Home / Browse projects / Pune, Maharashtra / UTOPIA GOLD

Registered No litigation declared Others project

UTOPIA GOLD

By AKSHAY DEEPAK PANJABI

RG-MH-23139 · RERA P52100033254 · Last updated on MahaRERA portal: 17 Jul 2026

Source: official MahaRERA filing

Red flags

  • 42 complaints at MahaRERA
  • Completion date moved by 12 months
  • 2 extensions taken
  • Rs 45.00 crore secured on the land, in favour of CAPRI GLOBAL CAPITAL
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
28 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 85%
83 of 544Units unsoldnot recorded sold or booked
42Complaints at MahaRERAon this registration
Jump to the 215 documents Report an error

UTOPIA GOLD is a Others project by AKSHAY DEEPAK PANJABI in Pune, Maharashtra, registered with MahaRERA as P52100033254 on 9 Feb 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 461 of the 544 units on this registration are recorded sold or booked, and 28 of 44 construction stages are filed complete. 42 complaints are on record with the regulator.

At a glance

Project

  • NameUTOPIA GOLD
  • TypeOthers
  • Location
    • BORHADEWADI MOSHI PUNE
    • Moshi
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100033254
  • ReraGenie IDRG-MH-23139

Builder

  • NameAKSHAY DEEPAK PANJABI
  • Entity typeIndividual

Key dates

this monthRegisteredFeb 2022First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Feb 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings4 building records
  • Documents filed215 files

Current status

85%461 of 544 units booked
78.2%Work done, per cost certificate

Figures as on 17 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
UTOPIA GOLD - TOWER ANA24181512153
UTOPIA GOLD - TOWER BNA241812610136
UTOPIA GOLD - TOWER CNA231812610136
UTOPIA GOLD - TOWER DNA23181109119

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

28 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 85%.

UTOPIA GOLD - TOWER A54%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%
UTOPIA GOLD - TOWER B58%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%
UTOPIA GOLD - TOWER C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
UTOPIA GOLD - TOWER D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes20%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1276

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,276
Closed/Covered520
Open Space756
BuildingClosed/CoveredOpen SpaceTotal
UTOPIA GOLD - TOWER A159216375
UTOPIA GOLD - TOWER B125195320
UTOPIA GOLD - TOWER C125194319
UTOPIA GOLD - TOWER D111151262

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area7,457 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofCAPRI GLOBAL CAPITAL
Secured amountRs 45.00 crore
CERSAI search filedYes
Declared on11 Jul 2025

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNICIPAL CORPORATION
Permissible FSI52959.26
Proposed, not sanctioned43,703 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGRD AND MEZZANINE FLR P W D 24 9 10 NR ASHOK THEATRE SHASTRI GARDEN PIMPRI PUNE MAHARASHTRA 411017
Estimated costRs 123.52 cr
Cost incurredRs 96.54 cr
Work done78.16%
BuildingWingEstimatedIncurred
UTOPIA GOLD - TOWER ANARs 30.82 crRs 22.17 cr
UTOPIA GOLD - TOWER BNARs 30.82 crRs 22.17 cr
UTOPIA GOLD - TOWER CNARs 30.82 crRs 26.03 cr
UTOPIA GOLD - TOWER DNARs 30.82 crRs 26.03 cr
-NARs 24.70 lakhRs 15.00 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDREAM SPACE ARCHITECTURES
EngineerPRASHANT KULKARNI
EngineerSARANG PATIL
EngineerVishal Janardan Patil
EngineerISMAIL HASAAN SAB
EngineerRAMBHAU GORAKH SONAWANE
Chartered AccountantPGMJ AND ASSOCIATES
Chartered AccountantNITISH VAIDYA & ASSOCIATES
PartnerRole in project
AKSHAY DEEPAK PANJABI-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA07112518258Dec 2025 → Jun 2026

Reason as filed by the promoterThe progress of our project was unavoidably delayed Due to heavy rainfall, a large amount of water got accumulated in the project basement. This caused delays in construction and finishing work as dewatering and drying took extra time to make the area safe for further work. We request an extension of the project completion period due to this unavoidable situation.

EA23052621071Dec 2025 → Dec 2026

Reason as filed by the promoterThe progress of our project was unavoidably delayed Due to heavy rainfall, a large amount of water got accumulated in the project basement. This caused delays in construction and finishing work as dewatering and drying took extra time to make the area safe for further work. We request an extension of the project completion period due to this unavoidable situation.

