Home / Browse projects / Pune, Maharashtra / Ved - Ashritha Phase I

Completed No litigation declared Residential / Group Housing project

Ved - Ashritha Phase I

By Yogvinda Promoters & Developers Pvt. Ltd.

RG-MH-10837 · RERA P52100002175 · Last updated on MahaRERA portal: 11 Mar 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 50 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2023Possession promisedregistration recorded completed
9 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 32 documents Report an error

Ved - Ashritha Phase I is a Residential / Group Housing project by Yogvinda Promoters & Developers Pvt. Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100002175 on 31 Jul 2017. The registration is recorded completed; possession was promised by 31 Oct 2023. The completion date has moved by 50 months from the original filing.

At a glance

Project

  • NameVed - Ashritha Phase I
  • TypeResidential / Group Housing
  • Location
    • Katraj Kondhwa Road
    • Katraj
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002175
  • ReraGenie IDRG-MH-10837

Builder

  • NameYogvinda Promoters & Developers Pvt. Ltd.
  • Entity typeCompany
  • Managing DirectorGANESH VASANT JARANDE
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredJul 2017First promiseAug 2019Revised toOct 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Jul 2017
  • Promised completion31 Oct 2023
  • Revised completionRevised to 31 Oct 2023 (originally 15 Aug 2019)
  • Buildings2 building records
  • Documents filed32 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ved-Ashritha Phase INA80000
Ved - Ashritha Phase IINA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 11 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

Ved-Ashritha Phase I82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Ved - Ashritha Phase II0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed72

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots72
Closed/Covered59
Open Space13
BuildingClosed/CoveredOpen SpaceTotal
Ved-Ashritha Phase I22628
Ved - Ashritha Phase II37744

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
Minanath Pandharinath MorePimpri Chinchawad (M Corp.)Pune
Vikram Minanath MorePimpri Chinchawad (M Corp.)Pune
Urmila Minanath MorePimpri Chinchawad (M Corp.)Pune
Sangramshinh Minanath MorePimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Permissible FSI5154.48
Proposed, not sanctioned2,045 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDHANKAWADE PATIL HOUSE SR NO 20 OBLIC 2 PUNE SATARA ROAD DHANKAWADI PUNE 411043

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAniruddhe Tanaji Shinde
ArchitectMilind Anil Joshi
EngineerRamchandra Krishnarao Randhave
Chartered AccountantKailash R Mundada
PartnerRole in project
Yogvinda Promoters & Developers Pvt. Ltd.-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100002046Aug 2019 → Aug 2020

Reason as filed by the promoterDate:- 29.06.2019 Sub: - Extension of Project completion period. Dear Sir, We have registered project in Maharashtra Real Estate Regulatory Authority ACT on date of 31/07/2017 and we have got registration number P52100002175, we have register project as VED - ASHRITHA PHASE I with below declaration : Wing A = P + 6 (36 Flat/apartments) Wing A = One Commercial Shop on Ground Floor & Future Potential of Project Wing A = P+9 (52 Flat/apartments) + One Commercial Shop on Ground Floor. Wing B = P + 9 (52 Flat/apartments) + One Commercial Shop on Ground Floor . As on date at site “Ved - Ashritha Pha

EXT52100016571Aug 2019 → Oct 2023

Reason as filed by the promoterWe have received Ved Aashritha Phase I (P52100002175) completion certificate on dated 17.02.2022, and project expiry date on 14.02.2021. So we need extension for upload form 4.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 9 Mar 2023

Documents filed32

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Ved-Ashritha Phase l.PDF11 Mar 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.PDF15 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF9 May 2023
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY.PDF22 Apr 2023
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.PDF14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.PDF11 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.PDF11 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.PDF11 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate.pdf9 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2021-2022.PDF22 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5- 2018-2019.PDF21 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 2019-2020.PDF21 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 2020-2021.PDF21 Feb 2023
CERSAI detailsFile: CERSAI Search Report.pdf13 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion certificate Ved Aashritha.pdf21 Feb 2022
PAN CardFile: Pan Card.PDF29 Nov 2021
OtherFile: Application for part completion certificate.PDF24 Nov 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect Certificate.PDF25 Sep 2021
Certificates of CA (Form 5)File: RERA FORM 5.PDF28 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.PDF24 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ved Aashritha Engineers Certificate.pdf26 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Ved Aashritha.pdf26 Jul 2017
Proforma of Allotment letterFile: Allotment Letter.pdf26 Jul 2017
Proforma of Allotment letterFile: FINAL RERA DRAFT AGREEMENT VED AASHRITHA.pdf26 Jul 2017
Layout approvalFile: Layout Ved-Ashritha.PDF25 Jul 2017
Building plan approvalFile: Floor Plan Ved-Ashritha.PDF25 Jul 2017
Copy of the legal title reportFile: Search And Title Report Ved Ashritha.PDF25 Jul 2017
Details of encumbrancesFile: Encumbrances for Phase 2.pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Ved-Ashritha.PDF25 Jul 2017
Building Plan Approval (IOD)File: Floor Plan Ved-Ashritha.PDF25 Jul 2017
Declaration in FORM BFile: Form B Ved- Aashritha Phase 1.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf25 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 50 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ved - Ashritha Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Katraj13,700+ in Pune

Builder: Yogvinda Promoters & Developers Pvt. Ltd.

Yogvinda Promoters & Developers Pvt. Ltd. has 2 registrations on MahaRERA, including Ashritha Phase I and Ved - Ashritha Phase I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Ved - Ashritha Phase I is delayed beyond 31 Oct 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ved - Ashritha Phase I?

The registered promoter entity is Yogvinda Promoters & Developers Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ved - Ashritha Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Ved - Ashritha Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ved - Ashritha Phase I?

The professionals named in the filing: Architect: Aniruddhe Tanaji Shinde; Architect: Milind Anil Joshi; Engineer: Ramchandra Krishnarao Randhave; Chartered Accountant: Kailash R Mundada. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ved - Ashritha Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ved - Ashritha Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ved - Ashritha Phase I to a free account