Home / Browse projects / Pune, Maharashtra / Uma Residency

Registration lapsed No litigation declared Others project

Uma Residency

By Dipak Babanrao Kavitake

RG-MH-09370 · RERA P52100002474 · Last updated on MahaRERA portal: 10 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 9 months past the filed date
  • Completion date moved by 43 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2026Possession promised9 months past this date
3 of 33Construction stages doneacross 3 buildings; furthest along: Staircases, 98%
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

Uma Residency is a Others project by Dipak Babanrao Kavitake in Pune, Maharashtra, registered with MahaRERA as P52100002474 on 1 Aug 2017. Possession was promised by 31 Jan 2026 and is now 9 months past that date. The completion date has moved by 43 months from the original filing.

At a glance

Project

  • NameUma Residency
  • TypeOthers
  • Location
    • Sahakar Chowk
    • Daund
    • Daund (CT)
    • Pune
    • 413801
  • Pincode413801
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002474
  • ReraGenie IDRG-MH-09370

Builder

  • NameDipak Babanrao Kavitake
  • Entity typeIndividual
  • GSTIN27AFJPK6100P1Z6
  • Declared earlier projects1 →

Key dates

9 months past promisethis monthRegisteredAug 2017First promiseJun 2022Revised toJan 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Aug 2017
  • Promised completion31 Jan 2026
  • Revised completionRevised to 31 Jan 2026 (originally 12 Jun 2022)
  • Buildings3 building records
  • Documents filed71 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA80000
B WINGNA80000
UMANA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 10 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 98%.

A WING58%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
B WING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
UMA0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes95%
Street LightingYes30%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes90%
Open ParkingYes50%

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered31
Open Space20
BuildingClosed/CoveredOpen SpaceTotal
A WING101525
B WING21526

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,800 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Arvind R WagajkarDaund (CT)Pune
Vaibhav Arvind WagajkarDaund (CT)Pune

Approvals and building plan

Sanctioning authorityKrishna Constructions
Permissible FSI5166.0
Proposed, not sanctioned5,166 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchS No 34/35 Parvati Darshan Swargate Pune 411009

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Dipak Babanrao Kavitake-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011370Jun 2022 → Jun 2023

Reason as filed by the promoterThere is no single agreement executed with any client till date, because there is very few response from customers, therefore we mutually decided to extend the project completion date to avoid any further disputes. Accordingly we have registered a correction deed for only project completion period. Rest of the part of agreement and all details of project remains same.

EXT52100024121Jun 2022 → Jan 2026

Reason as filed by the promoterTwo Buildings are in our Project Bldg.-A & Bldg.-B. In this project, Bldg-A is almost about to completion level including all required services & amenities. As our project is in rural area, client response is very slow for our project. So this is the main reason of delay of for project completion. We are trying our best possible to complete the project at the earliest, by introducing our own funds.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Nov 2022

