Red flags

  • Completion date moved by 66 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2031Possession promisedmoved 66 months from the original
0 of 11Construction stages donefurthest along: Excavation, 0%
16 of 26Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 95 documents Report an error

Urban Waterfront is a Residential / Group Housing project by HAREKRUSHNA DEVELOPERS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800026251 on 2 Sep 2020. Possession is promised by 31 Dec 2031. The completion date has moved by 66 months from the original filing. 10 of the 26 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameUrban Waterfront
  • TypeResidential / Group Housing
  • Location
    • Bandra west
    • Andheri
    • Mumbai Suburban
    • 400050
  • Pincode400050
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800026251
  • ReraGenie IDRG-MH-28498

Builder

  • NameHAREKRUSHNA DEVELOPERS LLP
  • Entity typePartnership
  • PartnersPraveen Awate, Vihaan Doshi, Indraneel Roy, Jai Nagwani
  • Other registrations1 more →

Key dates

this monthRegisteredSep 2020First promiseJun 2026Revised toDec 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Sep 2020
  • Promised completion31 Dec 2031
  • Revised completionRevised to 31 Dec 2031 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed95 files

Current status

38%10 of 26 units booked
5.2%Work done, per cost certificate

Figures as on 5 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Urban WaterfrontNA272726026

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

Urban Waterfront: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,910 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Jun 2025

Approvals and building plan

Sanctioning authoritySRA
Permissible FSI10992.98
Proposed, not sanctioned10,993 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch386, Veer Savarkar Marg, opp siddhivinayak temple, Prabhadevi mumbai maharashtra 400025
Estimated costRs 439.00 cr
Cost incurredRs 22.76 cr
Work done5.18%
BuildingWingEstimatedIncurred
Urban WaterfrontNARs 298.00 crRs 22.76 cr
-NARs 141.00 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSet Square
EngineerJW Consultants LLP
EngineerMANOJ KRIPLANI
Chartered AccountantC K Patil
Chartered AccountantCHIRAG DOSHI
PartnerRole in project
HAREKRUSHNA DEVELOPERS LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA25062501732Jun 2026 → Dec 2031

Reason as filed by the promoterI, Mr. Indraneel Roy, duly authorised by HAREKRUSHNA DEVELOPERS LLP, Promoter of the project Urban Waterfront registered with MahaRERA under project registration number - P51800026251 (hereinafter referred to as the said project), here by state that the project registration validity of the said project is due to expire post June 30, 2026. I state that the completion work of the said project has been delayed due to certain mitigating circumstances beyond the control of the Promoter. I further state that the promoter of the said project is desirous of completing the balance project completion wo

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2031

Documents filed95

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Engi Certificate Waterfront Rera Form 2A.pdf5 Aug 2026
Withdrawal Update Form 1File: Ar Certificate Waterfront Rera.pdf23 Jul 2026
Withdrawal Update Form 2File: Engi Certificate Waterfront Rera.pdf23 Jul 2026
Withdrawal Update Form 3File: CA Certificate Waterfront.pdf23 Jul 2026
Withdrawal Update Form 1File: Ar Certificate Waterfront Rera.pdf24 Apr 2026
Withdrawal Update Form 2File: Engi Certificate Waterfront Rera.pdf24 Apr 2026
Withdrawal Update Form 3File: CA Certificate Waterfront.pdf24 Apr 2026
Withdrawal Update Form 1File: Ar Certificate Waterfront Rera.pdf9 Mar 2026
Withdrawal Update Form 2File: Engi Certificate Waterfront Rera.pdf9 Mar 2026
Withdrawal Update Form 3File: CA Certificate Waterfront.pdf9 Mar 2026
Withdrawal Update Form 1File: Ar Certificate Waterfront Rera.pdf15 Dec 2025
Withdrawal Update Form 1File: form 1 waterfront sept 25.pdf15 Dec 2025
Withdrawal Update Form 2File: form 2 waterfront june 25.pdf15 Dec 2025
Withdrawal Update Form 2File: form 2 waterfront sept 25.pdf15 Dec 2025
Withdrawal Update Form 3File: form 3 waterfront june 25.pdf15 Dec 2025
Withdrawal Update Form 3File: CA Certificate Waterfront sept 25.pdf15 Dec 2025
Form 5 (FY 2024-2025)File: CA Form 5 Water Front 24 25.pdf15 Dec 2025
Form 1File: Ar Certificate Waterfront Rera.pdf25 Jun 2025
Form 2File: Engi Certificate Waterfront Rera.pdf25 Jun 2025
Form 3File: CA Certificate Waterfront.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Waterfront Rera.pdf25 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate Waves Rera.pdf16 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Waterfront Rera.pdf16 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Waterfront Rera.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Certificate Waterfront Rera.pdf16 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure Waterfront Rera.pdf16 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf10 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure Waterfront Rera.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FOrm 3.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FOrm 3.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf10 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure Waterfront Rera.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate Waterfront Rera.pdf23 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Certificate Waterfront Rera.pdf23 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Waterfront Rera.pdf23 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Waterfront Rera.pdf23 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate Water Front Rera.pdf23 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Certificate Water Front Rera.pdf23 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Water Front Rera.pdf23 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Form 1 Waterfront.pdf22 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Form 2 Waterfront.pdf22 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Waterfront Rera.pdf22 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form - 1 Waterfront.pdf21 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Form 2 Waterfront s.pdf21 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form - 3 Waterfront_compressed.pdf21 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold unsold waterfront March 31 2023.pdf25 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 dec 30 2022.pdf9 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 front 30 dec 2022.pdf9 Feb 2023
Disclosure of sold/ booked inventoryFile: sold front dec 30 2022.pdf9 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 front dec 30 2022_compressed.pdf9 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 front dec 30 2022_compressed.pdf9 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2022_URBAN WATERFRONT.pdf9 Feb 2023
Declaration about Commencement CertificateFile: CC DEc.pdf20 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 water front.pdf20 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Waterfront.pdf20 Sep 2022
CERSAI detailsFile: CERSAI_Search_Report_200247002961_For_Asset_Based_Search_13_09_2022_16_16_35_320.pdf20 Sep 2022
Disclosure of sold/ booked inventoryFile: WATERFRONT SOLD .pdf20 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Scan 18-Feb-2022.pdf2 Mar 2022
Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf15 Feb 2022
Copy of the legal title reportFile: FLOW OF TITLE.pdf15 Feb 2022
Copy of the legal title reportFile: declaration title.pdf27 Aug 2020
Building plan approvalFile: ioa scan-1.pdf19 Aug 2020
Building plan approvalFile: ioa scan-2_compressed.pdf19 Aug 2020
Building plan approvalFile: ioa scan-3.pdf19 Aug 2020
Building plan approvalFile: ioa scan-4.pdf19 Aug 2020
Building plan approvalFile: ioa scan-5.pdf19 Aug 2020
Layout approvalFile: LAYOUT PLAN.pdf19 Aug 2020
Building plan approvalFile: LAYOUT PLAN.pdf19 Aug 2020
PAN CardFile: HARE KRUSHNA DEVELOPERS LLP PAN CARD.pdf19 Aug 2020
Details of encumbrancesFile: Urban Water Front DECLARATION.pdf19 Aug 2020
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf19 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: LAYOUT PLAN.pdf19 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: ioa scan-1.pdf19 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: ioa scan-2_compressed.pdf19 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: ioa scan-3.pdf19 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: ioa scan-4.pdf19 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: ioa scan-5.pdf19 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: 1.pdf19 Aug 2020

How this compares with Mumbai Suburban

38%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 66 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Urban Waterfront on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near bandra West6,700+ in Mumbai Suburban

2 kmUrban WaterfrontCompleted 43Lapsed / revoked 14Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 73 registered projects within 2 km.

Builder: HAREKRUSHNA DEVELOPERS LLP

HAREKRUSHNA DEVELOPERS LLP has 2 registrations on MahaRERA, including URBAN WAVES and Urban Waterfront. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Urban Waterfront is delayed beyond 31 Dec 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Urban Waterfront?

The registered promoter entity is HAREKRUSHNA DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Urban Waterfront?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Urban Waterfront?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Urban Waterfront?

The professionals named in the filing: Architect: Set Square; Engineer: JW Consultants LLP; Engineer: MANOJ KRIPLANI; Chartered Accountant: C K Patil; Chartered Accountant: CHIRAG DOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Urban Waterfront?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Urban Waterfront. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Urban Waterfront to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.