ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / VAIBHAV HEIGHTS

Registered No litigation declared Residential / Group Housing project

VAIBHAV HEIGHTS

By RSN BALAJI REALTORS P LTD

RG-MH-12546 · RERA P51800002862 · Last updated on MahaRERA portal: 14 May 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 96 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 96 months from the original
18 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 95%
0 of 52Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

VAIBHAV HEIGHTS is a Residential / Group Housing project by RSN BALAJI REALTORS P LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002862 on 4 Aug 2017. Possession is promised by 30 Dec 2026. The completion date has moved by 96 months from the original filing. 52 of the 52 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameVAIBHAV HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • SHIVAJI NAGAR ROAD
    • NEAR JAIN MANDIR
    • Andheri
    • Mumbai Suburban
    • 400055
  • Pincode400055
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002862
  • ReraGenie IDRG-MH-12546

Builder

  • NameRSN BALAJI REALTORS P LTD
  • Entity typeCompany
  • Managing DirectorMITHALAL MOOLCHAND JAIN

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Aug 2017
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 31 Dec 2018)
  • Buildings2 building records
  • Documents filed86 files

Current status

100%52 of 52 units booked

Figures as on 14 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WING CHOKSI APT REHABNA1514909
B WING VAIBHAV HEIGHTSNA151439443

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.

A WING CHOKSI APT REHAB90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
B WING VAIBHAV HEIGHTS90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed47

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots47
Closed/Covered47
BuildingClosed/CoveredTotal
A WING CHOKSI APT REHAB2727
B WING VAIBHAV HEIGHTS2020

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,387 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Jul 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI4109.85
Proposed, not sanctioned3,589 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVAKOLA, SANTACRUZ EAST MUMBAI 400055

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSYNERGY ARCHITECH
EngineerFRAMES
Chartered AccountantCHETAN JAIN & CO
PartnerRole in project
RSN BALAJI REALTORS P LTD-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000915Dec 2018 → Apr 2020

Reason as filed by the promoterDue to awaiting implementation of DCPR 2034 and road TDR policy in connection to DCPR 2034, no file was being processed by MCGM for concession and issue of further CC. Thus due to non issuance of permission by the authority the project was not completed on time. The said permission is now seeked into by applying for the same to MCGM after implementation of DCPR 2034. Thus we request for an extension till Dec 2019.

EXT51800003750Dec 2018 → Apr 2020

Reason as filed by the promoter1) Ours is an ongoing project on land bearing CTS No. 3929 to 3949 proposed for 14th floors. We have completed work up till 12th floor having achieved height of 42.83 AMSL. We are applying for part OC upto 12th Floor. 2) We received NOC from Airport Authority of India (AAI), vide their letter no. BT-1/NOC/ CS/MUM/13/NOCAS/391 dated 9/5/2014 with sanctioned height of 50.50 AMSL valid for 5 years. 3) Thus we had applied to (AAI) for Revalidation of our NOC for further 3 years. To our surprise they have replied that “no construction work has commenced within the coordinates mentioned in the NOC”

EXT51800006381Dec 2018 → Jun 2023

Reason as filed by the promoterDue to Promoters RSN Balaji Realtors has received NOC from Airport Authority of India (AAI), vide their letter no. BT-1/NOC/ CS/MUM/13/NOCAS/391 dated 9/5/2014. This NOC is firstly issued for 5 (five) years, and then it can be further extended for 3 (three) years. And the Promoter has applied to (AAI) for Revalidation of NOC for further 3 years. This is expected to get very soon. As per the new DCPR 2034, new widening of RL road from 12.20 mtrs. to 18.30 mtrs. on the existing C S M Road, and the same is under EP (excluded portion). Which is supposed to be sanctioned under s/c 30 .

EXT51800018202Dec 2018 → Dec 2024

Reason as filed by the promoterDUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 31/12/2024

EXT51800025455Dec 2018 → Dec 2026

Reason as filed by the promoterThe Project was Delay Due to awaiting implementation of DCPR 2034 and road policy in connection to DCPR 2034 and also because of getting Revalidations of NOC from civil aviation authority. The Plot was affected by road set back from both side i.e back and front, therefore it took long to handover the road set back to both the DP department and RL department separately

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000198853CORRINDA MIRANDAM/S RSN BALAJI REALTORS (P) LTD29/10/2021
CC006000000591137SANJAY SINGHRSN BALAJI REALTORS P LTD12/07/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Sep 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Oct 2022