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Disclosure Sold Unsold Units.pdf10 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 dt 09012025.pdf10 Jan 2025
Declaration in FORM BFile: Declaration FORM B 25112024.pdf25 Nov 2024
Certificates of CA (Form 3)File: FORM 3 231124.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2A 111124.pdf25 Nov 2024
Proforma of Agreement for saleFile: DRAFT OF AGREEMENT.pdf25 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 231124.pdf25 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure Sold Unsold Units 21112024.pdf21 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 1-11-24 R.pdf21 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Architect Certificate FY 2023 2024.pdf10 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold Inventory.pdf10 Jul 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure Of Interest in other Real Estate Orgnanizations.pdf10 Jul 2024
Certificates of CA (Form 3)File: Form 3 CA CETIFICATE July 2024.pdf10 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA ANNUAL REPORT ON STATEMENT OF ACCOUNTS FY2022 2023.pdf10 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA ANNUAL REPORT ON STATEMENT OF ACCOUNTS FY2023 2024.pdf10 Jul 2024
Other - TechnicalFile: Reason of extention.pdf10 Jul 2024
Other - TechnicalFile: Reason of extention.pdf10 Jul 2024
Other - TechnicalFile: Actual site Photos.pdf10 Jul 2024
Other - TechnicalFile: Daund photo A wing.pdf10 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate FY20222023.pdf8 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineers Certificate FY 2023 2024.pdf8 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold Inventory.pdf8 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Of Interest in other Real Estate Orgnanizations.pdf8 Jul 2024
Details of encumbrances concerned to FinanceFile: Declaration-Non Encumbrance.pdf11 Nov 2022
Details of encumbrances concerned to LegalFile: Declaration-Non Encumbrance.pdf11 Nov 2022
Declaration about Commencement CertificateFile: PLINTH COMPLETION - DAUND MUNICIPAL COUNCIL.pdf11 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form2-A.pdf11 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate Form2-A.pdf11 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate Form2-A.pdf11 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Certificate Form2-A.pdf11 Nov 2022
Disclosure of sold/ booked inventoryFile: Declaration Under Circular-29.pdf11 Nov 2022
CERSAI detailsFile: Declaration Under Circular-32.pdf11 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA Certificate-Form 5.pdf11 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Certificate-Form 5.pdf11 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Certificate-Form 5.pdf11 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Certificate-Form 5.pdf11 Nov 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PLINTH COMPLETION - DAUND MUNICIPAL COUNCIL.pdf11 Nov 2022
Certificates of CA (Form 5)File: FORM5.pdf31 Dec 2018
Certificates of CA (Form 5)File: FORM 5.pdf19 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: REVISED COMMENCEMENT.pdf9 Apr 2018
Proforma of Allotment letterFile: DRAFT OF ALLOTMENT LETTER.pdf9 Apr 2018
Building plan approvalFile: PLOT LAYOUT DRAWING.pdf7 Apr 2018
Building plan approvalFile: 1ST, 3RD, 5TH, 7TH SLAB DRAWING-min.pdf7 Apr 2018
Building plan approvalFile: 2ND, 4TH, 6TH SLAB DRAWING.pdf7 Apr 2018
Building plan approvalFile: ELEVATION DRAWING.pdf7 Apr 2018
Building plan approvalFile: 2ND, 4TH, 6TH SLAB DRAWING.pdf7 Apr 2018
Building plan approvalFile: 1ST, 3RD, 5TH, 7TH SLAB DRAWING-min.pdf7 Apr 2018
Building Plan Approval (IOD)File: 2ND, 4TH, 6TH SLAB DRAWING.pdf7 Apr 2018
Building Plan Approval (IOD)File: 1ST, 3RD, 5TH, 7TH SLAB DRAWING-min.pdf7 Apr 2018
Building Plan Approval (IOD)File: PLOT LAYOUT DRAWING.pdf7 Apr 2018
Building Plan Approval (IOD)File: 1ST, 3RD, 5TH, 7TH SLAB DRAWING-min.pdf7 Apr 2018
Building Plan Approval (IOD)File: 2ND, 4TH, 6TH SLAB DRAWING.pdf7 Apr 2018
Building Plan Approval (IOD)File: ELEVATION DRAWING.pdf7 Apr 2018
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf7 Apr 2018
Proforma of Allotment letterFile: AGREEMENT DRAFT.pdf7 Apr 2018
Copy of the legal title reportFile: SEARCH REPORT.pdf27 Jul 2017
Proforma of Allotment letterFile: DRAFT OF ALLOTMENT LETTER.PDF27 Jul 2017
Proforma of Allotment letterFile: DRAFT OF AGREEMENT.pdf27 Jul 2017
Details of encumbrancesFile: ENCUMBRANCES CERTIFICATE.pdf26 Jul 2017
Declaration in FORM BFile: FORM B.pdf26 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE-FORM 3.pdf25 Jul 2017
Building plan approvalFile: RES BLDG 1ST AND 3RD FLOOR PLAN.pdf17 Jul 2017
Building plan approvalFile: RESD BLDG PARKING, 2ND AND 4TH FLOOR PLAN.pdf17 Jul 2017
Building plan approvalFile: COMMERICAL BUILDING PLAN.pdf17 Jul 2017
Layout approvalFile: LAYOUT PLAN.pdf17 Jul 2017
PAN CardFile: PAN CARD.pdf17 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf17 Jul 2017
Building Plan Approval (IOD)File: RES BLDG 1ST AND 3RD FLOOR PLAN.pdf17 Jul 2017
Building Plan Approval (IOD)File: RESD BLDG PARKING, 2ND AND 4TH FLOOR PLAN.pdf17 Jul 2017
Building Plan Approval (IOD)File: COMMERICAL BUILDING PLAN.pdf17 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIIFICATE.pdf17 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Shalini VillaS.No 65, Plot No. 18, Bhadkamkar Nagar, Phaltan, Dist- Satara16CompletedMay 2018Late, May 2024

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 43 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Uma Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Daund13,700+ in Pune

2 kmUma ResidencyCompleted 16Lapsed / revoked 5Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: Dipak Babanrao Kavitake

Dipak Babanrao Kavitake has 1 registration on MahaRERA, including Uma Residency. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Uma Residency shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Uma Residency is delayed beyond 31 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Uma Residency?

The registered promoter entity is Dipak Babanrao Kavitake, an individual as per the filing. Its GSTIN 27AFJPK6100P1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Uma Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Uma Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Uma Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Uma Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Uma Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.