Urbanlife plotting
RG-MH-14660 · RERA P52100023117 · Last updated on MahaRERA portal: 25 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 52 months past the filed date
- 3 complaints at MahaRERA
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Urbanlife plotting is a Plotted project by Kakade Vtp Associates in Pune, Maharashtra, registered with MahaRERA as P52100023117 on 2 Dec 2019. Possession was promised by 30 Jun 2022 and is now 52 months past that date. The completion date has moved by 18 months from the original filing. 0 of the 41 units on this registration are recorded sold or booked. 3 complaints are on record with the regulator.
At a glance
Project
- NameUrbanlife plotting
- TypePlotted
- Location
- midc road
- talegaon
- Katavi
- Mawal
- Pune
- 410507
- Pincode410507
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100023117
- ReraGenie IDRG-MH-14660
Builder
- NameKakade Vtp Associates
- Entity typePartnership
- PartnerNilesh Vilas Palresha
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 Dec 2019
- Promised completion30 Jun 2022
- Revised completionRevised to 30 Jun 2022 (originally 30 Dec 2020)
- BuildingsNot stated in filing
- Documents filed44 files
Current status
Figures as on 25 Nov 2024, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 25 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Purnanad Co operative Housing Society | - | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Reza Kabul |
| Engineer | Yogesh Dhapre |
| Chartered Accountant | Kailash agarwal |
| Partner | Role in project |
|---|---|
| Kakade Vtp Associates | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to change in sanction authority from PMRDA TO NAGARPANCHAYAT
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000096094 | KRISHNAPRASAD NAIR | anil balasaheb kakade | 14/12/2021 |
| CC12502994 | Kakade Vtp Associates | SNEHALATA BABASAHEB THORAT | 25/08/2025 |
| CC12502993 | Kakade Vtp Associates | GAJANAN DIGAMBER NARANGALE | 25/08/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Nov 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Dec 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Nov 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Nov 2024
Documents filed44
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Urbanlife Plotting_7-12 extracts.pdf | 25 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Urbanlife Plotting.pdf | 24 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: URBAN LIFE PLOTTING 30062024.pdf | 16 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Urban Life Plotting 31032024.pdf | 18 May 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY 31032022.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY 30062022.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY 30092022.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY 31122022.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY 31032023.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY 30062023.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY 30092023.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY 31122023.pdf | 30 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 URBANLIFE PLOTTING 30062022.pdf | 30 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 URBANLIFE PLOTTING 2022-23.pdf | 19 Oct 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: NA order.pdf | 5 Jul 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ME-2123.pdf | 5 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Katvi NA order dtd 05-07-2014.pdf | 4 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Mutation Entry No2123_compressed.pdf | 4 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kakade Ploting 21-22.pdf | 25 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5- Ploting SIGNED_compressed (1).pdf | 25 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032020.pdf | 20 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032021.pdf | 20 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5-19 20.pdf | 20 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20 21.pdf | 20 Mar 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4.pdf | 29 Nov 2022 |
| CERSAI detailsFile: Urban Life Phase 1.pdf | 19 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Urban life plotting.pdf | 15 Feb 2022 |
| Layout approvalFile: Urban Life compressed.pdf | 14 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: Urban Life compressed.pdf | 14 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 14 Dec 2021 |
| Declaration about Commencement CertificateFile: Urban Life plotting.pdf | 14 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: Urban Life Plotting.pdf | 14 Dec 2021 |
| Proforma of Allotment letterFile: Allotment Letter urban life.pdf | 28 Nov 2019 |
| Building plan approval or NA orderFile: URBAN LIFE LAYOUT1.pdf | 14 Nov 2019 |
| Layout approvalFile: URBAN LIFE LAYOUT1.pdf | 14 Nov 2019 |
| PAN CardFile: PAN CARD.pdf | 14 Nov 2019 |
| Copy of the legal title reportFile: TITLE REPORT.pdf | 14 Nov 2019 |
| Details of encumbrancesFile: Encumbrance_-_Life.pdf | 14 Nov 2019 |
| Copy of Layout Approval (in case of layout)File: URBAN LIFE LAYOUT1.pdf | 14 Nov 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: URBAN LIFE LAYOUT1.pdf | 14 Nov 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate,.pdf | 14 Nov 2019 |
| Declaration in FORM BFile: BHUSHAN SIR FORM B.pdf | 14 Nov 2019 |
| Proforma of Allotment letterFile: Urban Life plot draft.pdf | 14 Nov 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 5 Nov 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 44 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Urbanlife plotting on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near talegaon13,700+ in Pune
Filed coordinates, straight-line distance. 268 registered projects within 2 km.
ANANDAM PHASE I
A V BHAT DEVELOPERS LLP
Ashiana Amodh Phase I
Ashiana Housing Limited
Ashiana Amodh Phase 3
Ashiana Housing Limited
HAPPYCITY VARALE
NAMRATA DEVELOPERS PRIVATE LIMITED
Namrata Sarvam
NAMRATA KHANDGE VENTURES
PLATINUM ELITE
Sugat Properties
Builder: Kakade Vtp Associates
Kakade Vtp Associates has 2 registrations on MahaRERA, including Urban Life Phase 1 and Urbanlife plotting. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Urbanlife plotting shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Urbanlife plotting is delayed beyond 30 Jun 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Urbanlife plotting?
The registered promoter entity is Kakade Vtp Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Urbanlife plotting?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Urbanlife plotting?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Urbanlife plotting?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Urbanlife plotting?
The professionals named in the filing: Architect: Reza Kabul; Engineer: Yogesh Dhapre; Chartered Accountant: Kailash agarwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Urbanlife plotting?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.