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architech Certificate.pdf14 May 2026
Withdrawal Update Form 2File: FORM 2 ENGINEERS CERTIFICATE.pdf14 May 2026
Withdrawal Update Form 3File: FORM 3 C A CERTIFICATE.pdf14 May 2026
Withdrawal Update Form 1File: Form 1 Architech Certificate.pdf7 May 2026
Withdrawal Update Form 2File: FORM 2 ENGINEERS CERTIFICATE.pdf7 May 2026
Withdrawal Update Form 3File: FORM 3 C A CERTIFICATE.pdf7 May 2026
Withdrawal Update Form 1File: Form 1 Architech Certificate.pdf6 Dec 2025
Withdrawal Update Form 2File: FORM 2 ENGINEERS CERTIFICATE.pdf6 Dec 2025
Withdrawal Update Form 3File: FORM 3 C A CERTIFICATE.pdf6 Dec 2025
Form 1File: Form 1 Architech Certificate.pdf31 Jul 2025
Form 2File: Form 2 engineer Certificate.pdf31 Jul 2025
Form 3File: Form 3 C A Certifiacte.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: Discloser of Sold - Booked inventory.pdf31 Jul 2025
Certificates of CA (Form 3)File: form 3 july to sep 24.pdf7 Dec 2024
Declaration in FORM BFile: FORM B (3).pdf4 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 ARCH CERTIFICATE WITH PROMOTER SIGN.pdf4 Dec 2024
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE WITH PROMOTER SIGN.pdf4 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: FULL CC Signed.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: DISCLOSERE OF SOLD BOOKED INVENTORY.pdf4 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 23-24.pdf4 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 C A CERTIFICATE.pdf4 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECH CERTIFICATE.pdf12 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEERS CERTIFICATE.pdf12 Dec 2023
Disclosure of sold/ booked inventoryFile: INVENTORY DISCLOSURE SOLD AND UNSOLD.pdf12 Dec 2023
Certificates of CA (Form 3)File: FORM 3 C A CERTIFICATE.pdf12 Dec 2023
Declaration about Commencement CertificateFile: CC Covering letter.pdf11 Dec 2023
Declaration in FORM BFile: FORM B.pdf11 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2a 19-20.pdf11 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2a 20-21.pdf11 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2a 21-22.pdf11 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2a 22-23.pdf11 Dec 2023
CERSAI detailsFile: Cresai declaration.pdf11 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf11 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf11 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf11 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.pdf11 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: C C UPTO 14th Floor of A wing and 13 th Floor of B wing.pdf12 Oct 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC upto 12 th floor of Wing A and B wing.pdf12 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NO PROGRESS LETTER.pdf9 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: no progress letter.pdf20 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch letter rsn.pdf20 Aug 2020
Details of Restarting of Construction work post lockdownFile: covid-19 rsn.pdf20 Aug 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH_compressed.pdf4 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG.pdf4 Feb 2020
Certificates of CA (Form 3)File: CA.pdf4 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 RSN BALAJI.pdf26 Dec 2019
Building plan approvalFile: IOD 1 FINAL PLAN.pdf18 Sep 2019
Building plan approvalFile: IOD 2 FINAL PLAN.pdf18 Sep 2019
Building plan approvalFile: IOD 3 FINAL PLAN.pdf18 Sep 2019
Building plan approvalFile: IOD 4 FINAL PLAN.pdf18 Sep 2019
Building plan approvalFile: IOD 5 FINAL PLAN.pdf18 Sep 2019
Building plan approvalFile: IOD 6 FINAL PLAN.pdf18 Sep 2019
Building plan approvalFile: IOD 7 FINAL PLAN.pdf18 Sep 2019
Building Plan Approval (IOD)File: IOD 1 FINAL PLAN.pdf18 Sep 2019
Building Plan Approval (IOD)File: IOD 2 FINAL PLAN.pdf18 Sep 2019
Building Plan Approval (IOD)File: IOD 3 FINAL PLAN.pdf18 Sep 2019
Building Plan Approval (IOD)File: IOD 4 FINAL PLAN.pdf18 Sep 2019
Building Plan Approval (IOD)File: IOD 5 FINAL PLAN.pdf18 Sep 2019
Building Plan Approval (IOD)File: IOD 6 FINAL PLAN.pdf18 Sep 2019
Building Plan Approval (IOD)File: IOD 7 FINAL PLAN.pdf18 Sep 2019
Certificates of CA (Form 5)File: Form 5 certificate.pdf31 Jul 2019
Certificates of CA (Form 5)File: Corrected certificate form 5.pdf31 Jul 2019
Certificates of CA (Form 5)File: Corrected certificate form 5.pdf31 Jul 2019
Building plan approvalFile: Amended Issue Letter.pdf23 Jun 2018
Building Plan Approval (IOD)File: Amended Issue Letter.pdf23 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: FULL CC DATED - 21-06-2018.pdf23 Jun 2018
Certificates of CA (Form 3)File: CA certificate for RERA.pdf26 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH CERTIFICATE FOR RERA.pdf24 Jul 2017
Layout approvalFile: NO LAYOUT COPY.pdf22 Jul 2017
Building plan approvalFile: BUILDING PLAN IOD 1.pdf22 Jul 2017
Building plan approvalFile: BUILDING PLAN IOD 12.pdf22 Jul 2017
Building plan approvalFile: BUILDING PLAN IOD 13.pdf22 Jul 2017
Building plan approvalFile: BUILDING PLAN IOD 14.pdf22 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE FROM VIGIL JURIS.pdf22 Jul 2017
Details of encumbrancesFile: Encumbrances copy.pdf22 Jul 2017
Copy of Layout Approval (in case of layout)File: NO LAYOUT COPY.pdf22 Jul 2017
Building Plan Approval (IOD)File: BUILDING PLAN IOD 1.pdf22 Jul 2017
Building Plan Approval (IOD)File: BUILDING PLAN IOD 12.pdf22 Jul 2017

How this compares with Mumbai Suburban

100%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 96 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VAIBHAV HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR JAIN MANDIR6,700+ in Mumbai Suburban

2 kmVAIBHAV HEIGHTSCompleted 116Lapsed / revoked 71Other 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 309 registered projects within 2 km.

Builder: RSN BALAJI REALTORS P LTD

RSN BALAJI REALTORS P LTD has 1 registration on MahaRERA, including VAIBHAV HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if VAIBHAV HEIGHTS is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VAIBHAV HEIGHTS?

The registered promoter entity is RSN BALAJI REALTORS P LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VAIBHAV HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VAIBHAV HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VAIBHAV HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VAIBHAV HEIGHTS?

The professionals named in the filing: Architect: SYNERGY ARCHITECH; Engineer: FRAMES; Chartered Accountant: CHETAN JAIN & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VAIBHAV HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VAIBHAV HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VAIBHAV HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.