Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedmoved 24 months from the original
0 of 77Construction stages doneacross 7 buildings; furthest along: Excavation, 0%
79 of 177Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

R CITY is a Others project by REVA CONSTRUCTION AND DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100027362 on 6 Dec 2020. Possession is promised by 31 Mar 2028. The completion date has moved by 24 months from the original filing. 98 of the 177 units on this registration are recorded sold or booked, and 0 of 77 construction stages are filed complete.

At a glance

Project

  • NameR CITY
  • TypeOthers
  • Location
    • GOPALWADI
    • DAUND
    • Daund (M Cl)
    • Pune
    • 413801
  • Pincode413801
  • RERA no.P52100027362
  • ReraGenie IDRG-MH-16898

Builder

  • NameREVA CONSTRUCTION AND DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAYFR2402F1Z3
  • PartnersYOGESH GORAKH RANDHAVE, BHAUSAHEB BAPU RANDHAVE

Key dates

this monthRegisteredDec 2020First promiseMar 2026Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Dec 2020
  • Promised completion31 Mar 2028
  • Revised completionRevised to 31 Mar 2028 (originally 30 Mar 2026)
  • Buildings7 building records
  • Documents filed76 files

Current status

55%98 of 177 units booked
78.5%Work done, per cost certificate

Figures as on 5 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
R CITY LowergroundNA5556121177
R CITY GroundfloorNA50000
R CITY Frist FloorNA50000
R CITY Secound floorNA50000
R CITY Third FloorNA50000
0NA00000
0NA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Excavation, at 0%.

R CITY Lowerground0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
R CITY Groundfloor0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
R CITY Frist Floor0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
R CITY Secound floor0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
R CITY Third Floor0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
00%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
00%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership11

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners11
LandownerVillageDistrict
POPAT BAPU RANDHAVEGopalwadiPune
BHAUSO BAPU RANDHAVEGopalwadiPune
HARIBHAU BAPU RANDHAVEGopalwadiPune
GORAKH BANDU RANDHAVEDaund (M Cl)Pune
MADHUKAR BANDU RANDHAVEGopalwadiPune
RAMDAS BANDU RANDHAVEGopalwadiPune
TATYA BANDU RANDHAVEGopalwadiPune
SAMPAT BANDU RANDHAVEGopalwadiPune
LAKHAN SURESH RANDHAVEGopalwadiPune
SHANKAR BANDU RANDHAVEGopalwadiPune
REVA CONSTRUCTION AND DEVLOPERSGopalwadiPune

Approvals and building plan

Sanctioning authorityDaund Nagarparishad, Daund
Permissible FSI15870.09
Proposed, not sanctioned8,206 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCITY CENTRAL BUILDING SAHAKAR
Estimated costRs 24.83 cr
Cost incurredRs 19.50 cr
Work done78.54%
BuildingWingEstimatedIncurred
R CITY LowergroundNARs 24.83 crRs 19.50 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAHENDRA M BHAONGLE
EngineerMAHENDRA M BHAONGLE
Chartered AccountantCA NAGNATH S JADHAV
Chartered AccountantVikas Vyas
PartnerRole in project
REVA CONSTRUCTION AND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA05052620834Mar 2026 → Mar 2028