Complaints filed with MahaRERA42

Case no.ComplainantRespondentFiled
CC12604871SHUBHAM VITTHALRAO GAIKWADAKSHAY DEEPAK PANJABI02/08/2026
CC12604870VENKATASHIVIAH GAKSHAY DEEPAK PANJABI02/08/2026
CC12604874HEMANTKUMAR YASHWANT PARDHIAKSHAY DEEPAK PANJABI02/08/2026
CC12604868SANDEEP SUNIL PISEAKSHAY DEEPAK PANJABI02/08/2026
CC12604881SANYAM NANDKISHOR KHARCHEAKSHAY DEEPAK PANJABI02/08/2026
CC12604883DEVENDRA BHANGALEAKSHAY DEEPAK PANJABI02/08/2026
CC12604884ANIL ANNARAY JATTIAKSHAY DEEPAK PANJABI02/08/2026
CC12604875ATUL SHRIKRUSHNA CHOPADEAKSHAY DEEPAK PANJABI02/08/2026
CC12604879MUKESH LAXMAN PATILAKSHAY DEEPAK PANJABI02/08/2026
CC12604889MALLIKARJUN SajjanAKSHAY DEEPAK PANJABI02/08/2026
CC12604893PRITAM RAMESH CHAVANAKSHAY DEEPAK PANJABI02/08/2026
CC12604894VISHAL BASAVARAJAKSHAY DEEPAK PANJABI02/08/2026
CC12604908TUSHAR SATISH ROKADEAKSHAY DEEPAK PANJABI03/08/2026
CC12604911NIKHIL RAJENDRA FOLANEAKSHAY DEEPAK PANJABI03/08/2026
CC12604920PRAVIN AAPASAHEB MOREAKSHAY DEEPAK PANJABI03/08/2026
CC12604916HARSHAD UTTAMRAO CHAPTEAKSHAY DEEPAK PANJABI03/08/2026
CC12604977AKSHAYKUMAR BHAUSAHEB WALEAKSHAY DEEPAK PANJABI05/08/2026
CC12604913RAHUL ASHOK TANPUREAKSHAY DEEPAK PANJABI03/08/2026
CC12604917NILESH SUDHAKAR THORAKSHAY DEEPAK PANJABI03/08/2026
CC12604936VIKAS KUMARAKSHAY DEEPAK PANJABI04/08/2026
CC12604934APURV MISHRAAKSHAY DEEPAK PANJABI04/08/2026
CC12604933BALAJI GANAPATIAKSHAY DEEPAK PANJABI04/08/2026
CC12604886GANESH MALLAPPA GUGRIAKSHAY DEEPAK PANJABI02/08/2026
CC12604906CHETAN CHINTAMAN CHAVHANAKSHAY DEEPAK PANJABI03/08/2026
CC12604907MAYURESHWAR RAMESHWAR KUMBHARAKSHAY DEEPAK PANJABI03/08/2026
CC12604918PRANAY RAMDAS KOHALEAKSHAY DEEPAK PANJABI03/08/2026
CC12604953SHRIKANT SHIVAJI MADANEAKSHAY DEEPAK PANJABI05/08/2026
CC12604954SHRINIVAS SHIVAJI MADANEAKSHAY DEEPAK PANJABI05/08/2026
CC12604978JITENDRA CHAVHANAKSHAY DEEPAK PANJABI05/08/2026
CC12604972KISHOR SOMNATH SABLEAKSHAY DEEPAK PANJABI05/08/2026
CC12604955TANAJI SHIVAJI SHINDEAKSHAY DEEPAK PANJABI05/08/2026
CC12604949RAJKUMAR BASWARAJ BAWAGEAKSHAY DEEPAK PANJABI04/08/2026
CC12604948SANKET VIKAS FIRKEAKSHAY DEEPAK PANJABI04/08/2026
CC12604974PRAMOD BALASO WABLEAKSHAY DEEPAK PANJABI05/08/2026
CC12604989NIKHIL ARVIND BANGALIAKSHAY DEEPAK PANJABI06/08/2026
CC12604990MAHESH PANDITRAO PAITHANEAKSHAY DEEPAK PANJABI06/08/2026
CC12604991SANTOSH NAMDEO SHINDEAKSHAY DEEPAK PANJABI06/08/2026
CC12604994DEVESHREE KIRAN KOLHEAKSHAY DEEPAK PANJABI06/08/2026
CC12604996JACKSON SALWADOR MARTISAKSHAY DEEPAK PANJABI06/08/2026
CC12605012PRAVIN BALAJI DATALAKSHAY DEEPAK PANJABI06/08/2026
CC12605061AMITKUMAR MOHAN KOSHTIAKSHAY DEEPAK PANJABI08/08/2026
CC12605057SANKET POPAT WABLEAKSHAY DEEPAK PANJABI08/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Apr 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed215

