Home / Browse projects / Pune, Maharashtra / Vasukamal EXPRESS

Registration lapsed No litigation declared Commercial project

Vasukamal EXPRESS

By Dilip Ramanlal Kabra

RG-MH-16178 · RERA P52100025762 · Last updated on MahaRERA portal: 23 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

Vasukamal EXPRESS is a Commercial project by Dilip Ramanlal Kabra in Pune, Maharashtra, registered with MahaRERA as P52100025762 on 9 Jul 2020. Possession was promised by 16 Sep 2025 and is now 13 months past that date.

At a glance

Project

  • NameVasukamal EXPRESS
  • TypeCommercial
  • Location
    • Baner
    • 34/3
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • RERA no.P52100025762
  • ReraGenie IDRG-MH-16178

Builder

  • NameDilip Ramanlal Kabra
  • Entity typeIndividual

Key dates

13 months past promisethis monthRegisteredJul 2020PromisedSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Jul 2020
  • Promised completion16 Sep 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Matrix office SpaceNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Matrix office Space: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Open Space1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area914 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI764.0
Proposed, not sanctioned764 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchbaner Pune

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNitin Joshi
ArchitectSans Architect
EngineerRohit Potdar
Chartered AccountantANIL SHAH
PartnerRole in project
Dilip Ramanlal Kabra-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Mar 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Jan 2025

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Architect Form 4 Kailash Sir (1).pdf23 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Kailash sir oc.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: 5 Disclosure of sold_ booked inventory (5) (1).pdf22 Nov 2024
Copy of the legal title reportFile: Dilipkumar Kabara Search.pdf31 Mar 2024
Declaration about Commencement CertificateFile: Declaration format D kailash.pdf21 Mar 2024
Declaration in FORM BFile: form B kailash.pdf21 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA certificate form 2a (1)-5-6.pdf21 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QA certificate form 2a (1)-1-2.pdf21 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QA certificate form 2a (1)-3-4.pdf21 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of intrest kailash.pdf21 Mar 2024
Details of encumbrances concerned to FinanceFile: no legal encum kailash.pdf20 Mar 2024
Details of encumbrances concerned to FinanceFile: No financial encum kailash.pdf20 Mar 2024
Details of encumbrances concerned to LegalFile: no legal encum kailash.pdf20 Mar 2024
Details of encumbrances concerned to LegalFile: No financial encum kailash.pdf20 Mar 2024
Declaration about Commencement CertificateFile: Dec Cc kailash.pdf20 Mar 2024
Disclosure of sold/ booked inventoryFile: inventory 1.pdf20 Mar 2024
Disclosure of sold/ booked inventoryFile: inventory 2.pdf20 Mar 2024
Disclosure of sold/ booked inventoryFile: inventory 3.pdf20 Mar 2024
Disclosure of sold/ booked inventoryFile: inventory 4.pdf20 Mar 2024
Proforma of Agreement for saleFile: agreement for sale format kailash.pdf20 Mar 2024
Proforma of Allotment letterFile: allotment letter kailash.pdf20 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Dec Cc kailash.pdf20 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: matrix office spaces form 2 Q1.pdf19 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: matrix office spaces form 2 Q2.pdf19 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: matrix office spaces form 2 Q3.pdf19 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: matrix office spaces form 2 Till Date.pdf19 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: matrix office spaces form 2 Q3.pdf19 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects certificate QUARTER 1 (1).pdf18 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects certificate QUARTER 2 (1).pdf18 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects certificate QUARTER 3 (1).pdf18 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects certificate Designated Account (1).pdf18 Mar 2024
CERSAI detailsFile: CERSAI_Search_Report_200300883528_For_Asset_Based_Search_18_03_2024_16_38_16_221.pdf18 Mar 2024
Building plan approvalFile: 1 (8)_compressed.pdf14 Mar 2024
Building plan approvalFile: Plan new page 1_compressed.pdf14 Mar 2024
Building plan approvalFile: Plan New Page 2_compressed.pdf14 Mar 2024
Copy of the legal title reportFile: Search Report (8).pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 1 (8)_compressed.pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan new page 1_compressed.pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan New Page 2_compressed.pdf14 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Matrix CC 2019.pdf14 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Matrix CC 2021.pdf14 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Matrix CC 2023.pdf14 Mar 2024
Other - TechnicalFile: BANER-34- INDEX II.pdf14 Mar 2024
Disclosure of sold/ booked inventoryFile: Inventory Disclosure - Promoter Letterhead.pdf14 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: f2 f2 f2.pdf14 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Kailash Kabra 2021.pdf14 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Kailash Kabra 2122.pdf14 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Kailash Kabra 2223.pdf14 Dec 2023
Building plan approvalFile: matrix bp.pdf13 Mar 2020
Layout approvalFile: matrix bp.pdf13 Mar 2020
PAN CardFile: Dilip Sir PAN.pdf13 Mar 2020
Copy of the legal title reportFile: matrix bp.pdf13 Mar 2020
Details of encumbrancesFile: no encumbrance matrix.pdf13 Mar 2020
Copy of Layout Approval (in case of layout)File: matrix bp.pdf13 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: matrix bp.pdf13 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert Matrix.pdf13 Mar 2020
Declaration in FORM BFile: matrix bp.pdf13 Mar 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Matrix dfg.pdf13 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Matrix CA CErt.pdf13 Mar 2020
Proforma of Allotment letterFile: Matrix Allotment letter.pdf13 Mar 2020

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vasukamal EXPRESS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near 34/313,700+ in Pune

Builder: Dilip Ramanlal Kabra

Dilip Ramanlal Kabra has 1 registration on MahaRERA, including Vasukamal EXPRESS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Vasukamal EXPRESS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Vasukamal EXPRESS is delayed beyond 16 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vasukamal EXPRESS?

The registered promoter entity is Dilip Ramanlal Kabra, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vasukamal EXPRESS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vasukamal EXPRESS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vasukamal EXPRESS?

The professionals named in the filing: Architect: Nitin Joshi; Architect: Sans Architect; Engineer: Rohit Potdar; Chartered Accountant: ANIL SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vasukamal EXPRESS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vasukamal EXPRESS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vasukamal EXPRESS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.