Home / Browse projects / Pune, Maharashtra / VANDAN VIHAR

Registered No litigation declared Residential / Group Housing project

VANDAN VIHAR

By GVN DEVELOPERS PVT LTD

RG-MH-51895 · RERA P52100016206 · Last updated on MahaRERA portal: 8 Apr 2025

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 51 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 51 months from the original
7 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 80%
2Complaints at MahaRERAon this registration
Jump to the 142 documents Report an error

VANDAN VIHAR is a Residential / Group Housing project by GVN DEVELOPERS PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100016206 on 24 Apr 2018. Possession is promised by 30 Jun 2027. The completion date has moved by 51 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameVANDAN VIHAR
  • TypeResidential / Group Housing
  • Location
    • WADKI NALA ROAD
    • WADKI
    • Haveli
    • Pune
    • 412308
  • Pincode412308
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100016206
  • ReraGenie IDRG-MH-51895

Builder

  • NameGVN DEVELOPERS PVT LTD
  • Entity typeCompany
  • DirectorsVANDANA NARENDRA LODHA, Shweta Vaibhav Lodha
  • Managing DirectorVAIBHAV NARENDRA LODHA
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2018First promiseMar 2023Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Apr 2018
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Mar 2023)
  • Buildings2 building records
  • Documents filed142 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BNA70000
ANA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 80%.

B55%
ActivityProgress
Excavation100%
Basement (if any)1%
Podiums (if any)0%
Plinth1%
Stilt Floor0%
Slabs of Super Structure8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A24%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes50%

Parking filed616

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots616
Closed/Covered308
Open Space308
BuildingClosed/CoveredOpen SpaceTotal
B154154308
A154154308

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHRI DATTATRAY PARSHURAM MODAK AND OTHERSWadkiPune

Approvals and building plan

Permissible FSI6407.87
Proposed, not sanctioned5,499 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGALAXY SOCIETY, DHOLE PATIL ROAD, BUND GARDEN ROAD, PUNE - 411001

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
GVN DEVELOPERS PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100014009Mar 2023 → Mar 2024

Reason as filed by the promoterThe proposed date of completion was 30/03/2023. But due to changes in UDCPR rules along with waiting period for new sanctioning, we were unable to move forward with our construction. So the proposed date of completion needs to be changed to 29/03/2024.

EXT52100019311Mar 2023 → Jun 2027

Reason as filed by the promoterWe will apply for final Fire NOC of Building B to PMRDA, which we expect to get by 30.05.2024. On receiving, we will apply for grant of OCCUPANCY CERTIFICATE to PMRDA, which we expect to get by 30.06.2024. Accordingly, we plan to execute this compliance process accordingly and thereby handover the possession of Building “B” at the earliest possible depending on the ease of obtaining NOCs and OCCUPANCY CERTIFICATE from concerned government authorities. With regards to commencement of work of Building “A”, we have already started construction of footings and as per the present socio-economic cir

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000208209Shubham Santosh MoreVaibhav Narendra Lodha02/02/2023
CC12501298SACHIN BHANUDAS JAGTAPGVN DEVELOPERS PVT LTD19/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 9 Jan 2025

Documents filed142

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 142 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf8 Apr 2025
Certificates of CA (Form 3)File: Q4 Fy23-24.pdf22 Feb 2025
Certificates of CA (Form 3)File: q1 Fy24-25.pdf22 Feb 2025
Certificates of CA (Form 3)File: Q2 Fy24-25.pdf22 Feb 2025
Certificates of CA (Form 3)File: Q3 Fy24-25.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng Q4 Fy23-24.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng Q1 Fy24-25.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng Q2 Fy24-25.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng Q3 Fy24-25.pdf22 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: wadki new commencement certificate.pdf9 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VV B building Occupancy certificate oc.pdf9 Jan 2025
Declaration in FORM BFile: GVN DEVELOPERS PVT LTD (1).pdf4 Apr 2024
Declaration in FORM BFile: rera form b 2024.pdf4 Apr 2024
Declaration about Commencement CertificateFile: commencement certificate declaration.pdf12 Mar 2024
Disclosure of sold/ booked inventoryFile: march 2024 disclosure rera.pdf12 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest.pdf12 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy19-20 Q1.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy19-20 Q2.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy19-20 Q3.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy19-20 Q4.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy20-21 Q1.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy20-21 Q2.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy20-21 Q3.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy20-21 Q4.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy21-22 Q1.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy21-22 Q2.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy21-22 Q3.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy21-22 Q4.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy22-23 Q1.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy22-23 Q2.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy22-23 Q3.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fy22-23 Q4.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ar cert q1 23-24.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ar cert q2 23-24.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ar cert q3 23-24.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q1 FY19-20.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q2 FY19-20.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q3 FY19-20.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q4 FY19-20.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q1 FY20-21.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q2 FY20-21.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q3 FY20-21.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q4 FY20-21.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q1 FY21-22.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q2 FY21-22.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q3 FY21-22.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q4 FY21-22.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q1 FY22-23.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q2 FY22-23.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate Q3 FY22-23.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng cert q4 22-23.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng cert q1 23-24.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng cert q2 23-24.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng cert q3 23-24.pdf2 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: fy22-23 2A.pdf2 Mar 2024
Certificates of CA (Form 3)File: RERA Quarterly Certifications 2021-22 Q2 Signed.pdf2 Mar 2024
Certificates of CA (Form 3)File: RERA Quarterly Certifications 2021-22 Q3 Signed.pdf2 Mar 2024
Certificates of CA (Form 3)File: RERA Quarterly Certifications 2021-22 Q4 Signed.pdf2 Mar 2024
Certificates of CA (Form 3)File: RERA Quarterly Certifications 2022-23 Q1 Signed.pdf2 Mar 2024
Certificates of CA (Form 3)File: RERA Quarterly Certifications 2022-23 Q2 Signed-compressed.pdf2 Mar 2024
Certificates of CA (Form 3)File: RERA Quarterly Certifications 2022-23 Q3 Signed.pdf2 Mar 2024
Certificates of CA (Form 3)File: RERA Quarterly Certifications 2022-23 Q4 Signed.pdf2 Mar 2024
Certificates of CA (Form 3)File: ca cert q1 23-24-compressed.pdf2 Mar 2024
Certificates of CA (Form 3)File: ca cert q2 23-24-compressed.pdf2 Mar 2024
Certificates of CA (Form 3)File: ca cert q3 23-24-compressed.pdf2 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23 Final.pdf2 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Certificate 19-20.pdf28 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Certificate -20-21.pdf28 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Certificate 21-22.pdf28 Mar 2023
Declaration about Commencement CertificateFile: Format D.pdf27 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2a - 2020.pdf27 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2a - 2021.pdf27 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2a - 2022.pdf27 Mar 2023
Disclosure of sold/ booked inventoryFile: Inventory disclosure.pdf27 Mar 2023
Proforma of Agreement for saleFile: RERA - WADKI - AGREEMENT FOR SALE.pdf27 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: collection account details.pdf27 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: RERA Quarterly Certifications 2019-20 Q1.pdf24 Sep 2022
Certificates of CA (Form 3)File: fy18-19 Q2.pdf24 Sep 2022
Certificates of CA (Form 3)File: fy18-19 Q3.pdf24 Sep 2022
Certificates of CA (Form 3)File: fy18-19 Q4.pdf24 Sep 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
STEPPING STONELANE NO B22 DHAYARI PUNE 41104212CompletedMar 2015Late, Jul 2015

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 51 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VANDAN VIHAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WADKI13,700+ in Pune

2 kmVANDAN VIHARCompleted 1Lapsed / revoked 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 7 registered projects within 2 km.

Builder: GVN DEVELOPERS PVT LTD

GVN DEVELOPERS PVT LTD has 1 registration on MahaRERA, including VANDAN VIHAR. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VANDAN VIHAR is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VANDAN VIHAR?

The registered promoter entity is GVN DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VANDAN VIHAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VANDAN VIHAR?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VANDAN VIHAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in VANDAN VIHAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VANDAN VIHAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VANDAN VIHAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.