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 215 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf17 Jul 2026
Withdrawal Update Form 2File: FORM 2 signed.pdf17 Jul 2026
Withdrawal Update Form 3File: Form 3 Final.pdf17 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf24 Apr 2026
Layout approvalFile: Layout.pdf11 Apr 2026
Building plan approvalFile: Building Plan 1.pdf11 Apr 2026
Building plan approvalFile: Building Plan 2.pdf11 Apr 2026
Building plan approvalFile: Building Plan 3.pdf11 Apr 2026
Building plan approvalFile: Building Plan 4.pdf11 Apr 2026
Building plan approvalFile: Building Plan 5.pdf11 Apr 2026
Building plan approvalFile: Building Plan 6.pdf11 Apr 2026
Building plan approvalFile: Building Plan 7.pdf11 Apr 2026
Building plan approvalFile: Building Plan 8.pdf11 Apr 2026
Building plan approvalFile: Building Plan 9.pdf11 Apr 2026
Building plan approvalFile: Building Plan 10.pdf11 Apr 2026
Building plan approvalFile: Building Plan 11.pdf11 Apr 2026
Building plan approvalFile: Building Plan 12.pdf11 Apr 2026
Building plan approvalFile: Building Plan 13.pdf11 Apr 2026
Building plan approvalFile: Building Plan 14.pdf11 Apr 2026
Building plan approvalFile: Building Plan 16.pdf11 Apr 2026
Commencement certificateFile: Commencement Certificate.pdf11 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf11 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf11 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf11 Apr 2026
Layout approvalFile: Layout.pdf16 Feb 2026
Building plan approvalFile: Building Plan 1.pdf16 Feb 2026
Building plan approvalFile: Building Plan 2.pdf16 Feb 2026
Building plan approvalFile: Building Plan 3.pdf16 Feb 2026
Building plan approvalFile: Building Plan 4.pdf16 Feb 2026
Building plan approvalFile: Building Plan 5.pdf16 Feb 2026
Building plan approvalFile: Building Plan 6.pdf16 Feb 2026
Building plan approvalFile: Building Plan 7.pdf16 Feb 2026
Building plan approvalFile: Building Plan 8.pdf16 Feb 2026
Building plan approvalFile: Building Plan 9.pdf16 Feb 2026
Building plan approvalFile: Building Plan 10.pdf16 Feb 2026
Building plan approvalFile: Building Plan 11.pdf16 Feb 2026
Building plan approvalFile: Building Plan 12.pdf16 Feb 2026
Building plan approvalFile: Building Plan 13.pdf16 Feb 2026
Building plan approvalFile: Building Plan 14.pdf16 Feb 2026
Building plan approvalFile: Building Plan 15.pdf16 Feb 2026
Building plan approvalFile: Building Plan 16.pdf16 Feb 2026
Building plan approvalFile: Building Plan.pdf16 Feb 2026
Withdrawal Update Form 1File: Form 1 Final.pdf14 Jan 2026
Withdrawal Update Form 2File: Form 2 Final.pdf14 Jan 2026
Withdrawal Update Form 3File: Form 3 Final.pdf14 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 Final.pdf14 Nov 2025
Form 2A (FY 2024-2025)File: Form 2A Final.pdf7 Nov 2025
Withdrawal Update Form 1File: Form1.pdf11 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf11 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf11 Oct 2025
Withdrawal Update Form 1File: Form1.pdf9 Oct 2025
Withdrawal Update Form 2File: Form2.pdf9 Oct 2025
Withdrawal Update Form 3File: Form3.pdf9 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf19 Jul 2025
Form 2File: Form 2.pdf19 Jul 2025
Form 3File: Form 3 Final_compressed.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf30 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final_compressed.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf30 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf30 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final_compressed.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Final.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Circular Final_compressed.pdf18 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Upload_.pdf24 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Upload_compressed.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Upload.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold_compressed.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Upload_compressed.pdf23 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 ( april to June 2024).pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: disclosure of sold inventories.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Upload.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 upload.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: sold inventories.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Upload File_11zon.pdf20 Apr 2024
Building plan approvalFile: A WING 1-18 ALL FLOOR PLAN.pdf26 Mar 2024
Building plan approvalFile: A WING TERRACE FLOOR.pdf26 Mar 2024

How this compares with Pune

85%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep UTOPIA GOLD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORHADEWADI MOSHI PUNE13,700+ in Pune

2 kmUTOPIA GOLDCompleted 84Lapsed / revoked 50Other 89Dot size: filed unitsN

Filed coordinates, straight-line distance. 223 registered projects within 2 km.

Builder: AKSHAY DEEPAK PANJABI

AKSHAY DEEPAK PANJABI has 1 registration on MahaRERA, including UTOPIA GOLD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if UTOPIA GOLD is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UTOPIA GOLD?

The registered promoter entity is AKSHAY DEEPAK PANJABI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UTOPIA GOLD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against UTOPIA GOLD?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for UTOPIA GOLD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UTOPIA GOLD?

The professionals named in the filing: Architect: DREAM SPACE ARCHITECTURES; Engineer: PRASHANT KULKARNI; Engineer: SARANG PATIL; Engineer: Vishal Janardan Patil; Engineer: ISMAIL HASAAN SAB; Engineer: RAMBHAU GORAKH SONAWANE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UTOPIA GOLD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UTOPIA GOLD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UTOPIA GOLD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.