ReraGenieLog inGet a buyer report

Home / Browse projects / Washim, Maharashtra / VASANT PARK

Registered No litigation declared Residential / Group Housing project

VASANT PARK

By S S R DEVELOPERS

RG-MH-33601 · RERA P50200032642 · Last updated on MahaRERA portal: 10 Jan 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Washim registration emailed to you, free during the pilot beta.
Jan 2027Possession promisedno revision filed
0 of 44Construction stages doneacross 4 buildings; furthest along: Excavation, 75%
0Complaints at MahaRERAon this registration
Jump to the 17 documents Report an error

VASANT PARK is a Residential / Group Housing project by S S R DEVELOPERS in Washim, Maharashtra, registered with MahaRERA as P50200032642 on 17 Jan 2022. Possession is promised by 4 Jan 2027.

At a glance

Project

  • NameVASANT PARK
  • TypeResidential / Group Housing
  • Location
    • NEAR DATTA NAGAR
    • WASHIM-3
    • VASANT PARK
    • Plot No.33
    • SURVEY No 375/2
    • AKOLA HIGHWAY WASHIM
    • Washim (M Cl)
    • Washim
    • 444505
  • Pincode444505
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50200032642
  • ReraGenie IDRG-MH-33601

Builder

  • NameS S R DEVELOPERS
  • Entity typePartnership
  • PartnersSAWAIRAM SAKHARAM RATHOD, SANDHYA SANDESH RATHOD, PUSHPA SAWAIRAM RATHOD
  • Other registrations2 more →

Key dates

this monthRegisteredJan 2022PromisedJan 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Jan 2022
  • Promised completion4 Jan 2027
  • Revised completionNone
  • Buildings4 building records
  • Documents filed17 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROW HOUSESNA20000
APARTMENTNA50000
INDIVIDUAL BUANGLOWNA30000
TWIN BUNGALOWNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 10 Jan 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 75%.

ROW HOUSES7%
ActivityProgress
Excavation25%
Basement (if any)25%
Podiums (if any)0%
Plinth25%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
APARTMENT0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
INDIVIDUAL BUANGLOW11%
ActivityProgress
Excavation75%
Basement (if any)25%
Podiums (if any)0%
Plinth25%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TWIN BUNGALOW0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Jan 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed182

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots182
Closed/Covered53
Open Space129
BuildingClosed/CoveredOpen SpaceTotal
ROW HOUSES04848
APARTMENT534194
INDIVIDUAL BUANGLOW01616
TWIN BUNGALOW02424

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,574 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9431.71
Proposed, not sanctioned9,432 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPATNI CHOWK WASHIM

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMILIND BHAVSAR
EngineerPRADIP VISHWANATH RATHOD
Chartered AccountantADITYA MOHATA
PartnerRole in project
S S R DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 4 Jan 2027

Documents filed17

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Certificate.pdf10 Jan 2022
Building plan approvalFile: Sanction Plan.pdf8 Jan 2022
Building plan approvalFile: N A Order.pdf8 Jan 2022
Copy of the legal title reportFile: Title Report.pdf8 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan.pdf8 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: N A Order.pdf8 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: Commismence Certificate.pdf8 Jan 2022
Declaration about Commencement CertificateFile: Decleration Certificate.pdf8 Jan 2022
Declaration in FORM BFile: Form B_.pdf8 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Certificate of Architect.pdf8 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate.pdf8 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200227710045_For_Asset_Based_Search_08_01_2022_13_05_46_769.pdf8 Jan 2022
Proforma of Allotment letterFile: Draft Agreement.pdf8 Jan 2022
Layout approvalFile: Layout Plan.pdf7 Jan 2022
PAN CardFile: PAN Card.pdf7 Jan 2022
Details of encumbrancesFile: Enchubrance.pdf7 Jan 2022
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf7 Jan 2022

How this compares with Washim

0%of Washim projects moved their completion datethis one has not
42%of Washim registrations have lapsed or been cancelledthis one is on the register

Computed across the 28 Washim projects on ReraGenie, from their own filings.

Keep VASANT PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VASANT PARK, Plot No.33, SURVEY No 375/2, AKOLA HIGHWAY WASHIM28 in Washim

Builder: S S R DEVELOPERS

S S R DEVELOPERS has 3 registrations on MahaRERA, including VASANT PARK and UNIQUE PARK 4. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Washim district page.

Frequently asked questions

What are my rights if VASANT PARK is delayed beyond 4 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VASANT PARK?

The registered promoter entity is S S R DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VASANT PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VASANT PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VASANT PARK?

The professionals named in the filing: Architect: MILIND BHAVSAR; Engineer: PRADIP VISHWANATH RATHOD; Chartered Accountant: ADITYA MOHATA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VASANT PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VASANT PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VASANT PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.