Home / Browse projects / Pune, Maharashtra / VARADH RESIDENCY - PHASE 2
VARADH RESIDENCY - PHASE 2
RG-MH-39434 · RERA P52100016872 · Last updated on MahaRERA portal: 19 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 45 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VARADH RESIDENCY - PHASE 2 is a Residential / Group Housing project by RADIANTS PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100016872 on 20 Jun 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 45 months from the original filing.
At a glance
Project
- NameVARADH RESIDENCY - PHASE 2
- TypeResidential / Group Housing
- Location
- VILLAGE RAJGURUNAGAR
- MALIMALA
- Rajgurunagar (CT)
- Khed
- Pune
- 410505
- Pincode410505
- RERA no.P52100016872
- ReraGenie IDRG-MH-39434
Builder
- NameRADIANTS PROPERTIES
- Entity typePartnership
- PartnersDEEPALI PRAVIN PUJARI, SANJAY BABANRAO RAUT, DHARMENDRA EKNATH BHUJBAL, SHANTA RATNAKAR PANDHE, SUCHITA GANESH KHEDKAR, TUKARAM MALHARI NARAWADE
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on20 Jun 2018
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2023)
- Buildings3 building records
- Documents filed75 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING B | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING C | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING D | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 19 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 0%.
BUILDING B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 19 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 80% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed19
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BUILDING B | 8 | 8 |
| BUILDING C | 8 | 8 |
| BUILDING D | 3 | 3 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MR GULAB GENU DEVHARKAR | Rajgurunagar (CT) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAHUL R JADHAVE |
| Engineer | SAURABH SHRISATH |
| Partner | Role in project |
|---|---|
| RADIANTS PROPERTIES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe reason for extension of the date of completion of the project is primarily based on unavailability of the standard material which is to be used in the construction of the said project & non-availability/ delay of finance, due to COVID-19 lockdown.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Jun 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Jul 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Jun 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Jun 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 13 Jul 2021
Documents filed75
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Form 1 March 31 2024.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Form 1 June 30 2024.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Form 1 June 30 2024.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 Form 1 sept 30 2024.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 Form 1 Dec 31 2024.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 Form1 march 31 2023.pdf | 19 Feb 2025 |
| Certificates of CA (Form 3)File: 1 Form 3 31 03 2023.pdf | 19 Feb 2025 |
| Certificates of CA (Form 3)File: 2 Form 3 31 03 2024.pdf | 19 Feb 2025 |
| Certificates of CA (Form 3)File: 3 Form 3 Q1 30 06 2024.pdf | 19 Feb 2025 |
| Certificates of CA (Form 3)File: 4 Form 3 Q2 30 09 2024.pdf | 19 Feb 2025 |
| Certificates of CA (Form 3)File: 5 Form 3 Q3 31 12 2024.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Enginner certi 30 sep 2024.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Engineee Cert 31 dec 2024.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Engineee Cert 30 jun 2024.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Engineee Certi March 2024.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 engineer cert march 2023.pdf | 19 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 2 sold and unsold 31 03 2024.pdf | 19 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 3 sold unsold 30 06 2024.pdf | 19 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 4 sold unsold 30 09 2024.pdf | 19 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 5 sold unsold 31 12 2024.pdf | 19 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 engineer cert march 2023.pdf | 19 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022 23.pdf | 19 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2 Form 2A 31 03 2024.pdf | 19 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3 Form 2A 30 06 2024.pdf | 19 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3 Form 2A 30 06 2024.pdf | 19 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 4 Form 2A 30 09 2024.pdf | 19 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 5 Form 2A 31 12 2024.pdf | 19 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 2023 24.pdf | 19 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 2022_signed__compressed.pdf | 12 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 FY 2018-19_compressed.pdf | 10 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 2019-20_compressed.pdf | 10 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2020-21_compressed.pdf | 10 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_2018-19_compressed.pdf | 7 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_ FY 2019-20_compressed.pdf | 7 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A 2018-19_compressed.pdf | 7 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A FY 2019-20_compressed.pdf | 7 Apr 2023 |
