Home / Browse projects / Pune, Maharashtra / Varad Lake City
Varad Lake City
RG-MH-54474 · RERA P52100016913 · Last updated on MahaRERA portal: 31 Oct 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 43 months past the filed date
- 4 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Varad Lake City is a Residential / Group Housing project by VARAD SHELTERS PVT.LTD. in Pune, Maharashtra, registered with MahaRERA as P52100016913 on 22 Jun 2018. Possession was promised by 30 Mar 2023 and is now 43 months past that date. The completion date has moved by 12 months from the original filing. 4 complaints are on record with the regulator.
At a glance
Project
- NameVarad Lake City
- TypeResidential / Group Housing
- Location
- OFF MUMBAI BENGALURU HIGHWAY
- Ambegaon KH
- Haveli
- Pune
- 411046
- Pincode411046
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100016913
- ReraGenie IDRG-MH-54474
Builder
- NameVARAD SHELTERS PVT.LTD.
- Entity typeCompany
- DirectorsNITIN SHANKARRAO SHINDE, PRAKASH MARUTRAO PANSARE, ALKA PRAKASH PANSARE, MANGESH BALKRISHNA DEOKAR
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Jun 2018
- Promised completion30 Mar 2023
- Revised completionRevised to 30 Mar 2023 (originally 30 Mar 2022)
- Buildings2 building records
- Documents filed62 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RUKHMINI B | NA | 16 | 0 | 0 | 0 | 0 |
| RUKHMINI A | NA | 14 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 31 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 90%.
RUKHMINI B58%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 70% |
| Plinth | 90% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
RUKHMINI A56%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 70% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 60% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 31 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 30% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 30% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 10% |
| Open Parking | Yes | 0% |
Parking filed174
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| RUKHMINI B | 95 | 95 |
| RUKHMINI A | 79 | 79 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| VARAD SHELTERS PVT LTD | Vitthalvadi | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Walhekar and Associates |
| Engineer | G A Bhilare |
| Partner | Role in project |
|---|---|
| VARAD SHELTERS PVT.LTD. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. The Aviation NOC by Ministry of Defence was made compulsory. This put us on hold for construction before lockdown. 2. The lockdown has made big issue about scarcity of labor and material in time. The lock down has also impacted our sales and required cash flow. This has delayed all our plan by one year. 3. The Amenity Handover Procedure was delayed due to lockdown to load the balance FSI.
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000279765 | Aniket Mohan Nandre | M/s. Varad Shelters PVT. LTd | 17/12/2023 |
| CC005000000320629 | MANDAR ASHOK DAMALE | VARAD SHELTERS PVT.LTD | 17/03/2024 |
| CC005000000320617 | AJIT JANARDAN GURAV | VARAD SHELTERS PVT LTD. | 17/03/2024 |
| CC005000000371035 | Priti Ashok Lagad | M/s Varad Shelters Pvt. Ltd.Through its Director Mr. Nitin S. Shinde | 29/05/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Jun 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Jun 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Jun 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 31 Oct 2023
Documents filed62
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Details of encumbrances concerned to FinanceFile: Encumbrances Certificate Oct 2023.pdf | 31 Oct 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrances Certificate Oct 2023.pdf | 31 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Engineers Certificate For Quality Assurance 2023.pdf | 31 Oct 2023 |
| Proforma of Agreement for saleFile: Model Agreement to sale-RERA.pdf | 31 Oct 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Mar 2023.pdf | 31 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Form 2 Engineers certificate Sep 2022.pdf | 22 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Form 2 Engineers Certificate March 2023.pdf | 22 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Engineers Certificate For Quality Assurance 2022.pdf | 22 May 2023 |
| Certificates of CA (Form 3)File: Form -3 March 2023 Varad.pdf | 22 May 2023 |
| Certificates of CA (Form 3)File: Form-3 Varad March 2023.pdf | 22 May 2023 |
| Certificates of CA (Form 3)File: RERA form 3 Sep 2022.pdf | 9 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 March 2022.pdf | 26 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form 2 March 2022.pdf | 26 Apr 2022 |
| Certificates of CA (Form 3)File: RERA Form 3 March 2022.pdf | 26 Apr 2022 |
| Certificates of CA (Form 3)File: Form 3 Varad Lake City 30 Sept 2021- Upload.pdf | 17 Dec 2021 |
