Home / Browse projects / Washim, Maharashtra / VYANKATESH HOMES
VYANKATESH HOMES
RG-MH-02577 · RERA P50200029149 · Last updated on MahaRERA portal: 5 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 17 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Washim registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VYANKATESH HOMES is a Residential / Group Housing project by VYANKATESH HOMES in Washim, Maharashtra, registered with MahaRERA as P50200029149 on 29 Apr 2021. Possession was promised by 31 May 2025 and is now 17 months past that date. 122 of the 249 units on this registration are recorded sold or booked, and 52 of 99 construction stages are filed complete.
At a glance
Project
- NameVYANKATESH HOMES
- TypeResidential / Group Housing
- Location
- Washim-3 S N.392/1
- Kondala Road Washim
- Washim (M Cl)
- Washim
- 444505
- Pincode444505
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50200029149
- ReraGenie IDRG-MH-02577
Builder
- NameVYANKATESH HOMES
- Entity typePartnership
- PartnersSANGEETA GIRISH LAHOTI, SUBHASH DADARAO SARNAIK, ANIL SUDHAKAR KULKARNI, SHAILESH KIRANKUMAR SOMANI
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 Apr 2021
- Promised completion31 May 2025
- Revised completionNone
- Buildings9 building records
- Documents filed22 files
Current status
Figures as on 5 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VYANKATESH WING A-1 | NA | 6 | 6 | 44 | 0 | 44 |
| VYANKATESH WING A-2 | NA | 5 | 5 | 36 | 0 | 36 |
| VYANKATESH WING B-1 | NA | 6 | 6 | 44 | 0 | 44 |
| VYANKATESH WING B-2 | NA | 5 | 5 | 36 | 0 | 36 |
| VYANAKTESH WING B-3 | NA | 5 | 5 | 36 | 0 | 36 |
| VYANKATESH WING B-4 | NA | 5 | 5 | 36 | 0 | 36 |
| VYANKATESH ROW HOUSES | NA | 2 | 2 | 4 | 0 | 4 |
| VYANKATESH SHOPS UNIT-1 | NA | 1 | 1 | 0 | 7 | 7 |
| VYANKATESH SHOPS UNIT-2 | NA | 1 | 1 | 0 | 6 | 6 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building9
As on 5 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
52 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Internal walls, at 90%.
VYANKATESH WING A-170%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
VYANKATESH WING A-282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
VYANKATESH WING B-111%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 25% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
VYANKATESH WING B-282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
VYANAKTESH WING B-382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
VYANKATESH WING B-482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
VYANKATESH ROW HOUSES82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
VYANKATESH SHOPS UNIT-10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
VYANKATESH SHOPS UNIT-20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 5 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 70% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 70% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed378
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| VYANKATESH WING A-1 | 30 | 40 | 70 |
| VYANKATESH WING A-2 | 27 | 37 | 64 |
| VYANKATESH WING B-1 | 18 | 52 | 70 |
| VYANKATESH WING B-2 | 0 | 38 | 38 |
| VYANAKTESH WING B-3 | 16 | 38 | 54 |
| VYANKATESH WING B-4 | 14 | 54 | 68 |
| VYANKATESH ROW HOUSES | 0 | 6 | 6 |
| VYANKATESH SHOPS UNIT-1 | 0 | 4 | 4 |
| VYANKATESH SHOPS UNIT-2 | 0 | 4 | 4 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| VYANKATESH WING B-1 | NA | Rs 5.10 cr | Rs 45.37 lakh |
| VYANKATESH WING A-1 | NA | Rs 4.61 cr | Rs 4.38 cr |
| VYANKATESH WING A-2 | NA | Rs 3.45 cr | Rs 3.45 cr |
| VYANKATESH WING B-2 | NA | Rs 2.86 cr | Rs 2.86 cr |
| VYANAKTESH WING B-3 | NA | Rs 2.86 cr | Rs 2.86 cr |
| VYANKATESH WING B-4 | NA | Rs 2.86 cr | Rs 2.86 cr |
| - | NA | Rs 2.49 cr | Rs 1.99 cr |
| VYANKATESH ROW HOUSES | NA | Rs 51.98 lakh | Rs 51.98 lakh |
