Home / Browse projects / Mumbai Suburban, Maharashtra / Bluemoon Annexe

Registration lapsed No litigation declared Residential / Group Housing project

Bluemoon Annexe

By MUDASSAR BUILDERS & DEVELOPERS

RG-MH-12391 · RERA P51800003318 · Last updated on MahaRERA portal: 8 Jun 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 87 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
19 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 80%
120 of 135Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

Bluemoon Annexe is a Residential / Group Housing project by MUDASSAR BUILDERS & DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003318 on 5 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 87 months from the original filing. 15 of the 135 units on this registration are recorded sold or booked, and 19 of 33 construction stages are filed complete.

At a glance

Project

  • NameBluemoon Annexe
  • TypeResidential / Group Housing
  • Location
    • Sunder Nagar
    • Kalina
    • Andheri
    • Mumbai Suburban
    • 400055
  • Pincode400055
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003318
  • ReraGenie IDRG-MH-12391

Builder

  • NameMUDASSAR BUILDERS & DEVELOPERS
  • Entity typePartnership

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseSep 2018Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Sep 2018)
  • Buildings3 building records
  • Documents filed72 files

Current status

11%15 of 135 units booked

Figures as on 8 Jun 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A wingNA8759665
C wingNA111039342
B wingNA10925328

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 8 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 80%.

A wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C wing45%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B wing82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 8 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes10%
Street LightingYes25%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes25%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes25%
Open ParkingNoNot applicable

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered3
Open Space14
BuildingClosed/CoveredOpen SpaceTotal
A wing11011
C wing145
B wing101

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,337 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY
Permissible FSI3.0
Proposed, not sanctioned3 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPATTATHE HOUSE, KALINA KURLA ROAD, SANTACRUZ EAST, MUMBAI - 400029

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAVIN JAGANNATH NAIK
Chartered AccountantI N SHAH
PartnerRole in project
MUDASSAR BUILDERS & DEVELOPERS-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008757Sep 2018 → Dec 2021

Reason as filed by the promoterproject delayed due to Pandamic and stop work notice

EXT51800011966Sep 2018 → Dec 2023

Reason as filed by the promoterLOI for ā€œCā€ wing was pending, now SRA has approved new LOI is having complete Approval i.e. ā€œCā€ wing is having Grd+10 storied approval and also there was no progress in Covid period i.e. March 20 to May 21.

EXT51800000853Sep 2018 → Sep 2019

Reason as filed by the promoterSRA has issued Stop work notice that's why project work is stop and project is delayed.

EXT51800018794Sep 2018 → Dec 2024

Reason as filed by the promoterThe Approval i.e. SRAC IOA & CC which was issued till that level the project is completed & Occupation Certificate is obtained & handed over Flats to all buyers , old Rehab tenants & Government reserve Flats to Government. the balance approval IOA is issued CC is awaited and same is expected to be issued in January 2024 hence the delay is due to delay in approval.

EXT51800027706Sep 2018 → Dec 2025

Reason as filed by the promoterCC is issued on 11.06.24 , We completed work of C wing as SRA handing over flats of PTC are involved by March 2025 we will try to obtained OC of C wing by December 2025 , we will try to complete B wing 8th & 9th floor and obtained OC for entire project.

Litigation declared1

CaseCourtStatus
595/2017HIGH COURTPENDING

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1-architech-2024-2025.pdf8 Jun 2025
Certificates of CA (Form 3)File: FORM 3-2024-25_.pdf8 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2-enginer-2024-2025.pdf8 Jun 2025
Other - TechnicalFile: consent from buyers-bluemoon-2025.pdf8 Jun 2025
Certificates of CA (Form 3)File: IMG_0001 (1)_compressed.pdf22 May 2025
Other - TechnicalFile: form 2-enginer-2025.pdf22 May 2025
Other - TechnicalFile: form 1-architech-24-25.pdf22 May 2025
Other - TechnicalFile: form 2A-24-25-bluemoon.pdf22 May 2025
Layout approvalFile: GRD FLR-compressed.pdf15 Apr 2025
Layout approvalFile: 1ST FLR.pdf15 Apr 2025
Layout approvalFile: 2ND FLR-compressed.pdf15 Apr 2025
Copy of Layout Approval (in case of layout)File: GRD FLR-compressed.pdf15 Apr 2025
Copy of Layout Approval (in case of layout)File: 1ST FLR.pdf15 Apr 2025
Copy of Layout Approval (in case of layout)File: 2ND FLR-compressed.pdf15 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD LIST.pdf7 Apr 2025
Declaration about Commencement CertificateFile: FORMAT D-.pdf7 Apr 2025
Other - TechnicalFile: BUYERS CONSENT-BLUEMOON_page-0001.pdf7 Apr 2025
Other - TechnicalFile: FORM E.pdf7 Apr 2025
Other - LegalFile: BUYERS CONSENT-BLUEMOON.pdf26 Feb 2025
Other - LegalFile: REASON LETTER-BLUEMOON.pdf26 Feb 2025
Other - LegalFile: BUYERS CONSENT-.pdf26 Feb 2025
Other - FinanceFile: PERT CAHRT-B WING.pdf26 Feb 2025
Other - FinanceFile: PERT CAHRT-C WING.pdf26 Feb 2025
Declaration in FORM BFile: FORM_B_2025.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD-2024.pdf24 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-23-24.pdf24 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A-23-24-bluemoon.pdf21 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: blue_moon_CC_compressed.pdf8 Jul 2024
Building plan approvalFile: 11zon_JPEG-to-PDF (7).pdf2 May 2024
Building Plan Approval (IOD)File: 11zon_JPEG-to-PDF (7).pdf2 May 2024
Layout approvalFile: Scan 30 04 2024_11zon.pdf30 Apr 2024
Copy of Layout Approval (in case of layout)File: Scan 30 04 2024_11zon.pdf30 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1-architech-signed.pdf23 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2-enginer-signed.pdf23 Feb 2024
Certificates of CA (Form 3)File: FORM 3-CA-NEW.pdf23 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: LH1.pdf23 Feb 2024
CERSAI detailsFile: Rera_letter_Mudassar builder.pdf31 Jan 2024
Disclosure of sold/ booked inventoryFile: soldunsold list-bluemoon.pdf31 Jan 2024
Declaration in FORM BFile: FORM B-2024.pdf23 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A-22-23-bluemoon.pdf23 Jan 2024
CERSAI detailsFile: letter to RERA.pdf23 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A PARTNERS.pdf23 Jan 2024
Proforma of Agreement for saleFile: SALE AGREEMENT_compressed.pdf23 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A BANK DECLARATION.pdf23 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A-22-23-bluemoon.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD LIST.pdf18 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM_5_2022.pdf30 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A-21-22-bluemoon.pdf29 Mar 2023
Declaration about Commencement CertificateFile: FORMAT D.pdf7 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Mudassar_Builder_RERA_ Supervisor letter (1)-6.pdf18 Aug 2021
Disclosure of sold/ booked inventoryFile: LIST OF SOLD-UNSOLD.pdf18 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM_5_2021_compressed (1).pdf18 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY ASSUANCE CERTIFICATE.pdf23 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSUANCE CERTIFICATE.pdf23 Jun 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLF FLAT INVENTORY.pdf23 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM_5_2018_compressed.pdf23 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM_5_2019_compressed.pdf23 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM_5_2020_compressed.pdf23 Jun 2021
Layout approvalFile: Doc1.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Doc1.pdf28 Jul 2017
Declaration in FORM BFile: Form_B.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_1_-min-min.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form_2.pdf28 Jul 2017
Certificates of CA (Form 3)File: 1_4_files_merged_.pdf28 Jul 2017
Details of encumbrancesFile: letter - mudassar2.pdf25 Jul 2017
Building plan approvalFile: IOD_-_Mudassar.pdf24 Jul 2017
Building Plan Approval (IOD)File: IOD_-_Mudassar.pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: C_C_-_Mudassar.pdf24 Jul 2017
Proforma of Allotment letterFile: Allotment letter.pdf24 Jul 2017
Proforma of Allotment letterFile: Sale agreement_.pdf24 Jul 2017
PAN CardFile: PAN CARD - Mudassar.pdf21 Jul 2017
Copy of the legal title reportFile: title certificate - Mudassar-ilovepdf-compressed.pdf21 Jul 2017

How this compares with Mumbai Suburban

11%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 87 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Bluemoon Annexe on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kalina6,700+ in Mumbai Suburban

2 kmBluemoon AnnexeCompleted 130Lapsed / revoked 73Other 138Dot size: filed unitsN

Filed coordinates, straight-line distance. 341 registered projects within 2 km.

Builder: MUDASSAR BUILDERS & DEVELOPERS

MUDASSAR BUILDERS & DEVELOPERS has 1 registration on MahaRERA, including Bluemoon Annexe. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Bluemoon Annexe shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Bluemoon Annexe is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Bluemoon Annexe?

The registered promoter entity is MUDASSAR BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Bluemoon Annexe?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Bluemoon Annexe?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Bluemoon Annexe?

The professionals named in the filing: Architect: PRAVIN JAGANNATH NAIK; Chartered Accountant: I N SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Bluemoon Annexe?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Bluemoon Annexe. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Bluemoon Annexe to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.