITI ELITE PHASE 2MUNDHWA MANJARI ROAD KESHAVNAGAR MUNDHWA PUNE 411036101CompletedDec 2022Jun 2021
Venkatesh Graffiti Elite Phase 1Sr 31 2 2B Beside Venkatesh Graffiti Open Space 1 Mundhwa Manjari Rd Keshav Nagar PUNE 41103690CompletedAug 2022Nov 2020
VENKATESH NAVITA101 by 7 AMBEGAON KHURD PUNE 411046174CompletedDec 2021Jun 2021
VENKATESH JOYNEST PHASE - 5PUNE SOLAPUR ROAD LONI KALBHOR PUNE 41220139CompletedMar 2020Dec 2019
VENKATESH JOYNEST PHASE 4PUNE SOLAPUR HIGHWAY LONI KALBHOR PUNE 41220143CompletedDec 2019Nov 2019
VENKATESH JOYNEST PHASE 3PUNE SOLAPUR ROAD LONI KALBHOR PUNE 41220186CompletedSep 2019May 2019

How this compares with Pune

42%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VENKATESH ANANDMAYI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMBEGAON BUDRUK13,700+ in Pune

2 kmVENKATESH ANANDMAYICompleted 80Lapsed / revoked 30Other 65Dot size: filed unitsN

Filed coordinates, straight-line distance. 175 registered projects within 2 km.

Builder: SHREE VENKATESH ENTERPRISES

SHREE VENKATESH ENTERPRISES has 1 registration on MahaRERA, including VENKATESH ANANDMAYI. Its filings disclose 9 earlier MahaRERA projects: declares 9 of 9 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VENKATESH ANANDMAYI is delayed beyond 30 Sep 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VENKATESH ANANDMAYI?

The registered promoter entity is SHREE VENKATESH ENTERPRISES, a partnership as per the filing. Its GSTIN 27AETFS0357P1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VENKATESH ANANDMAYI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VENKATESH ANANDMAYI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VENKATESH ANANDMAYI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VENKATESH ANANDMAYI?

The professionals named in the filing: Architect: AJAY E AMLE; Engineer: Mahendra Rampure; Engineer: NIKHIL MILIND GHOLAP; Chartered Accountant: Sunilkumar Wadhwani; Chartered Accountant: Avinash Jeevan Utgikar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VENKATESH ANANDMAYI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VENKATESH ANANDMAYI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VENKATESH ANANDMAYI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.