Reason as filed by the promoterWe hereby request an extension of the project timeline under RERA due to unforeseen delays caused by a shortage of both skilled labour and essential construction materials. Over the past few months, our project has faced significant disruptions in workforce availability, which has slowed down on-site progress. Additionally, the supply chain for critical raw materials such as cement and steel has been inconsistent, leading to delays in procurement and execution of key construction activities. These challenges are beyond our control and have impacted our ability to meet the originally committed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Nov 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Architect Certificate _31-12-2025.pdf5 May 2026
Withdrawal Update Form 2File: FORM 2 Engineer certificate 31-12-2025.pdf5 May 2026
Withdrawal Update Form 3File: FORM - 3 31-12-2025.pdf5 May 2026
Withdrawal Update Form 1File: FORM 1 Architect Certificate _31-12-2025.pdf29 Apr 2026
Withdrawal Update Form 2File: FORM 2 Engineer certificate 31-12-2025.pdf29 Apr 2026
Withdrawal Update Form 3File: FORM - 3 31-12-2025.pdf29 Apr 2026
Form 1File: FORM 1 Architect Certificate _31-03-2025.pdf30 Mar 2026
Form 2File: FORM 2 Engineer certificate 31-03-2025.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - 31-03-2025.pdf30 Mar 2026
Form 3File: FORM -3 31-03-2025.pdf30 Mar 2026
Form 2File: FORM 2 Engineer certificate 30-06-2025.pdf30 Mar 2026
Form 1File: FORM 1 Architect Certificate _30-06-2025.pdf30 Mar 2026
Form 3File: FORM - 3 30-06-2025.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - 30-06-2025.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - 30-9-2025.pdf30 Mar 2026
Form 1File: FORM 1 Architect Certificate _30-09-2025.pdf30 Mar 2026
Form 2File: FORM 2 Engineer certificate 30-09-2025.pdf30 Mar 2026
Form 3File: FORM - 3 30-09-2025.pdf30 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A - FY 2024-25.pdf30 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 - FY 2024-25.pdf30 Mar 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE.pdf9 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 UPLOAD.pdf9 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEEAR CERTIFICATE.pdf9 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021-2022.pdf9 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-2023.pdf9 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 2023-2024.pdf9 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FROM 5.pdf9 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 31 Mar 2023.pdf15 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022-23.pdf15 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020-21.PDF19 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 2021-22.PDF19 Jul 2023
Declaration about Commencement CertificateFile: JUNE 21.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MARCH 21.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JUNE 21.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SEP 21.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DEC 22.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MARCH 22.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JUNE 22.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SEP 22.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DEC 22.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MARCH 21.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JUNE 21.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SEP 21.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DEC 21.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MARCH 22.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SEP 21.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DEC 21.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MARCH 22.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JUNE 22.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SEP 22.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DEC 22.pdf11 Jul 2023
Proforma of Agreement for saleFile: New draft of R city.pdf11 Jul 2023
OtherFile: deed.pdf4 Dec 2020
Building plan approvalFile: lower ground floor.pdf27 Nov 2020
Building plan approvalFile: ground floor.pdf27 Nov 2020
Building plan approvalFile: Frist Floor.pdf27 Nov 2020
Building plan approvalFile: Second Floor.pdf27 Nov 2020
Building plan approvalFile: third floor.pdf27 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: lower ground floor.pdf27 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: ground floor.pdf27 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Frist Floor.pdf27 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Second Floor.pdf27 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: third floor.pdf27 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf27 Nov 2020
Proforma of Allotment letterFile: PROFARMA LETTERR.pdf27 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: COMEENCMENT CERTIFICATE.pdf26 Nov 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERTIFATE.pdf26 Nov 2020
OtherFile: leteer of authority.pdf26 Nov 2020
Details of encumbrancesFile: encumberance certificate.pdf24 Nov 2020
Declaration in FORM BFile: form b_compressed (1).pdf24 Nov 2020
Layout approvalFile: NA ORDER RESIZE.pdf21 Nov 2020
Copy of Layout Approval (in case of layout)File: NA ORDER RESIZE.pdf21 Nov 2020
PAN CardFile: Firm Pan Card.pdf19 Nov 2020
Copy of the legal title reportFile: SEARCH REPORT RESIZE.pdf19 Nov 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf19 Nov 2020
Proforma of Allotment letterFile: agreement of sale.pdf19 Nov 2020

How this compares with Pune

55%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep R CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DAUND13,700+ in Pune

Builder: REVA CONSTRUCTION AND DEVELOPERS

REVA CONSTRUCTION AND DEVELOPERS has 1 registration on MahaRERA, including R CITY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if R CITY is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of R CITY?

The registered promoter entity is REVA CONSTRUCTION AND DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAYFR2402F1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in R CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for R CITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at R CITY?

The professionals named in the filing: Architect: MAHENDRA M BHAONGLE; Engineer: MAHENDRA M BHAONGLE; Chartered Accountant: CA NAGNATH S JADHAV; Chartered Accountant: Vikas Vyas. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in R CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About R CITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save R CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.