| VYANKATESH SHOPS UNIT-1 | NA | Rs 26.98 lakh | - |
| VYANKATESH SHOPS UNIT-2 | NA | Rs 23.13 lakh | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MANDAR KELKAR |
| Engineer | GAJANAN RAMBHAU WADEKAR |
| Chartered Accountant | ANAND DODIYA |
| Chartered Accountant | TRUPTI KAPIL RATHI |
| Partner | Role in project |
|---|---|
| VYANKATESH HOMES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Apr 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Apr 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Apr 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed22
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Form 2A.pdf | 5 Dec 2025 |
| Withdrawal Update Form 1File: Form 1_Final.pdf | 28 Nov 2025 |
| Withdrawal Update Form 2File: Form 2_Final.pdf | 28 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 vyankatesh.pdf | 28 Nov 2025 |
| Form 5 (FY 2024-2025)File: from 5 24-25001.pdf | 28 Nov 2025 |
| Copy of the legal title reportFile: Titel Report.pdf | 27 Apr 2021 |
| Copy of the legal title reportFile: Titel Report.pdf | 23 Apr 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Certificate of Architect.pdf | 23 Apr 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 23 Apr 2021 |
| Layout approvalFile: Layout Plan.pdf | 21 Apr 2021 |
| Building plan approvalFile: Sanction Plan.pdf | 21 Apr 2021 |
| PAN CardFile: PAN Card.pdf | 21 Apr 2021 |
| PAN CardFile: PAN Card.pdf | 21 Apr 2021 |
| PAN CardFile: PAN Card.pdf | 21 Apr 2021 |
| Details of encumbrancesFile: Enchubrance.pdf | 21 Apr 2021 |
| Copy of Layout Approval (in case of layout)File: Layout Plan.pdf | 21 Apr 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan.pdf | 21 Apr 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencment Certificate.pdf | 21 Apr 2021 |
| Declaration in FORM BFile: Form B.pdf | 21 Apr 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Certificate of Engineer.pdf | 21 Apr 2021 |
| Proforma of Allotment letterFile: Draft Agreement.pdf | 21 Apr 2021 |
| OtherFile: Certificate of Registration.pdf | 21 Apr 2021 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| VYANKAONTESH HOMES | PLOT No 01 & 02 VYANKATESH HOMES SURVEY No 39 GONDESHWAR RISOD ROAD WASHIM | 95 | Completed | May 2022 | Nov 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Washim
Computed across the 28 Washim projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 22 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VYANKATESH HOMES on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kondala Road Washim28 in Washim
Badlani Park
Purankumar Lalchand Badlani
Varco City 2 Washim
VARCO INFRASTRUCTURE INDIA Pvt Ltd
Washim Trade Centre
Sharangdhar Developers
WAHEGURU LAND DEVELOPERS
Waheguru Land Deve;opers
DM Majestique
DM DEVELOPERS
AMRUTVEL
Jogee Associates
See every Washim project, with the district possession charts
Builder: VYANKATESH HOMES
VYANKATESH HOMES has 1 registration on MahaRERA, including VYANKATESH HOMES. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Washim district page.
Frequently asked questions
What does it mean that VYANKATESH HOMES shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VYANKATESH HOMES is delayed beyond 31 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VYANKATESH HOMES?
The registered promoter entity is VYANKATESH HOMES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VYANKATESH HOMES?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VYANKATESH HOMES?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VYANKATESH HOMES?
The professionals named in the filing: Architect: MANDAR KELKAR; Engineer: GAJANAN RAMBHAU WADEKAR; Chartered Accountant: ANAND DODIYA; Chartered Accountant: TRUPTI KAPIL RATHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VYANKATESH HOMES?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback