Home / Browse projects / Pune, Maharashtra / VASTUREKHA TOWNSHIP BUILDING-A

Registration lapsed No litigation declared Residential / Group Housing project

VASTUREKHA TOWNSHIP BUILDING-A

By AAYUSH ASSOCIATES THROUGH PROPRIETOR KAPIL VILASRAO BARGE

RG-MH-21419 · RERA P52100029241 · Last updated on MahaRERA portal: 2 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 27 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 90%
0Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

VASTUREKHA TOWNSHIP BUILDING-A is a Residential / Group Housing project by AAYUSH ASSOCIATES THROUGH PROPRIETOR KAPIL VILASRAO BARGE in Pune, Maharashtra, registered with MahaRERA as P52100029241 on 10 May 2021. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 27 months from the original filing.

At a glance

Project

  • NameVASTUREKHA TOWNSHIP BUILDING-A
  • TypeResidential / Group Housing
  • Location
    • -
    • DADA PATIL NAGAR
    • Tandulwadi
    • Baramati
    • Pune
    • 413102
  • Pincode413102
  • RERA no.P52100029241
  • ReraGenie IDRG-MH-21419

Builder

  • NameAAYUSH ASSOCIATES THROUGH PROPRIETOR KAPIL VILASRAO BARGE
  • Entity typeIndividual

Key dates

10 months past promisethis monthRegisteredMay 2021First promiseSep 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 May 2021
  • Promised completion30 Dec 2025
  • Revised completionRevised to 30 Dec 2025 (originally 30 Sep 2023)
  • Buildings1 building record
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VASTUREKHA TOWNSHIP BUILDING-ANA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

VASTUREKHA TOWNSHIP BUILDING-A: 46% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered10

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,618 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
KISHOR VASANTRAO KALEMalegaon BkPune
PRAKASH BHANUDAS NALKOLMalegaon BkPune
SHRIMATI UJWALA MANSIGH SHINDEMalegaon BkPune
KIRAN DIGAMBAR KSHIRSAGARTandulwadiPune

Approvals and building plan

Permissible FSI1169.6
Proposed, not sanctioned1,170 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHIGAWAN ROAD , BARAMATI DIST PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectP R TALKUTE
EngineerKAPIL VIASRAO BARGE
Chartered AccountantABHAY B KULKARNI
PartnerRole in project
AAYUSH ASSOCIATES THROUGH PROPRIETOR KAPIL VILASRAO BARGE-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017654Sep 2023 → Sep 2024

Reason as filed by the promoterthe project is delayed due to Covid Pandemic and shortage of Material and Labour

EXT52100025155Sep 2023 → Dec 2025

Reason as filed by the promoteras some work has been pending and an Occupancy Certificate has not been issued by the Competant Authority as Promoter had applied for the same

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Signed Form 5 Aayush Associates FY 2023-24.pdf2 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A - converted.pdf29 Nov 2024
Declaration in FORM BFile: DECLARATION IN FORM B.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: DETAILS OF SOLD AND UNSOLD INVENTORY.pdf27 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE - converted.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf25 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf23 Nov 2024
Other - FinanceFile: LOAN SANCTION LETTER.pdf12 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2020- 21.pdf6 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021-22.pdf6 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-23.pdf6 Nov 2023
Declaration in FORM BFile: FORM B.pdf30 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf30 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 22-23.pdf30 Oct 2023
Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD INVENTORY.pdf26 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf26 Sep 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf7 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2020- 21.pdf7 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021-22.pdf7 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-23.pdf7 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNAXURE A.pdf7 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION ABOUT BANK DETAILS.pdf7 Sep 2023
Deviation Report with respect to Allotment letterFile: DEVIATION.pdf7 Sep 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION.pdf7 Sep 2023
Building plan approvalFile: Building Plan-Barge.pdf9 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan-Barge.pdf9 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement -Vasturekha.pdf8 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architech cerificate.pdf8 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginear_certificate.pdf8 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Barge-CA_Certificate.pdf8 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect_certificate-vasturekha.pdf11 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginear_certificate-vasturekha.pdf11 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C_A_certificate-Vasturekha.pdf11 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Barge-Bandhakam Parvangi.pdf3 May 2021
Layout approvalFile: Barge-Layout.pdf30 Apr 2021
Copy of the legal title reportFile: Barge-Search_New.pdf30 Apr 2021
Details of encumbrancesFile: Barge-Declaration_for_No_Encumbrances.pdf30 Apr 2021
Copy of Layout Approval (in case of layout)File: Barge-Layout.pdf30 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: Barge-N_A_Order_New.pdf30 Apr 2021
Declaration in FORM BFile: Barge-Form_B.pdf30 Apr 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Barge-Engineer_Certificate_New.pdf30 Apr 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Barge-C_A_Certificate_New.pdf30 Apr 2021
Proforma of Allotment letterFile: Barge-Declaration_for_Agreement_to_Sale.pdf30 Apr 2021
Building plan approvalFile: Barge-Building_Plan.pdf29 Apr 2021
PAN CardFile: Barge_-_Pan_Card.pdf29 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: Barge-Building_Plan.pdf29 Apr 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Barge-Architect_Certificate_Form_1.pdf29 Apr 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 27 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VASTUREKHA TOWNSHIP BUILDING-A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DADA PATIL NAGAR13,700+ in Pune

Builder: AAYUSH ASSOCIATES THROUGH PROPRIETOR KAPIL VILASRAO BARGE

AAYUSH ASSOCIATES THROUGH PROPRIETOR KAPIL VILASRAO BARGE has 1 registration on MahaRERA, including VASTUREKHA TOWNSHIP BUILDING-A. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that VASTUREKHA TOWNSHIP BUILDING-A shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VASTUREKHA TOWNSHIP BUILDING-A is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VASTUREKHA TOWNSHIP BUILDING-A?

The registered promoter entity is AAYUSH ASSOCIATES THROUGH PROPRIETOR KAPIL VILASRAO BARGE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VASTUREKHA TOWNSHIP BUILDING-A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VASTUREKHA TOWNSHIP BUILDING-A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VASTUREKHA TOWNSHIP BUILDING-A?

The professionals named in the filing: Architect: P R TALKUTE; Engineer: KAPIL VIASRAO BARGE; Chartered Accountant: ABHAY B KULKARNI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VASTUREKHA TOWNSHIP BUILDING-A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VASTUREKHA TOWNSHIP BUILDING-A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VASTUREKHA TOWNSHIP BUILDING-A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.