| Declaration about Commencement CertificateFile: MAHARERA Form B Declaration by Promoter Oct 2021.pdf | 10 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Units Oct 2021.pdf | 10 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: RERA Form 5 2018.pdf | 10 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Engineers Certificate For Quality Assurance 2020.pdf | 1 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Engineers Certificate For Quality Assurance 2021.pdf | 1 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: REAR Form 5 2019.pdf | 1 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Form 5 2020.pdf | 1 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Form 5 2021.pdf | 1 Nov 2021 |
| OtherFile: Format D Declaration.pdf | 1 Nov 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Form 1 Architect Certificate 30 06 2021_.pdf | 14 Sep 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Form 2 Engineers Certificate 30 June 2021-.pdf | 14 Sep 2021 |
| Certificates of CA (Form 3)File: RERA FORM 3 CA CERTIFICATE 30 JUNE 2021.pdf | 14 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Form 1 Architect Certificate.pdf | 28 Jan 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera form 2 ENGINEER'S CERTIFICATE 31 Dec 2020.pdf | 28 Jan 2021 |
| Certificates of CA (Form 3)File: Rear Form - 3 CA Certificate.pdf | 28 Jan 2021 |
| Certificates of CA (Form 3)File: MAHA RERA FORM 3- CA Certificate 31082020 uploaded.pdf | 25 Sep 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1 June 2019 Uploaded.pdf | 22 Sep 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MAHA RERA FORM 1 Arch Certf Aug 2020.pdf | 22 Sep 2020 |
| Details of Restarting of Construction work post lockdownFile: Post Loackdown Construction Work 30082020.pdf | 22 Sep 2020 |
| Details of encumbrancesFile: Encumberance Declaration SBI March 2019.pdf | 18 Sep 2020 |
| Certificates of CA (Form 3)File: FORM3 31122018.pdf | 14 Mar 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1 Arch Certf 31122018.pdf | 12 Mar 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 ENG CERTF 31122018.pdf | 12 Mar 2019 |
| Layout approvalFile: Copy of Layout Approval.pdf | 12 Jun 2018 |
| Copy of the legal title reportFile: Legal_Title_Search.pdf | 12 Jun 2018 |
| Copy of the legal title reportFile: Legal_Title_Search_Report_1.pdf | 12 Jun 2018 |
| Details of encumbrancesFile: Encum Declaration.pdf | 12 Jun 2018 |
| Copy of Layout Approval (in case of layout)File: Copy of Layout Approval.pdf | 12 Jun 2018 |
| Declaration in FORM BFile: RERA-Form B.pdf | 12 Jun 2018 |
| Proforma of Allotment letterFile: Model Agreement to sale-RERA.pdf | 12 Jun 2018 |
| Building plan approvalFile: 01-07-R.pdf | 6 Jun 2018 |
| Building plan approvalFile: 02 of 07.pdf | 6 Jun 2018 |
| Building plan approvalFile: 03 of 07.pdf | 6 Jun 2018 |
| Building plan approvalFile: 04 of 07.pdf | 6 Jun 2018 |
| Building plan approvalFile: 05 of 07.pdf | 6 Jun 2018 |
| Building plan approvalFile: 06 of 07.pdf | 6 Jun 2018 |
| Building plan approvalFile: 07 of 07.pdf | 6 Jun 2018 |
| Building Plan Approval (IOD)File: 01-07-R.pdf | 6 Jun 2018 |
| Building Plan Approval (IOD)File: 02 of 07.pdf | 6 Jun 2018 |
| Building Plan Approval (IOD)File: 03 of 07.pdf | 6 Jun 2018 |
| Building Plan Approval (IOD)File: 04 of 07.pdf | 6 Jun 2018 |
| Building Plan Approval (IOD)File: 05 of 07.pdf | 6 Jun 2018 |
| Building Plan Approval (IOD)File: 06 of 07.pdf | 6 Jun 2018 |
| Building Plan Approval (IOD)File: 07 of 07.pdf | 6 Jun 2018 |
| Certificates of CA (Form 3)File: FORM3.pdf | 6 Jun 2018 |
| PAN CardFile: PAN CARD VSPL.pdf | 27 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates pmrda.pdf | 27 Mar 2018 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Varad Lake City - RUKHMINI C | Ambegaon khurd | 42 | Completed | Dec 2013 | Oct 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 62 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Varad Lake City on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ambegaon KH13,700+ in Pune
Filed coordinates, straight-line distance. 433 registered projects within 2 km.
Sai Nagari Phase I
Saikedareshwar Developers LLP
SAI NAGARI Phase V
Saikedareshwar Developers LLP
Sai Nagari Phase II
Saikedareshwar Developers LLP
Sai Nagari Phase IV
Saikedareshwar Developers LLP
Sai Nagari Phase III
Saikedareshwar Developers LLP
Bella Casa - Phase 1
Kakkad Infra LLP
Builder: VARAD SHELTERS PVT.LTD.
VARAD SHELTERS PVT.LTD. has 1 registration on MahaRERA, including Varad Lake City. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Varad Lake City shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Varad Lake City is delayed beyond 30 Mar 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Varad Lake City?
The registered promoter entity is VARAD SHELTERS PVT.LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Varad Lake City?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Varad Lake City?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Varad Lake City?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Varad Lake City?
The professionals named in the filing: Architect: Walhekar and Associates; Engineer: G A Bhilare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Varad Lake City?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.