Home / Browse projects / Pune, Maharashtra / Vande Mataram D wing
Vande Mataram D wing
By Shree Sai Samarth Developers
RG-MH-22151 · RERA P52100032057 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vande Mataram D wing is a Residential / Group Housing project by Shree Sai Samarth Developers in Pune, Maharashtra, registered with MahaRERA as P52100032057 on 3 Dec 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 6 months from the original filing. 31 of the 87 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameVande Mataram D wing
- TypeResidential / Group Housing
- Location
- A05/ 13
- Plot no. 20
- JSector 06alvayu Vihar
- Moshi
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100032057
- ReraGenie IDRG-MH-22151
Builder
- NameShree Sai Samarth Developers
- Entity typePartnership
- PartnersVijay Karamsi Patel, Prabhulal Ramji Patel, Lalit Shantilal Patel, Vandana Naresh Patel, Ujjvalbhai Chhaganbhai Patel, MohammadSiddique Mohammedhanif Patel, Chandubhai Jayantibhai Patel, Bhikaram Bharaji Choudhary, Brijesh Vijay Patel
- PartnerAshvinkumar Haribhai Patel
- Other registrations2 more →
- Completed1 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on3 Dec 2021
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2026)
- Buildings1 building record
- Documents filed108 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Vande Mataram D wing | NA | 14 | 11 | 87 | 0 | 87 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.
Vande Mataram D wing: 62% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 65% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed136
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| BAJIRAO CHABBU PAWAR | Pimpri Chinchawad (M Corp.) | Pune |
| BHAGWANT MARUTI PAWAR | Pimpri Chinchawad (M Corp.) | Pune |
| ASHOK MARUTI BAGADE | Pune (M Corp.) | Pune |
| VIJAY DASHRATH CHOUDHARY | Moshi | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Vande Mataram D wing | NA | Rs 28.47 cr | Rs 9.11 cr |
| - | NA | Rs 3.27 cr | - |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRECISION ARCHITECTS & PLANNER |
| Engineer | SARVASIDDHANT CONSULTANTS |
| Engineer | RATHI GROUP |
| Engineer | AKSHAY TUPE |
| Chartered Accountant | PGMJ AND ASSOCIATES |
| Chartered Accountant | NITISH VAIDYA & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Shree Sai Samarth Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe reason for seeking this extension is that we have received a revised sanctioned plan dated 22/12/2025, bearing File No. B.P/Dudulgaon/67/2025. The inclusion of additional units as per the revised plan requires extra time for construction, and therefore, we are applying for an extension of the project
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jan 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jan 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed108
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 20 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A Final.pdf | 18 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 17 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 17 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 17 Apr 2026 |
| Form 2A (FY 2021-2022)File: Form 2A 2021-22.pdf | 18 Mar 2026 |
| Form 2A (FY 2022-2023)File: Form 2A 2022-23.pdf | 18 Mar 2026 |
| Form 2A (FY 2023-2024)File: Form 2A 2023-24.pdf | 18 Mar 2026 |
| Form 2A (FY 2024-2025)File: Form 2A 2024-25.pdf | 18 Mar 2026 |
| Layout approvalFile: Sanction Plan Highlighted.pdf | 28 Jan 2026 |
| Building plan approvalFile: Building Plan 1.pdf | 28 Jan 2026 |
| Building plan approvalFile: Building Plan 2.pdf | 28 Jan 2026 |
| Building plan approvalFile: Building Plan 3.pdf | 28 Jan 2026 |
| Building plan approvalFile: Building Plan 4.pdf | 28 Jan 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 CA Signed.pdf | 20 Jan 2026 |
| Form 5 (FY 2022-2023)File: Form 5 FY 22-23.pdf | 26 Nov 2025 |
| Form 5 (FY 2023-2024)File: Form 5 FY 23-24.pdf | 26 Nov 2025 |
| Form 5 (FY 2024-2025)File: Form 5 FY 24-25.pdf | 26 Nov 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 20 Oct 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 20 Oct 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 20 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 Final.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 Final.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 ...pdf | 17 Oct 2025 |
| Form 1File: Form 1 Final.pdf | 18 Jul 2025 |
| Form 2File: Form 2 Final.pdf | 18 Jul 2025 |
| Form 3File: Form 3 Upload.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Circular Final.pdf | 18 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final_compressed.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Final.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Circular Final.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf | 10 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf | 10 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Final.pdf | 10 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Final Sold Circular.pdf | 10 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Uploaded_compressed.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 22 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 final.pdf | 22 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf | 5 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2nd Engineer Certificate of Shree Sai Samarth Developers Vande Mataram (D Wing) (30-06-202 | 5 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: sold circular june 2024 new.pdf | 5 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Upload.pdf | 5 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 22 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2.pdf | 22 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 22 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 (Q4 23-24).pdf | 22 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 1 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 1 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 1 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 1 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 1 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 1 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 1 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 1 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 1 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA Signed Form 3 (Q3 21-22).pdf | 1 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 (Q4 21-22).pdf | 1 Apr 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 108 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Vande Mataram D wing on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Moshi13,700+ in Pune
Filed coordinates, straight-line distance. 195 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: Shree Sai Samarth Developers
Shree Sai Samarth Developers has 3 registrations on MahaRERA, including Vande Mataram and Vande Mataram D wing. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Vande Mataram D wing is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vande Mataram D wing?
The registered promoter entity is Shree Sai Samarth Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vande Mataram D wing?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Vande Mataram D wing?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vande Mataram D wing?
The professionals named in the filing: Architect: PRECISION ARCHITECTS & PLANNER; Engineer: SARVASIDDHANT CONSULTANTS; Engineer: RATHI GROUP; Engineer: AKSHAY TUPE; Chartered Accountant: PGMJ AND ASSOCIATES; Chartered Accountant: NITISH VAIDYA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vande Mataram D wing?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback