Home / Browse projects / Raigarh, Maharashtra / VAISHNAV VILLA

Completed No litigation declared Residential / Group Housing project

VAISHNAV VILLA

By AVDHOOT REALITY

RG-MH-42362 · RERA P52000019588 · Last updated on MahaRERA portal: 21 Oct 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 56 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedregistration recorded completed
9 of 9Construction stages doneevery applicable stage filed complete
4 of 23Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 172 documents Report an error

VAISHNAV VILLA is a Residential / Group Housing project by AVDHOOT REALITY in Raigarh, Maharashtra, registered with MahaRERA as P52000019588 on 12 Feb 2019. The registration is recorded completed; possession was promised by 31 Mar 2027. The completion date has moved by 56 months from the original filing. 19 of the 23 units on this registration are recorded sold or booked, and 9 of 9 construction stages are filed complete.

At a glance

Project

  • NameVAISHNAV VILLA
  • TypeResidential / Group Housing
  • Location
    • KARJAT MURBAD ROAD
    • LADIWALI
    • Karjat
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000019588
  • ReraGenie IDRG-MH-42362

Builder

  • NameAVDHOOT REALITY
  • Entity typePartnership
  • GSTIN27ABDFA2440A1Z7
  • PartnerSHANU RAMASHANKER SINGH

Key dates

this monthRegisteredFeb 2019First promiseJul 2022Revised toMar 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on12 Feb 2019
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Jul 2022)
  • Buildings1 building record
  • Documents filed172 files

Current status

83%19 of 23 units booked
87.3%Work done, per cost certificate

Figures as on 21 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VAISHNAV VILLANA4420323

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 9 construction stages are filed complete.

VAISHNAV VILLA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered12

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area620 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Oct 2026

Approvals and building plan

Sanctioning authorityCollector of Raigad
Permissible FSI619.97
Proposed, not sanctioned620 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEW PANVEL WEST BRANCH PANVEL 410206
Estimated costRs 1.48 cr
Cost incurredRs 1.30 cr
Work done87.33%
BuildingWingEstimatedIncurred
VAISHNAV VILLANARs 1.38 crRs 1.25 cr
-NARs 9.89 lakhRs 4.95 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSARA CONSULTANCY
EngineerATUL KUDTARKAR
EngineerAtul Kudtarkar & Associates
Chartered AccountantGanesh Bhoir & Asscoiates
Chartered AccountantB.N.Dudani & Co
PartnerRole in project
AVDHOOT REALITY-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000012318Jul 2022 → Jul 2023

Reason as filed by the promoterMy projects got disturbed by Covid-19 pandemic very badly. Our construction activity not yet got stable, as our labour and contractors migrated to their hometown. We still not able to get competent labour and contractors to get the work completed. Please grant us extension.

EXT52000016875Jul 2022 → Jul 2024

Reason as filed by the promoterDue to Covid 19 pandemic, Second Waive, our construction activity got shucked. Labour hired by us are not able to come to the project place due to non-availability of transport facility. Lockdown cause non-availability of construction material. We genuinely want to complete the project within time, but due to invoking force majeure we are unable to complete the project within due date. Therefore, we hereby request you to Grant us extension to our project by One (1) Year. We assure you that we will complete the project within a period of one year of extension.

EA03092622454Jul 2022 → Mar 2027

Reason as filed by the promoterDear Sir/Ma’am, We, AVDHOOT REALITY, hereby declare the following with respect to the project “VAISHNAV VILLA” bearing registration number P52000019588 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Occupatio

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Feb 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Sep 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Sep 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed172

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 172 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 September 2026.pdf21 Oct 2026
Withdrawal Update Form 2File: Form 2 September 2026.pdf21 Oct 2026
Withdrawal Update Form 3File: Form 3 September 2026.pdf21 Oct 2026
Form 2A (FY 2026-2027)File: Form 2A 25-26.pdf21 Oct 2026
Form 5 (FY 2025-2026)File: Form 5 2024-25.pdf21 Oct 2026
Occupational CertificateFile: vaishnav villa OC_11zon.pdf21 Oct 2026
Layout approvalFile: Clear Plan_11zon.pdf19 Sep 2026
Building plan approvalFile: Clear Plan_11zon.pdf19 Sep 2026
Form 1File: Form 1.pdf19 Sep 2026
Form 2File: Form 2.pdf19 Sep 2026
Form 3File: Form 3.pdf19 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2024.pdf19 Sep 2026
Form 1File: Form 1.pdf19 Sep 2026
Form 2File: Form 2.pdf19 Sep 2026
Form 3File: Form 3.pdf19 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2025.pdf19 Sep 2026
Withdrawal Update Form 1File: Form 1.pdf19 Sep 2026
Withdrawal Update Form 1File: Form 1.pdf19 Sep 2026
Withdrawal Update Form 1File: Form 1.pdf19 Sep 2026
Withdrawal Update Form 1File: Form 1.pdf19 Sep 2026
Withdrawal Update Form 1File: Form 1.pdf19 Sep 2026
Withdrawal Update Form 2File: Form 2.pdf19 Sep 2026
Withdrawal Update Form 2File: Form 2.pdf19 Sep 2026
Withdrawal Update Form 2File: Form 2.pdf19 Sep 2026
Withdrawal Update Form 2File: Form 2.pdf19 Sep 2026
Withdrawal Update Form 2File: Form 2.pdf19 Sep 2026
Withdrawal Update Form 3File: Form 3.pdf19 Sep 2026
Withdrawal Update Form 3File: Form 3.pdf19 Sep 2026
Withdrawal Update Form 3File: Form 3.pdf19 Sep 2026
Withdrawal Update Form 3File: Form 3.pdf19 Sep 2026
Withdrawal Update Form 3File: Form 3.pdf19 Sep 2026
Form 2A (FY 2025-2026)File: Form 2A 25-26.pdf19 Sep 2026
Withdrawal Update Form 1File: Form 1.pdf3 Sep 2026
Withdrawal Update Form 2File: Form 2.pdf3 Sep 2026
Withdrawal Update Form 3File: Form 3.pdf3 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2019.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2019.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2019.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2019.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2020.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2020.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2020.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2020.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2021.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2021.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026
Form 2File: Form 2.pdf2 Sep 2026
Form 3File: Form 3.pdf2 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2021.pdf2 Sep 2026
Form 1File: Form 1.pdf2 Sep 2026

How this compares with Raigarh

83%of this project is bookeddistrict median 28%
21%of Raigarh projects moved their completion datethis one moved by 56 months
25%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VAISHNAV VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near LADIWALI5,900+ in Raigarh

2 kmVAISHNAV VILLACompleted 51Lapsed / revoked 33Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 123 registered projects within 2 km.

Builder: AVDHOOT REALITY

AVDHOOT REALITY has 1 registration on MahaRERA, including VAISHNAV VILLA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if VAISHNAV VILLA is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VAISHNAV VILLA?

The registered promoter entity is AVDHOOT REALITY, a partnership as per the filing. Its GSTIN 27ABDFA2440A1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VAISHNAV VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VAISHNAV VILLA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VAISHNAV VILLA?

The professionals named in the filing: Architect: SARA CONSULTANCY; Engineer: ATUL KUDTARKAR; Engineer: Atul Kudtarkar & Associates; Chartered Accountant: Ganesh Bhoir & Asscoiates; Chartered Accountant: B.N.Dudani & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VAISHNAV VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VAISHNAV VILLA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VAISHNAV VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.