Home / Browse projects / Bengaluru Urban, Karnataka / VAISHNAVI SENATE

Registration approved No litigation declared Commercial project

VAISHNAVI SENATE

By VAISHNAVI INFRASTRUCTURE PVT LTD

RG-KA-81782 · RERA PRM/KA/RERA/1251/446/PR/041023/006299 · Last updated on RERA Karnataka portal: 14 Sep 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 125 documents Report an error

VAISHNAVI SENATE is a Commercial project by VAISHNAVI INFRASTRUCTURE PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/041023/006299 on 4 Oct 2023. Possession is promised by 31 Dec 2026.

At a glance

Project

  • NameVAISHNAVI SENATE
  • TypeCommercial
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560076
  • Pincode560076
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/041023/006299
  • ReraGenie IDRG-KA-81782

Builder

  • NameVAISHNAVI INFRASTRUCTURE PVT LTD
  • Entity typeCompany
  • CINU70102KA2006PTC040918
  • GSTIN29AACCV3531A1ZP
  • Authorized SignatoryK.R Shoban Babu
  • Managing DirectorC.N Govindaraju
  • DirectorsC Asha Govindaraju, Darshan Govindaraju, Kishan Govindaraju
  • Project HeadRadhakrishna
  • Other registrations2 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredOct 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Oct 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed125 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vaishnavi Senate---01111

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-
Others-

Progress on shared amenities40

As on 14 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyYes-
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningYes-
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areasYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership6

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,645 sq m
Named landowners6
LandownerVillageDistrict
B.S MANJUNATH--
B. S. RAMESH--
B.S NAGARAJ--
B. S. RAVI--
KATTAMMA--
B S BINDU--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 169.45 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 169.45 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDILIP NADIG
EngineerHareesh Gowda
Chartered AccountantS.P.Krishnamurthy & Co.

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed125

As listed on the registration, under the names the promoter filed them with; the newest 80 of 125 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/041023/006299 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Updated the Source of funds with the supporting documentsFile: Source of funds with the supporting - com.pdf14 Sep 2023
Uploaded Profit and loss and Balance sheet with Schedule - 2019-2020 with CA UDINFile: 1) BS PL 19-20 with UDIN Schedule.pdf14 Sep 2023
Uploaded Profit and loss and Balance sheet with Schedule - 2020-2021 with CA UDINFile: 2) BS PL 20-21 with UDIN Schedule.pdf14 Sep 2023
Uploaded Profit and loss and Balance sheet with Schedule - 2021-2022 with CA UDINFile: 3) BS PL 21-22 with UDIN Schedule.pdf14 Sep 2023
Uploaded RTC for survey No. 178/2File: 5) RTC.pdf14 Sep 2023
Uploaded latest EC dated 01-01-2022 - 31-08-2023File: 21) Encumbrance Certificate 01 Jan 2022 - 31 Aug 2023.pdf14 Sep 2023
Uploaded advocate search report - updated 04th SepFile: 27) ADVOCATE SEARCH REPORT-REVISED.pdf14 Sep 2023
Uploaded CDP map showing the proposed siteFile: 6) CDP.pdf14 Sep 2023
Uploaded Village map showing the proposed siteFile: 7) Village Map with Site.pdf14 Sep 2023
Uploaded Building LicenseFile: 8) Building Licence.pdf14 Sep 2023
Uploaded KSPCB CFEFile: 9) KSPCB CFE Senate.PDF14 Sep 2023
Uploaded sanctioned signed/digitally signed drawings,floor plans, sectional drawings and elevationsFile: 10) Approved Sanction plan - floor wise.pdf14 Sep 2023
Uploaded the Sel attested copy of the Engineer lincense certificateFile: 11) Self attested Engineer Certificate.pdf14 Sep 2023
Updated the Amenities and common area details, uploaded the Amenities and common area calculation shFile: 12) VAISHNAVI SENATE AMENITIES DETAILS.pdf14 Sep 2023
Uploaded the Land costcalculation sheet as per the guidance value(self attested copy)File: 20) Guidance Land Value Calculation.pdf14 Sep 2023
Uploaded the certificate from the registered Engineer indicating the structural safety for the projeFile: 15) Structural Stability certificate.pdf14 Sep 2023
Uploaded brief of Estimated engineering cost certified by the engineerFile: 14) Brief Estimated cost certified by Engg.pdf14 Sep 2023
Uploaded the Affidavit - BWSSB NOC, condition marked in the sanction planFile: 19) AFFIDAVIT_BWSSB NOC Condition marked.pdf14 Sep 2023
Notarised Affidavit of Sec 3(1) updated with the project name and the addressFile: 16) Affidavit - Sec 3.pdf14 Sep 2023
Uploaded the STP design drawing certified by the engineeras per the KSPCB NOCFile: 17) STP Senate certified.pdf14 Sep 2023
Uploaded the Proforma Allotment letter in the prescribed formatFile: Allotment - VS.pdf14 Sep 2023
Uploaded Proforma of the Agreement for sale as per GOK notifiedFile: AOS - L.pdf14 Sep 2023
Uploaded Project specification certified by the EngineerFile: 18) Project specification - certified by Engg.pdf14 Sep 2023
Uploaded BESCOM NOC with Fee receiptsFile: BESCOM NOC R.pdf14 Sep 2023
RTC, survey 178/2-
Mutation, survey 178/2-
Encumbrance Certificate, survey 178/2-
Conversion/Alienation Order, survey 178/2-
JDA, survey 178/2-
Khatha, survey 178/2-
Registration CertificateFile: Certificate of Incorporation VIPL.pdf-
Organization StructureFile: Org Chart Senate.pdf-
Certificate issued by CA Form 1File: Form 1 CA certificate.pdf-
Certificate issued by Architect Form 2File: Form2 - Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form 3 - Engg certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non- litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form 1 CA certificate.pdf-
Balance Sheet 2021 - 2022File: Balance sheet - 2022.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet-31-3-2021-VIPL.pdf-
Balance Sheet 2019 - 2020File: Balance Sheet-31-3-2020-VIPL.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Profit and loss - 2022.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit and Loss Ac as on 31-3-2021-VIPL.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit and Loss Ac as on 31-3-2020-VIPL.pdf-
Director's Report 2021 - 2022File: Director Report Mar 2022 com.pdf-
Director's Report 2020 - 2021File: Director Report Mar 21com.pdf-
Director's Report 2019 - 2020File: Director Report Mar 2020VIPL com.pdf-
Cash Flow Statement 2021 - 2022File: Cash flow -2022.pdf-
Cash Flow Statement 2020 - 2021File: Cash Flow Statement-31-3-2021-VIPL.pdf-
Auditor's Report 2021 - 2022File: Auditor Report-31-3-2022.pdf-
Auditor's Report 2020 - 2021File: Auditor Report-31-3-2021-VIPL_compressed.pdf-
Auditor's Report 2019 - 2020File: Auditor Report-31-3-2020-VIPL_compressed.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: VIPL IT Acknow AY 2021-22.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: VIPL IT Acknow AY 2021-22.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: VIPL IT Acknow AY 2020-21.pdf-
NA Blank-
BESCOM NOC-V Senate-
BWSSB-
V Senate BBMP Sanctioned plan-
SITE PLAN-
NA Blank-
Section & Elevation-
V Senate BBMP Sanctioned plan-
Project Specification-
Section & Elevation-
NA Blank-
NA Blank-
Advocate search report-
NA Blank-
V Senate - JDA-
Conversion Order - Commercial-
NA Blank-
NA Blank-
V Senate - GPA-
Draft - ATS F-
Allotment letter-
NA Blank-
Form B-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Vaishnavi Tech ParkPlot No. 19/16/1 & 17/2, Ambalipura Village, Varthur Hobli, Ward No. 150,Completed-No date filed
Vaishnavi Signature#77, 1, Marathahalli - Sarjapur Outer Ring Rd, Bellandur,Completed-No date filed
Vaishnavi ARS Gardenia#1, S.M Road, T. DasarahalliCompleted-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep VAISHNAVI SENATE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmVAISHNAVI SENATEOther 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: VAISHNAVI INFRASTRUCTURE PVT LTD

Vaishnavi Infrastructure Pvt Ltd has 3 registrations on RERA Karnataka, including Vaishnavi Tech Square and VAISHNAVI SENATE. Its filings declare 4 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if VAISHNAVI SENATE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of VAISHNAVI SENATE?

The registered promoter entity is VAISHNAVI INFRASTRUCTURE PVT LTD, a company as per the filing. Its CIN U70102KA2006PTC040918 and GSTIN 29AACCV3531A1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in VAISHNAVI SENATE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VAISHNAVI SENATE?

The professionals named in the filing: Architect: DILIP NADIG; Engineer: Hareesh Gowda; Chartered Accountant: S.P.Krishnamurthy & Co.. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VAISHNAVI SENATE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VAISHNAVI SENATE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VAISHNAVI SENATE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.