Home / Browse projects / Pune, Maharashtra / Varad Lake City

Registration lapsed No litigation declared Residential / Group Housing project

Varad Lake City

By VARAD SHELTERS PVT.LTD.

RG-MH-54474 · RERA P52100016913 · Last updated on MahaRERA portal: 31 Oct 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 43 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2023Possession promised43 months past this date
5 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 90%
4Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

Varad Lake City is a Residential / Group Housing project by VARAD SHELTERS PVT.LTD. in Pune, Maharashtra, registered with MahaRERA as P52100016913 on 22 Jun 2018. Possession was promised by 30 Mar 2023 and is now 43 months past that date. The completion date has moved by 12 months from the original filing. 4 complaints are on record with the regulator.

At a glance

Project

  • NameVarad Lake City
  • TypeResidential / Group Housing
  • Location
    • OFF MUMBAI BENGALURU HIGHWAY
    • Ambegaon KH
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100016913
  • ReraGenie IDRG-MH-54474

Builder

  • NameVARAD SHELTERS PVT.LTD.
  • Entity typeCompany
  • DirectorsNITIN SHANKARRAO SHINDE, PRAKASH MARUTRAO PANSARE, ALKA PRAKASH PANSARE, MANGESH BALKRISHNA DEOKAR
  • Declared earlier projects1 →

Key dates

43 months past promisethis monthRegisteredJun 2018First promiseMar 2022Revised toMar 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Jun 2018
  • Promised completion30 Mar 2023
  • Revised completionRevised to 30 Mar 2023 (originally 30 Mar 2022)
  • Buildings2 building records
  • Documents filed62 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RUKHMINI BNA160000
RUKHMINI ANA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 31 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 90%.

RUKHMINI B58%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)70%
Plinth90%
Stilt Floor0%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RUKHMINI A56%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)70%
Plinth100%
Stilt Floor100%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes30%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes10%
Open ParkingYes0%

Parking filed174

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots174
Open Space174
BuildingOpen SpaceTotal
RUKHMINI B9595
RUKHMINI A7979

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,116 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
VARAD SHELTERS PVT LTDVitthalvadiPune

Approvals and building plan

Permissible FSI7714.0
Proposed, not sanctioned5,439 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShirole Bhavan, PMT Building, J M Road, PUNE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectWalhekar and Associates
EngineerG A Bhilare
PartnerRole in project
VARAD SHELTERS PVT.LTD.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100010790Mar 2022 → Mar 2023

Reason as filed by the promoter1. The Aviation NOC by Ministry of Defence was made compulsory. This put us on hold for construction before lockdown. 2. The lockdown has made big issue about scarcity of labor and material in time. The lock down has also impacted our sales and required cash flow. This has delayed all our plan by one year. 3. The Amenity Handover Procedure was delayed due to lockdown to load the balance FSI.

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC005000000279765Aniket Mohan NandreM/s. Varad Shelters PVT. LTd17/12/2023
CC005000000320629MANDAR ASHOK DAMALEVARAD SHELTERS PVT.LTD17/03/2024
CC005000000320617AJIT JANARDAN GURAVVARAD SHELTERS PVT LTD.17/03/2024
CC005000000371035Priti Ashok LagadM/s Varad Shelters Pvt. Ltd.Through its Director Mr. Nitin S. Shinde29/05/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jun 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jun 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 31 Oct 2023

