Registration lapsed No litigation declared Residential / Group Housing project

URBAN Villa

By YASH INFRA

RG-MH-58315 · RERA P51700015488 · Last updated on MahaRERA portal: 20 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 3 months past the filed date
  • Completion date moved by 43 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jul 2026Possession promised3 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
17 of 78Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 108 documents Report an error

URBAN Villa is a Residential / Group Housing project by YASH INFRA in Thane, Maharashtra, registered with MahaRERA as P51700015488 on 1 Mar 2018. Possession was promised by 30 Jul 2026 and is now 3 months past that date. The completion date has moved by 43 months from the original filing. 61 of the 78 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameURBAN Villa
  • TypeResidential / Group Housing
  • Location
    • Pipe Line Road
    • Louisewadi
    • Thane (M Corp.)
    • Thane
    • 400604
  • Pincode400604
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700015488
  • ReraGenie IDRG-MH-58315

Builder

  • NameYASH INFRA
  • Entity typePartnership
  • PartnerTINA BHUSHAN BHANUSHALI
  • Other registrations11 more →
  • Completed2 of 12
  • No longer live5 lapsed, de-registered or revoked
  • Declared earlier projects9 →

Key dates

3 months past promisethis monthRegisteredMar 2018First promiseDec 2022Revised toJul 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Mar 2018
  • Promised completion30 Jul 2026
  • Revised completionRevised to 30 Jul 2026 (originally 15 Dec 2022)
  • Buildings1 building record
  • Documents filed108 files

Current status

78%61 of 78 units booked
91.8%Work done, per cost certificate

Figures as on 20 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Urban VillaNA171678078

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Urban Villa: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed86

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots86
Closed/Covered86

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,751 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Sai ConstructionThane (M Corp.)Thane
Bhushan BhanushaliThane (M Corp.)Thane
Tina Bhushan BhanushaliThane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI3239.32
Proposed, not sanctioned1,562 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 3 and 4 Ratna Umed Residency, Louisewadi,Thane W-400604
Estimated costRs 20.34 cr
Cost incurredRs 18.67 cr
Work done91.77%
BuildingWingEstimatedIncurred
Urban VillaNARs 16.74 crRs 16.74 cr
-NARs 3.60 crRs 1.93 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectInnovativeArchitech
EngineerPentacon Structural Consultants Pvt. Ltd.
Chartered AccountantAditi A Joshi & Co
PartnerRole in project
YASH INFRA-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018116Dec 2022 → Dec 2024

Reason as filed by the promoterWE REQUEST YOU TO EXTENT THE RERA DATE AS THE PROJECT IS GETTING EXTENDED DUE TO TOWER PARKING. THE TOWER PARKING HEIGHT WILL BE ABOVE 45 METERS, THE TIME FOR TOWER PARKING IS 8 TO 10 MONTHS. REST ALL THE WORK OF THE BUILDING IS COMPLETED.

EXT51700013597Dec 2022 → Dec 2023

Reason as filed by the promoterDUE TO COVID PANDEMIC THE PROJECT WAS DELAYED.

EXT51700027249Dec 2022 → Dec 2025

Reason as filed by the promoterWE HAVE COMPLETED THE PROJECT AND WE APPLIED FOR OC ON 3/12/2024 FOR URBAN VILLA PROJECT AND OUR RERA GOT EXPIRED ON 15/12/2024 .SO WE HAVE APPLIED FOR EXTENSION FOR RERA SO WE ARE REQUESTING YOU TO EXTEND THE RERA. THE OC PROCESS IS GOING ON IN TMC AND ONCE WE GET OC WE SHALL UPDATE RERA ACCORDINGLY SO KINDLY RENEW THE RERA .

EA20012619507Dec 2022 → Jul 2026

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The project has been delayed due to delay in Parking work. The parking work could not be completed within the stipulated timeline due to an unforeseen and unavoidable circumstance. The contractor originally appointed for the parking work unfortunately demised while the project was in progress. Consequently, the work had to be discontinued and reassigned to a new contractor. Additional time was required for the appointment, mobilization, and resumption of work by the new contractor. Due to this unexp

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed108

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: from1 URBAN VILLA Jun 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 Sep 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: FROM-1 DEC 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM 2 URBAN VILLA 30-06-2025.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM 2 Sep 25.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 Dec 25.pdf20 Jan 2026
Withdrawal Update Form 3File: FORM 3 URBAN VILLA 30-06-2025.pdf20 Jan 2026
Withdrawal Update Form 3File: FORM 3 Sep 25.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: FORM 1 QTR 4-sign.pdf12 Jan 2026
Withdrawal Update Form 1File: FORM 1 QTR 4-sign.pdf12 Jan 2026
Withdrawal Update Form 2File: FORM 2 URBAN VILLA 30-06-2025.pdf12 Jan 2026
Withdrawal Update Form 2File: FORM 2 URBAN VILLA 30-06-2025.pdf12 Jan 2026
Withdrawal Update Form 3File: FORM 3 URBAN VILLA 30-06-2025.pdf12 Jan 2026
Withdrawal Update Form 3File: FORM 3 URBAN VILLA 30-06-2025.pdf12 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: QTR -4 FORM-1 URBAN VILLA.pdf9 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: QTR-4 FORM -2 URBAN VILLA.pdf9 May 2025
Declaration in FORM BFile: Extention Form B - Urban Villa.pdf15 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A URBAN VILLA.pdf10 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A URBAN VILLA.pdf10 Mar 2025
Declaration in FORM BFile: Extention Form B - Urban Villa.pdf5 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Urban Villa - From 1 -.pdf5 Mar 2025
Certificates of CA (Form 3)File: Urban villa Form-3.pdf5 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - Urban Villa.pdf5 Mar 2025
Certificates of CA (Form 5)File: URBAN VILLA -ANNUAL REPORT ON STATMENT OF ACCOUNT.pdf22 Feb 2025
Certificates of CA (Form 5)File: URBAN VILLA -ANNUAL REPORT ON STATMENT OF ACCOUNT 1.pdf22 Feb 2025
Certificates of CA (Form 5)File: URBAN VILLA -ANNUAL REPORT ON STATMENT OF ACCOUNT 1.pdf22 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: URBAN VILLA -ANNUAL REPORT ON STATMENT OF ACCOUNT 1.pdf22 Feb 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: URBAN VILLA FORMAT A yash infra.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 QTR 3- sign.pdf29 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 QTR 4-sign.pdf29 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 QTR-3.pdf29 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 - QTR-4.pdf29 Jun 2024
Certificates of CA (Form 3)File: form 3 - yash infra -2023.pdf29 Jun 2024
Certificates of CA (Form 3)File: form 3 - yash infra -2024.pdf29 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 2- ENGINEER'S CERTIFICATE for Annx B_Compressed.pdf4 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf4 Dec 2023
Certificates of CA (Form 3)File: FORM 3- URBAN VILLA - Quater 2_compressed.pdf4 Dec 2023
Layout approvalFile: PROFORMA B - CONTENTS OF SHEET - UP TO 16TH FLOOR_compressed (1).pdf18 Nov 2023
Layout approvalFile: PROFORMA B - REFUGE FLOOR PLAN - UP TO 16TH FLOOR_compressed.pdf18 Nov 2023
Layout approvalFile: PROFORMA B -STAMP OF APPROVAL OF PLAN - URBAN VILLA - UP TO 16TH FLOOR_compressed.pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: PROFORMA B - CONTENTS OF SHEET - UP TO 16TH FLOOR_compressed (1).pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: PROFORMA B - REFUGE FLOOR PLAN - UP TO 16TH FLOOR_compressed.pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: PROFORMA B -STAMP OF APPROVAL OF PLAN - URBAN VILLA - UP TO 16TH FLOOR_compressed.pdf18 Nov 2023
Layout approvalFile: PROFORMA B - CONTENTS OF SHEET - UP TO 16TH FLOOR_compressed (1).pdf25 Oct 2023
Layout approvalFile: PROFORMA B - CONTENTS OF SHEET - UP TO 16TH FLOOR_compressed (1).pdf25 Oct 2023
Layout approvalFile: PROFORMA B -STAMP OF APPROVAL OF PLAN - URBAN VILLA - UP TO 16TH FLOOR_compressed.pdf25 Oct 2023
Layout approvalFile: PROFORMA B -STAMP OF APPROVAL OF PLAN - URBAN VILLA - UP TO 16TH FLOOR_compressed.pdf25 Oct 2023
Layout approvalFile: PROFORMA B - REFUGE FLOOR PLAN - UP TO 16TH FLOOR_compressed_compressed_compressed (1)_com25 Oct 2023
Copy of Layout Approval (in case of layout)File: PROFORMA B - CONTENTS OF SHEET - UP TO 16TH FLOOR_compressed (1).pdf25 Oct 2023
Copy of Layout Approval (in case of layout)File: PROFORMA B - CONTENTS OF SHEET - UP TO 16TH FLOOR_compressed (1).pdf25 Oct 2023
Copy of Layout Approval (in case of layout)File: PROFORMA B -STAMP OF APPROVAL OF PLAN - URBAN VILLA - UP TO 16TH FLOOR_compressed.pdf25 Oct 2023
Copy of Layout Approval (in case of layout)File: PROFORMA B -STAMP OF APPROVAL OF PLAN - URBAN VILLA - UP TO 16TH FLOOR_compressed.pdf25 Oct 2023
Copy of Layout Approval (in case of layout)File: PROFORMA B - REFUGE FLOOR PLAN - UP TO 16TH FLOOR_compressed_compressed_compressed (1)_com25 Oct 2023
Building plan approvalFile: URBAN LAYOUT.pdf17 Jan 2023
PAN CardFile: YASH INFRA - PAN.pdf17 Jan 2023
Copy of the legal title reportFile: TITLE REPORT URBAN VILLA AS PER RERA FORMAT.pdf17 Jan 2023
Details of encumbrancesFile: FINANCE ENCUMRBRANCE LETTER URBAN VILLA.pdf17 Jan 2023
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMRBRANCE LETTER URBAN VILLA.pdf17 Jan 2023
Details of encumbrances concerned to LegalFile: LEGAL ENCUMRBRANCE LETTER URBAN VILLA.pdf17 Jan 2023
Building Plan Approval (IOD)File: URBAN LAYOUT.pdf17 Jan 2023
Declaration about Commencement CertificateFile: DECLRATION COMMECEMENT CERTIFICATE.pdf17 Jan 2023
Declaration in FORM BFile: Form B - New.pdf17 Jan 2023
Declaration in FORM BFile: FORM B (1).pdf17 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13th SLAB CERTIFICATE.pdf17 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 -ARCHITECT CERTIFICATE for Annx B.pdf17 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2- ENGINEER'S CERTIFICATE for Annx B_Compressed.pdf17 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report.pdf17 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold inventory .pdf17 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Of Interest In other Real Estate Oragnization.pdf17 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA - FORM 5 2018.pdf17 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA form 5 2019_compressed.pdf17 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Form 5 2021 compressed.pdf17 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Form 5 2021 compressed.pdf17 Jan 2023
Proforma of Agreement for saleFile: Allotment Letter 22.pdf17 Jan 2023
Status of ConveyanceFile: URBAN VILLA DEED OF RELEASE 25 NOV 2022_compressed_compressed (1) (1).pdf17 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A.pdf17 Jan 2023
Deviation Report with respect to Allotment letterFile: Deviation Report - allotment letter format -22.pdf17 Jan 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT SALE AGREEMENT URBAN VILLA.pdf17 Jan 2023
PAN CardFile: YASH INFRA - PAN - NEW.pdf27 Dec 2022

How this compares with Thane

78%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 43 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep URBAN Villa on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Louisewadi7,600+ in Thane

2 kmURBAN VillaCompleted 103Lapsed / revoked 65Other 145Dot size: filed unitsN

Filed coordinates, straight-line distance. 313 registered projects within 2 km.

Builder: YASH INFRA

YASH INFRA has 12 registrations on MahaRERA, including NALANDA CHS and SHILPA CHS. Its filings disclose 9 earlier MahaRERA projects: declares 2 of 5 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that URBAN Villa shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if URBAN Villa is delayed beyond 30 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of URBAN Villa?

The registered promoter entity is YASH INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in URBAN Villa?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for URBAN Villa?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at URBAN Villa?

The professionals named in the filing: Architect: InnovativeArchitech; Engineer: Pentacon Structural Consultants Pvt. Ltd.; Chartered Accountant: Aditi A Joshi & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in URBAN Villa?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About URBAN Villa. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save URBAN Villa to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.