YASH INFRA has 12 registrations on MahaRERA, including NALANDA CHS and SHILPA CHS. Its filings disclose 9 earlier MahaRERA projects: declares 2 of 5 past projects completed on time.
Projects by this developer
Showing all 12 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Veer HillsP51700080034 | Shivai Nagar, Thane West, Thane, 400606 | 440 | 3% | 18 Apr 2025 | Registered |
| Veer GalaxyP51700051438 | near vandana depo, Thane, 400602 | 79 | 38% | 14 Jun 2023 | Completed |
| URBAN VillaP51700015488 | Louisewadi, Thane, 400604 | 78 | 78% | 1 Mar 2018 | Registration lapsed |
| Veer DevikaPR1330002600577 | Daulat Nagar, Thane East, Thane, 400603 | 50 | 0% | 29 May 2026 | Registered |
| VEER YASHODEEPP51700079872 | Naupada Thane west, Thane, 400602 | 35 | 0% | 28 Mar 2025 | Registered |
| YASHRAJ PARADISEP51700024174 | SHREE MALANG ROAD RELAX GARDEN NEAR NANDIVALI BUS STOP KALYAN, Thane, 421306 | 2 | 0% | 23 Jan 2020 | Registered |
| MAHALAXMI RESIDENCYP51700050262 | BADLAPUR WEST, Thane, 421503 | - | - | 27 Mar 2023 | Registration lapsed |
| NALANDA CHSP51700007972 | Thane (M Corp.), Thane, 400602 | - | - | 18 Aug 2017 | Registration lapsed |
| Ramleela Co-operative Housing Society LimitedP51700015143 | Near Shiv Mandir, Thane, 400603 | - | - | 2 Feb 2018 | Registration lapsed |
| Satyaneelayam Co Op HSg SocietyP51700049465 | Naupada, Thane, 400602 | - | - | 14 Feb 2023 | Registration lapsed |
| SHILPA CHSP51700009903 | Thane (M Corp.), Thane, 400602 | - | - | 22 Aug 2017 | Completed |
| VIRAJ RESIDENCYP51500053586 | AURANGABAD, Aurangabad, 431007 | - | - | 10 Nov 2023 | Registered |
What this promoter declares as its own experience
YASH INFRA declares experience on 9 earlier projects. 4 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
4 of these declarations can be compared with the dates those projects' own registrations hold. On 2, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. It changes nothing about whether those projects were delivered on time.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| MANJIRI HEIGHTS | 28 Feb 2018 | 30 Jun 2018 | +4 months |
| YASHRAJ HOMES | 1 Jan 2021 | 1 Jun 2022 | +17 months |
| Urban Villa | 31 Dec 2023 | 15 Apr 2023 | On time |
| URBAN VILLA | 30 Apr 2024 | 15 Dec 2024 | +8 months |
| URBAN Villa P51700015488 | 30 Jul 2026 | Not completed yet | Ongoing |
| Veer Galaxy P51700051438 | 30 Jul 2026 | Not completed yet | Ongoing |
| VEER VISHWA | 20 Feb 2027 | 20 Feb 2027 | On time |
| VEER YASHODEEP P51700079872 | 16 Jan 2028 | Not completed yet | Ongoing |
| Veer Hills P51700080034 | 28 Dec 2030 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify YASH INFRA as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AADFY0956G1Z0 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with YASH INFRA?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.