| Certificates of CA (Form 3)File: RERA FORM 3 SIGNED_FY 2018-19_compressed.pdf | 5 Apr 2023 |
| Certificates of CA (Form 3)File: RERA FORM 3 SIGNED_FY 2019-20_compressed.pdf | 5 Apr 2023 |
| Certificates of CA (Form 3)File: RERA FORM 3 SIGNED_FY 2020-21_compressed.pdf | 5 Apr 2023 |
| Certificates of CA (Form 3)File: RERA FORM 3 SIGNED_FY 2021-22_compressed.pdf | 5 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: P52100016872_FileName_0.pdf | 19 Jan 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200228388603_For_Asset_Based_Search_19_01_2022_14_55_18_188.pdf | 19 Jan 2022 |
| Details of encumbrancesFile: Non Encombrance Varad Residency.pdf | 15 Dec 2021 |
| Declaration about Commencement CertificateFile: Declaratio CC Varad Residency.pdf | 15 Dec 2021 |
| CERSAI detailsFile: Non Encombrance Varad Residency.pdf | 15 Dec 2021 |
| Layout approvalFile: rera phase 2(1).pdf | 13 Jul 2021 |
| Layout approvalFile: Rera phase 2 (2).pdf | 13 Jul 2021 |
| Layout approvalFile: Rera phase 2 (3).pdf | 13 Jul 2021 |
| Layout approvalFile: Rera phase 2 (4).pdf | 13 Jul 2021 |
| Layout approvalFile: Rera phase 2 (5).pdf | 13 Jul 2021 |
| Copy of Layout Approval (in case of layout)File: rera phase 2(1).pdf | 13 Jul 2021 |
| Copy of Layout Approval (in case of layout)File: Rera phase 2 (2).pdf | 13 Jul 2021 |
| Copy of Layout Approval (in case of layout)File: Rera phase 2 (3).pdf | 13 Jul 2021 |
| Copy of Layout Approval (in case of layout)File: Rera phase 2 (4).pdf | 13 Jul 2021 |
| Copy of Layout Approval (in case of layout)File: Rera phase 2 (5).pdf | 13 Jul 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Rera phase 2.pdf | 13 Jul 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC-phase 1.pdf | 4 Jul 2020 |
| Certificates of CA (Form 5)File: Form 5-Phase 2-compressed.pdf | 8 Jan 2019 |
| Building plan approvalFile: 03-compressed.pdf | 11 Jun 2018 |
| Building plan approvalFile: 04-compressed.pdf | 11 Jun 2018 |
| Building plan approvalFile: 05-compressed.pdf | 11 Jun 2018 |
| Layout approvalFile: 01-compressed.pdf | 11 Jun 2018 |
| PAN CardFile: radiant's properties pan.pdf | 11 Jun 2018 |
| Copy of the legal title reportFile: search and title report 2014.pdf | 11 Jun 2018 |
| Details of encumbrancesFile: NO ENCUMBERANCE CERTIFICATE.pdf | 11 Jun 2018 |
| Copy of Layout Approval (in case of layout)File: 01-compressed.pdf | 11 Jun 2018 |
| Building Plan Approval (IOD)File: 03-compressed.pdf | 11 Jun 2018 |
| Building Plan Approval (IOD)File: 04-compressed.pdf | 11 Jun 2018 |
| Building Plan Approval (IOD)File: 05-compressed.pdf | 11 Jun 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 11 Jun 2018 |
| Declaration in FORM BFile: declaration narawade phase 2.pdf | 11 Jun 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architects certificate phase 2-compressed.pdf | 11 Jun 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate phase 2.pdf | 11 Jun 2018 |
| Certificates of CA (Form 3)File: FORM 3-RADIANT PROP PHASE II.pdf | 11 Jun 2018 |
| Proforma of Allotment letterFile: Khed - Site Flat Agreement Draft 2018.pdf | 11 Jun 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 75 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep VARADH RESIDENCY - PHASE 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MALIMALA13,700+ in Pune
First City
Xrbia Developers Ltd
SURAJ EKYUM
SURAJ INFRA
Shankeshwar World
Nitin Chhaganlal Jain
Escape City Ph 1
Gajendra Patil , Pramod Patil , Vinod Pati
YESAI PARK
SIDDHIVINAYAK DEVELOPERS
Escape City Ph 2
Gajendra Patil , Pramod Patil , Vinod Pati
Builder: RADIANTS PROPERTIES
RADIANTS PROPERTIES has 2 registrations on MahaRERA, including VARADH RESIDENCY - PHASE 1 and VARADH RESIDENCY - PHASE 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if VARADH RESIDENCY - PHASE 2 is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VARADH RESIDENCY - PHASE 2?
The registered promoter entity is RADIANTS PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VARADH RESIDENCY - PHASE 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VARADH RESIDENCY - PHASE 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VARADH RESIDENCY - PHASE 2?
The professionals named in the filing: Architect: RAHUL R JADHAVE; Engineer: SAURABH SHRISATH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VARADH RESIDENCY - PHASE 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback