ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / Varsha Nagari

Registered No litigation declared Plotted project

Varsha Nagari

By Angad Milaji kale

RG-MH-89815 · RERA PP1190002600942 · Last updated on MahaRERA portal: 5 May 2026

Source: official MahaRERA filing

Red flags

  • Allotment letter deviates from the model form

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
May 2031Possession promisedno revision filed
53 of 53Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 3 documents Report an error

Varsha Nagari is a Plotted project by Angad Milaji kale in Nagpur, Maharashtra, registered with MahaRERA as PP1190002600942 on 25 Jun 2026. Possession is promised by 31 May 2031. 0 of the 53 units on this registration are recorded sold or booked.

At a glance

Project

  • NameVarsha Nagari
  • TypePlotted
  • Location
    • Khasra/ Survey No 87/1
    • Mouza Raipur
    • Raipur
    • Hingna
    • Nagpur
    • 441110
  • Pincode441110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PP1190002600942
  • ReraGenie IDRG-MH-89815

Builder

  • NameAngad Milaji kale
  • Entity typeIndividual

Key dates

this monthRegisteredJun 2026PromisedMay 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Jun 2026
  • Promised completion31 May 2031
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed3 files

Current status

0%0 of 53 units booked

Figures as on 5 May 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNo0%
Street LightingNo0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNo0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNo0%
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area20,500 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 May 2026
LandownerVillageDistrict
Varsha Purushottam KaduNagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNagpur Metropolitan Region Development Authority

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDISTNAGPUR MAHARASHTRA 440012

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDhawal Subhashrao Harshe
EngineerDhawal Subhashrao Harshe
Chartered AccountantMJM Associates
PartnerRole in project
Angad Milaji kale-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Apr 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Apr 2026
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 May 2031

Documents filed3

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration and undertaking (Annexure A)File: No Double Registration..pdf5 May 2026
Layout approvalFile: Map.pdf8 Apr 2026
Building plan approvalFile: Map.pdf8 Apr 2026

How this compares with Nagpur

0%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Varsha Nagari on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mouza Raipur2,800+ in Nagpur

2 kmVarsha NagariCompleted 18Lapsed / revoked 9Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 45 registered projects within 2 km.

Builder: Angad Milaji kale

Angad Milaji kale has 1 registration on MahaRERA, including Varsha Nagari. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Varsha Nagari is delayed beyond 31 May 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Varsha Nagari?

The registered promoter entity is Angad Milaji kale, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Varsha Nagari?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Varsha Nagari?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Varsha Nagari?

The professionals named in the filing: Architect: Dhawal Subhashrao Harshe; Engineer: Dhawal Subhashrao Harshe; Chartered Accountant: MJM Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Varsha Nagari?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Varsha Nagari. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Varsha Nagari to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.