Home / Browse projects / Gandhinagar, Gujarat / Uplands Two

Valid until 30 Jun 2027 Residential/Group Housing project

Uplands Two

By ARVIND SMARTSPACES LIMITED

RG-GJ-17188 · RERA PR/GJ/GANDHINAGAR/KALOL/Ahmedabad Urban Development Authority/MAA06869/A2M/EX2/011026/300627 · Last updated on GujRERA portal: 23 Sep 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Jun 2027Possession promisedmoved 24 months from the original
102 of 171Construction stages doneacross 19 buildings; furthest along: Internal walls, 98%
13 of 67Units unsoldnot recorded sold or booked
Jump to the 64 documents Report an error

Uplands Two is a Residential/Group Housing project by ARVIND SMARTSPACES LIMITED in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL/Ahmedabad Urban Development Authority/MAA06869/A2M/EX2/011026/300627 on 7 Mar 2020. Possession is promised by 30 Jun 2027. The completion date has moved by 24 months from the original filing. 54 of the 67 units on this registration are recorded sold or booked, and 102 of 171 construction stages are filed complete.

At a glance

Project

  • NameUplands Two
  • TypeResidential/Group Housing
  • Location
    • Arvind Uplands Township
    • At Village Namsed and Adhana
    • Village: Nasmed and Adhana
    • Taluko: Kalol
    • NASHMED-ADHANA
    • Kalol
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL/Ahmedabad Urban Development Authority/MAA06869/A2M/EX2/011026/300627
  • ReraGenie IDRG-GJ-17188

Builder

  • NameARVIND SMARTSPACES LIMITED
  • Entity typeCOMPANY
  • Other registrations1 more →

Key dates

this monthRegisteredMar 2020First promiseJun 2025Revised toJun 2027

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2027
  • Registered on7 Mar 2020
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2025)
  • Buildings19 building records
  • Documents filed64 files

Current status

81%54 of 67 units booked
93.6%Of the estimated cost spent so far

Figures as on 23 Sep 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Type A1 (1 villa)---101
Type A5 (1 villa)---101
Type A6 (4 villas)---404
Type A7 (2 villas)---202
Type A8 (1 villa)---101
Type A9 (1 villa)---101
Type A10 (1 villa)---101
Type A11 (1 villa)---101
Type A12 (9 villas)---909
Type B (12 villas)---12012
Type B2 (1 villa)---101
Type B4 (1 villa)---101
Type B5 (7 villas)---707
Type C3 (2 villas)---202
Type C4 (12 villas)---12012
Type C6 (4 villas)---404
Type D2 (1 villa)---101
Type D5 (1 villa)---101
Type D8 (5 villas)---505

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building19

As on 23 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

102 of 171 construction stages are filed complete across 19 buildings. The stage furthest along is Internal walls, at 98%.

Type A1 (1 villa)32%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure45%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing5%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type A5 (1 villa)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type A6 (4 villas)83%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
Type A7 (2 villas)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type A8 (1 villa)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type A9 (1 villa)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type A10 (1 villa)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type A11 (1 villa)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type A12 (9 villas)29%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth60%
Stilt Floor0%
Slabs of Super Structure45%
Internal walls, internal plaster, floorings, doors and windows within flats25%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing15%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type B (12 villas)84%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats98%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%
Type B2 (1 villa)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type B4 (1 villa)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type B5 (7 villas)82%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
Type C3 (2 villas)57%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats35%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing55%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing15%
Type C4 (12 villas)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type C6 (4 villas)23%
ActivityProgress
Excavation80%
Podiums (if any)Not applicable
Plinth65%
Stilt Floor0%
Slabs of Super Structure35%
Internal walls, internal plaster, floorings, doors and windows within flats15%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type D2 (1 villa)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type D5 (1 villa)23%
ActivityProgress
Excavation80%
Podiums (if any)Not applicable
Plinth65%
Stilt Floor0%
Slabs of Super Structure35%
Internal walls, internal plaster, floorings, doors and windows within flats15%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type D8 (5 villas)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 23 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes85%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsYes80%
Landscaping and tree plantingYes80%
Street lightingYes70%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes70%
Solid waste management and disposalYes55%
Water conservation, rain water harvestingYes70%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes75%
Fire fightingYes70%
Drinking water facilitiesYes65%
Emergency evacuationYes80%
Use of renewable energyYes55%
SecurityYes76%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area537,856 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 64.25 cr
Cost incurredRs 60.15 cr
Spent of the estimate93.62%
BuildingWingEstimatedIncurred
Type A12 (9 villas)NARs 11.70 crRs 10.00 cr
Type B (12 villas)NARs 9.95 crRs 9.80 cr
Type C4 (12 villas)NARs 9.12 crRs 9.12 cr
Type B5 (7 villas)NARs 6.20 crRs 6.09 cr
Type A6 (4 villas)NARs 5.54 crRs 5.50 cr
Type D8 (5 villas)NARs 3.17 crRs 3.17 cr
Type C6 (4 villas)NARs 3.04 crRs 1.90 cr
Type A7 (2 villas)NARs 2.95 crRs 2.95 cr
Type C3 (2 villas)NARs 1.52 crRs 1.50 cr
Type A9 (1 villa)NARs 1.39 crRs 1.39 cr
Type A1 (1 villa)NARs 1.32 crRs 80.23 lakh
Type A11 (1 villa)NARs 1.30 crRs 1.30 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/KALOL/Ahmedabad Urban Development Authority/MAA06869/A2M/EX1/150925/300626Applied Mar 2025; approved Sep 2025
PR/GJ/GANDHINAGAR/KALOL/Ahmedabad Urban Development Authority/MAA06869/A2M/EX2/011026/300627Applied May 2026; approved Oct 2026

Documents filed64

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL/Ahmedabad Urban Development Authority/MAA06869/A2M/EX2/011026/300627 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)23 Sep 2026
Engineer's certificate (Form 2)23 Sep 2026
Engineer's certificate annexure23 Sep 2026
Accountant's certificate (Form 3)23 Sep 2026
Site photograph, Type A1 (1 villa)23 Sep 2026
Site photograph, Type A5 (1 villa)23 Sep 2026
Site photograph, Type A6 (4 villas)23 Sep 2026
Site photograph, Type A7 (2 villas)23 Sep 2026
Site photograph, Type A8 (1 villa)23 Sep 2026
Site photograph, Type A9 (1 villa)23 Sep 2026
Site photograph, Type A10 (1 villa)23 Sep 2026
Site photograph, Type A11 (1 villa)23 Sep 2026
Site photograph, Type A12 (9 villas)23 Sep 2026
Site photograph, Type B (12 villas)23 Sep 2026
Site photograph, Type B2 (1 villa)23 Sep 2026
Site photograph, Type B4 (1 villa)23 Sep 2026
Site photograph, Type B5 (7 villas)23 Sep 2026
Site photograph, Type C3 (2 villas)23 Sep 2026
Site photograph, Type C4 (12 villas)23 Sep 2026
Site photograph, Type C6 (4 villas)23 Sep 2026
Site photograph, Type D2 (1 villa)23 Sep 2026
Site photograph, Type D5 (1 villa)23 Sep 2026
Site photograph, Type D8 (5 villas)23 Sep 2026
RERA registration certificate7 Mar 2020
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

81%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 24 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep Uplands Two on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near NASHMED-ADHANA1,600+ in Gandhinagar

Builder: ARVIND SMARTSPACES LIMITED

ARVIND SMARTSPACES LIMITED has 2 registrations on GujRERA, including Uplands Two and Uplands Three. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if Uplands Two is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Uplands Two?

The registered promoter entity is ARVIND SMARTSPACES LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Uplands Two?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Uplands Two?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Uplands Two. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Uplands Two to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.