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrances concerned to FinanceFile: Encumbrances Certificate Oct 2023.pdf31 Oct 2023
Details of encumbrances concerned to LegalFile: Encumbrances Certificate Oct 2023.pdf31 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Engineers Certificate For Quality Assurance 2023.pdf31 Oct 2023
Proforma of Agreement for saleFile: Model Agreement to sale-RERA.pdf31 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Mar 2023.pdf31 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Form 2 Engineers certificate Sep 2022.pdf22 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Form 2 Engineers Certificate March 2023.pdf22 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Engineers Certificate For Quality Assurance 2022.pdf22 May 2023
Certificates of CA (Form 3)File: Form -3 March 2023 Varad.pdf22 May 2023
Certificates of CA (Form 3)File: Form-3 Varad March 2023.pdf22 May 2023
Certificates of CA (Form 3)File: RERA form 3 Sep 2022.pdf9 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 March 2022.pdf26 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form 2 March 2022.pdf26 Apr 2022
Certificates of CA (Form 3)File: RERA Form 3 March 2022.pdf26 Apr 2022
Certificates of CA (Form 3)File: Form 3 Varad Lake City 30 Sept 2021- Upload.pdf17 Dec 2021
Declaration about Commencement CertificateFile: MAHARERA Form B Declaration by Promoter Oct 2021.pdf10 Nov 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Units Oct 2021.pdf10 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: RERA Form 5 2018.pdf10 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Engineers Certificate For Quality Assurance 2020.pdf1 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Engineers Certificate For Quality Assurance 2021.pdf1 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: REAR Form 5 2019.pdf1 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Form 5 2020.pdf1 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Form 5 2021.pdf1 Nov 2021
OtherFile: Format D Declaration.pdf1 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Form 1 Architect Certificate 30 06 2021_.pdf14 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Form 2 Engineers Certificate 30 June 2021-.pdf14 Sep 2021
Certificates of CA (Form 3)File: RERA FORM 3 CA CERTIFICATE 30 JUNE 2021.pdf14 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Form 1 Architect Certificate.pdf28 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera form 2 ENGINEER'S CERTIFICATE 31 Dec 2020.pdf28 Jan 2021
Certificates of CA (Form 3)File: Rear Form - 3 CA Certificate.pdf28 Jan 2021
Certificates of CA (Form 3)File: MAHA RERA FORM 3- CA Certificate 31082020 uploaded.pdf25 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1 June 2019 Uploaded.pdf22 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MAHA RERA FORM 1 Arch Certf Aug 2020.pdf22 Sep 2020
Details of Restarting of Construction work post lockdownFile: Post Loackdown Construction Work 30082020.pdf22 Sep 2020
Details of encumbrancesFile: Encumberance Declaration SBI March 2019.pdf18 Sep 2020
Certificates of CA (Form 3)File: FORM3 31122018.pdf14 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1 Arch Certf 31122018.pdf12 Mar 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 ENG CERTF 31122018.pdf12 Mar 2019
Layout approvalFile: Copy of Layout Approval.pdf12 Jun 2018
Copy of the legal title reportFile: Legal_Title_Search.pdf12 Jun 2018
Copy of the legal title reportFile: Legal_Title_Search_Report_1.pdf12 Jun 2018
Details of encumbrancesFile: Encum Declaration.pdf12 Jun 2018
Copy of Layout Approval (in case of layout)File: Copy of Layout Approval.pdf12 Jun 2018
Declaration in FORM BFile: RERA-Form B.pdf12 Jun 2018
Proforma of Allotment letterFile: Model Agreement to sale-RERA.pdf12 Jun 2018
Building plan approvalFile: 01-07-R.pdf6 Jun 2018
Building plan approvalFile: 02 of 07.pdf6 Jun 2018
Building plan approvalFile: 03 of 07.pdf6 Jun 2018
Building plan approvalFile: 04 of 07.pdf6 Jun 2018
Building plan approvalFile: 05 of 07.pdf6 Jun 2018
Building plan approvalFile: 06 of 07.pdf6 Jun 2018
Building plan approvalFile: 07 of 07.pdf6 Jun 2018
Building Plan Approval (IOD)File: 01-07-R.pdf6 Jun 2018
Building Plan Approval (IOD)File: 02 of 07.pdf6 Jun 2018
Building Plan Approval (IOD)File: 03 of 07.pdf6 Jun 2018
Building Plan Approval (IOD)File: 04 of 07.pdf6 Jun 2018
Building Plan Approval (IOD)File: 05 of 07.pdf6 Jun 2018
Building Plan Approval (IOD)File: 06 of 07.pdf6 Jun 2018
Building Plan Approval (IOD)File: 07 of 07.pdf6 Jun 2018
Certificates of CA (Form 3)File: FORM3.pdf6 Jun 2018
PAN CardFile: PAN CARD VSPL.pdf27 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates pmrda.pdf27 Mar 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Varad Lake City - RUKHMINI CAmbegaon khurd42CompletedDec 2013Oct 2013

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Varad Lake City on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ambegaon KH13,700+ in Pune

2 kmVarad Lake CityCompleted 163Lapsed / revoked 118Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: VARAD SHELTERS PVT.LTD.

VARAD SHELTERS PVT.LTD. has 1 registration on MahaRERA, including Varad Lake City. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Varad Lake City shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Varad Lake City is delayed beyond 30 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Varad Lake City?

The registered promoter entity is VARAD SHELTERS PVT.LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Varad Lake City?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Varad Lake City?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Varad Lake City?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Varad Lake City?

The professionals named in the filing: Architect: Walhekar and Associates; Engineer: G A Bhilare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Varad Lake City?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Varad Lake City. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Varad Lake City to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.